Top management has put together a chart that lists entire departments on the vertical axis and time on the horizontal axis. This allows managers to schedule capacity by work areas. This is an example of which resource allocation technique?
A) Gantt chart
B) PERT network
C) load chart
D) linear program
E) quantitative forecast