Compute the correct variances: budgeted sales $307 000: actual sales $298 000. actual direct labour $60 000: budgeted direct labour $63 000.
A) Sales variance $9000 F: direct labour variance $3000 F
B) Sales variance $9000 F: direct labour variance $3000 U
C) Sales variance $9000 U: direct labour variance $3000 F
D) Sales variance $9000 U: direct labour variance $3000 U
Correct Answer:
Verified
Q37: A variable costing income statement is the
Q38: Department Z has a gross profit of
Q39: In a decision relating to the possible
Q40: The expenses that will continue to exist
Q41: Anniversary Roses uses a special mix of
Q43: Which department is typically responsible for direct
Q44: Which of these is not an engineering
Q45: The fixed budget performance report of Millar
Q46: How many of these are considered
Q47: The performance standard that is usually considered
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents