If Ev = $500,ac = $450,pv = $475; Cpi =

Question 40
Multiple Choice

If EV = $500,AC = $450,PV = $475; CPI = __________. A)1)05 B)1)11 C))95 D))90

Related questions
Q 41
In earned value analysis,(CPI)(SPI)= __________. A)CV B)TPI C)CSI D)SV
Q 42
If CSI is less than 1,it is indicative of a(n)__________. A)problem B)good project C)efficient project D)budget error
Q 43
Conceptually,EAC represents the amount spent to date plus __________. A)the delay costs B)BAC C)CV D)ETC