Service Management

Business

Quiz 15 :

Managing Projects

Quiz 15 :

Managing Projects

Question Type
search
arrow
The following activities have been identified by a consulting firm that is developing an information system for an insurance firm to make a transition to a "paperless" organization: img a. Draw the project network showing the activities with their expected times. b. What is the critical path and the expected duration of the project? c. What is the probability of completing the project within 2 years?
Free
Essay
Answer:

Answer:

PERT and CPM:
In order to keep track of the different activities of a project, the following project evaluation tools have to be used. The most predominantly used techniques are PERT and CPM. It is used in project planning and coordination as well.
Program evaluation and review technique (PERT) is used to plan, schedule and control different projects such as construction works, design and installation of systems, maintenance work, and research and development processes. It is useful for planning for large and complicated projects.
Consider the following data showing optimistic, most probable and pessimistic time estimates for different activities:
img a) Project network and Expected duration:
Determine the critical activities of the project by the following steps as shown below:
Step 1 : Determine the expected (estimated) time for activity using the below mentioned formula:
img …… (1)
Here,
img refers to the optimistic time estimate
img refers to the most likely time estimate
img refers to the pessimistic time estimate.
Calculate expected time in the excel spread sheet with the help of the above formula as shown below:
img Step 2: Draw a network diagram for the data using the expected time of each activity as shown below:
img Step 3: Now, calculate the length of each path by adding the expected time required for completion of each activity present in a path.
img The path having the maximum completion time is considered as the critical path. From the above calculation it is clear that path B-E-H has the maximum completion time i.e. 16 months.
Therefore, path B-E-H is considered to be the critical path and the critical activities are B, E, and H.
To identify the critical path of the project, the longest path has to be selected and the path should have no slack. In order to do this, the following diagram is presented. Each circle or node represents an event. An activity occurs between two events. The network diagram is drawn accordingly keeping the predecessors and successors of each activity in mind. Each activity is denoted by an arrow and the number in the brackets is the time taken by each activity. The legend of the diagram is given as follows:
img Each node is then divided into three parts. The upper half of the node denotes the activity and the time taken to complete the event is in brackets. The lower half is sub-divided into two parts. The left hand side of the lower half of the node is the Earliest Start Time ( ES ) and the right hand side is the Latest Finish Time ( LF ). The calculation of ES for all the activities is done from left to right of the network diagram. This is known as Forward Pass. In this, the time taken by each activity is added to the Earliest Start time of each activity. The Earliest Start time from start is considered to be zero. The time taken by activity A is 6 months so the Earliest Start time for activity A is 6 months (i.e.
img ). In this manner, the Earliest Start Time is calculated for all the events. In case of multiple predecessors in forward pass, the highest value has to be considered as the Earliest Start time of the event. For example, in activity H, the Earliest Start Time can be
img (or)
img or
img . The highest value should be considered i.e. 16 months.
On reaching the last event, the calculation of the Latest Finish time of each event has to be done. This is done from right to left. This is known as backward pass. The Earliest Start time of the last event is equal to the Latest Finish time of the last event. The Latest Finish time is then calculated by subtracting the time taken by each activity. For activity B, the Latest Finish time is either
img (or)
img . In backward pass, in case of multiple predecessors, the lowest value has to be taken. Therefore, activity B will take 2 months. In this way, the calculation should be done from activity J to start. The Earliest Start time and the Latest Finish time should be equal to each other at the beginning and end of the network diagram, respectively.
img The critical path is shown by blue arrows as follows:
img The scheduling time for each activity is calculated as follows:
img Step 1: List down the different activities in column A, time taken in each activity in column B and the immediate predecessor for each activity in column C.
Step 2 : In the column D, write the Earliest Start Time ( ES) of each activity. If an activity has multiple predecessors, then
img .  The Earliest Start time for the subsequent activities will be the Earliest Finish time of the preceding activity. In case there are too many preceding activities, use the finish time of the activity which ends after all the others.
Step 3 : In column E, add the time taken in each activity with ES to get the Earliest Finish Time ( EF). The formula used is
img Step 4 : In column G, write the Latest Finish Time of each activity ( LF). If an activity has multiple successors,
img . In case of multiple successors, use the smallest late start time from among all of the activities, as the latest finish time.
Step 5 : In column F, subtract the time taken in each activity from LF of each activity and obtain LS. The formula used is
img Step 6: In column H, subtract ES from LS and obtain the Total Slack value ( TS ). The formula used is
img From the scheduling time for each activity also it can be observed that the activities which have slack time as zero are B, D, E and H. Thus, from this also it can be justified that the critical path will have the activities B, E and H.
c) Determine the probability for completion of the project within 2 years:
Step 1: Determine the variance for activity by using the formula as shown below:
img Calculate Variance using the above formula in the excel spread sheet as shown below:
img Step 2: Now, calculate the activity variance along critical path by adding the variance of each activity present in the path.
img Variance is
img Step 3: Determine the standard deviation of the expected time for each path by substituting variance in the formula as shown below:
img Standard deviation is
img Step 4: Calculate the probability for completion of the project before 2 years by substituting the values of standard deviation, specified time and path mean in the formulas shown below:
img Substituting the values in the formula:
img Step 5: Now, determine the probability for z value using NORMSDIST (4.5756) formula in an excel spread sheet as shown below:
img Therefore, the probability for completing the project i.e. P (z) before 2years or 24 months is
img (or)
img

Tags
Choose question tag
close menu
arrow
Illustrate the four stages of team building from your own experience.
Free
Essay
Answer:

Answer:

Project:
The project is an organized approach that is undertaken to plan and achieve a particular aim. These are a set of activities that have a definite beginning and end. They have a well-defined scope and utilize resources. A project is unique in nature and it has a specific set of operations designed for achieving the goal.
A project cannot be carried out individually. There is requirement of a number of people for carrying out the different activities of the project. So, there is a need for project team.
Four stages of Team building:
In order to achieve the objective of a project, the members of the project will have to come together and work as a team. The four stages of team building as given by B.W. Tuckman are: Forming, Storming, Norming and Performing.
Forming: In this stage the team members get introduced to each other. They are excited about the project but are not clear about their role in the project. The team is given instructions by the project manager and the objective, scope and schedule of the work has to be prepared accordingly.
Storming: This stage is characterized by some dissatisfaction in the minds of the team members. This is due to the project constraints and the dependence on the instructions given by the project manager. The project manager has to be able to handle and resolve the conflict as well as provide a good environment for the project work to progress.
Norming: This stage begins with the development of cohesion in the team members of the company. The decision making power of the project shifts from the project manager to the project team. The work performance and the productivity of the firm will improve due to the good and friendly environment at workplace. The project manager now plays only a supportive role.
Performing: This stage is the final stage in the project team development. The project team collaborates with each member of the team and accomplishes the goal. The project manager only monitors the performance of the team and its progress with respect to the time, cost, and plan of the project. If the project fails then the manager undertakes corrective emasures that should be implemented.

Tags
Choose question tag
close menu
arrow
The following activities are required for completing a project: img a. Draw a network diagram of this project showing the activities and their expected duration times. b. What is the critical path and the expected completion time of the project? c. What is the probability of completing the project in 41 days or less?
Free
Essay
Answer:

Answer:

PERT and CPM:
In order to keep track of the different activities of a project, the following project evaluation tools have to be used. The most predominantly used techniques are PERT and CPM. It is used in project planning and coordination as well.
Program evaluation and review technique (PERT) is used to plan, schedule and control different projects such as construction works, design and installation of systems, maintenance work, and research and development processes. It is useful for planning for large and complicated projects.
Consider the following data showing optimistic, most probable and pessimistic time estimates for different activities:
img a) Project network and Expected duration :
Determine the critical activities of the project by the following steps as shown below:
Step 1 : Determine the expected (estimated) time for activity using the below mentioned formula:
img …… (1)
Here,
img refers to the optimistic time estimate
img refers to the most likely time estimate
img refers to the pessimistic time estimate.
Calculate expected time in the excel spread sheet with the help of the above formula as shown below:
img Step 2: Draw a network diagram for the data using the expected time of each activity as shown below:
img b) Critical Path and Expected completion time:
Step 1: Calculate the length of each path by adding the expected time required for completion of each activity present in a path.
img The path having the maximum completion time is considered as the critical path. From the above calculation it is clear that path A-C-E-H-J has the maximum completion time i.e. 37 days. Therefore, path A-C-E-H-J is considered to be the critical path and the critical activities are A, C, E, H and J.
To identify the critical path of the project, the longest path has to be selected and the path should have no slack. In order to do this, the following diagram is presented. Each circle or node represents an event. An activity occurs between two events. The network diagram is drawn accordingly keeping the predecessors and successors of each activity in mind. Each activity is denoted by an arrow and the number in the brackets is the time taken by each activity. The legend of the diagram is given as follows:
img Each node is then divided into three parts. The upper half of the node denotes the activity and the time taken to complete the event is in brackets. The lower half is sub-divided into two parts. The left hand side of the lower half of the node is the Earliest Start Time ( ES ) and the right hand side is the Latest Finish Time ( LF ). The calculation of ES for all the activities is done from left to right of the network diagram. This is known as Forward Pass. In this, the time taken by each activity is added to the Earliest Start time of each activity. The Earliest Start time from start is considered to be zero. The time taken by activity A is 6 months so the Earliest Start time for activity A is 7 days (i.e.
img ). In this manner, the Earliest Start Time is calculated for all the events. In case of multiple predecessors in forward pass, the highest value has to be considered as the Earliest Start time of the event. For example, in activity H, the Earliest Start Time can be
img (or)
img . The highest value should be considered i.e. 36 days.
On reaching the last event, the calculation of the Latest Finish time of each event has to be done. This is done from right to left. This is known as backward pass. The Earliest Start time of the last
event is equal to the Latest Finish time of the last event. The Latest Finish time is then calculated by subtracting the time taken by each activity. In backward pass, in case of multiple predecessors, the lowest value has to be taken. Therefore, activity B will take 2 months. In this way, the calculation should be done from activity J to start. The Earliest Start time and the Latest Finish time should be equal to each other at the beginning and end of the network diagram, respectively.
img The critical path is shown in blue arrows as follows:
img The scheduling time for each activity is calculated as follows:
img Step 1 : List down the different activities in column A, time taken in each activity in column B and the immediate predecessor for each activity in column C.
Step 2 : In the column D, write the Earliest Start Time ( ES) of each activity. If an activity has multiple predecessors, then
img .  The Earliest Start time for the subsequent activities will be the Earliest Finish time of the preceding activity. In case there are too many preceding activities, use the finish time of the activity which ends after all the others.
Step 3 : In column E, add the time taken in each activity with ES to get the Earliest Finish Time ( EF). The formula used is
img Step 4 : In column G, write the Latest Finish Time of each activity ( LF). If an activity has multiple successors,
img . In case of multiple successors, use the smallest late start time from among all of the activities, as the latest finish time.
Step 5 : In column F, subtract the time taken in each activity from LF of each activity and obtain LS. The formula used is
img Step 6: In column H, subtract ES from LS and obtain the Total Slack value ( TS ). The formula used is
img From the scheduling time for each activity also it can be observed that the activities which have slack time as zero are A, C, E, H and J. Thus, from this also it can be justified that the critical path will have the activities A, C, E, H and J. The expected project time is 37 days on the critical path.
c) Determine the probability for completion of the project within 41days or less:
Step 1: Determine the variance for activity by using the formula as shown below:
img Calculate Variance using the above formula in the excel spread sheet as shown below:
img Step 2: Now, calculate the activity variance along critical path by adding the variance of each activity present in the path.
img Variance is
img Step 3: Determine the standard deviation of the expected time for each path by substituting variance in the formula as shown below:
img Standard deviation is
img Step 4: Calculate the probability for completion of the project before 41 days by substituting the values of standard deviation, specified time and path mean in the formulas shown below:
img Substituting the values in the formula:
img Step 5: Now, determine the probability for z value using NORMSDIST (0.8) formula in an excel spread sheet as shown below:
img Therefore, the probability for completing the project i.e. P (z) before 41 days is
img (or)
img

Tags
Choose question tag
close menu
arrow
A consulting firm is planning a reengineering project for a client. The following activities and time estimates have been identified: img a. Draw a project network diagram. b. Calculate the scheduling times and total slack for each activity. c. List the critical path activities and project duration. d. Assuming that one worker is required for each activity, prepare a resource-leveled schedule. What is the maximum number of workers required to finish the project on time?
Essay
Answer:
Tags
Choose question tag
close menu
arrow
Assume that you are part of the management staff whose task is to develop this sketch plan. Using Microsoft Project for Windows, develop the PERT network as outlined above, identify the critical path, and determine the expected time to reach basic operational status at the new facility.
Essay
Answer:
Tags
Choose question tag
close menu
arrow
2. The elapsed time for delivery of the hardware is estimated at 90 days. Would the project completion time be affected if delivery of the hardware were delayed by 30 days? Would the critical path change ?
Essay
Answer:
Tags
Choose question tag
close menu
arrow
A simple network consisting of four activities has the following network diagram: img The cost/time relationships for the activities are shown in the table below: img For example, if completed in 5 weeks, activity A would require $85,000, and if completed in 10 weeks, it would require $70,000. a. What would be the minimum cost of completing this project in 20 weeks? b. If the desired completion date is 33 weeks and the profit markup is 20 percent above cost, what should be the bid price for this project?
Essay
Answer:
Tags
Choose question tag
close menu
arrow
Are Gantt charts still viable project management tools? Explain.
Essay
Answer:
Tags
Choose question tag
close menu
arrow
Using the original network and critical path, what strategies could management consider to complete the project on time if activity B were delayed by several weeks ?
Essay
Answer:
Tags
Choose question tag
close menu
arrow
You have been asked to plan the following covert operation for the AIC: img a. Draw a network diagram for this project. b. Calculate the expected time and variance for each activity. c. Determine the critical path and the expected project completion time. d. What is the probability of the project taking more than 25 days to complete?
Essay
Answer:
Tags
Choose question tag
close menu
arrow
Give an example that demonstrates the trade-off inherent in projects between cost, time, and performance.
Essay
Answer:
Tags
Choose question tag
close menu
arrow
Slippery Rock College is planning a basketball tournament. The following information has been collected on each activity in the project: img a. Draw a network diagram of this project, and label the activities and events. b. Calculate the total slack and scheduling times for all activities. What is the critical path? c. When should team selection begin if the tournament is scheduled to start on the morning of December 27? (Include Saturday and Sunday as working days.)
Essay
Answer:
Tags
Choose question tag
close menu
arrow
Discuss the difference between time variance, cost variance, and schedule variance.
Essay
Answer:
Tags
Choose question tag
close menu
arrow
The project network and table below show the expected number of weeks to complete a series of activities and the corresponding variances: img img a. Determine the critical path and the earliest expected completion time. b. What is the probability of completing the project in 24 weeks or less?
Essay
Answer:
Tags
Choose question tag
close menu
arrow
Explain why the PERT estimate of expected project duration is always optimistic. Can we get any feel for the magnitude of this bias ?
Essay
Answer:
Tags
Choose question tag
close menu
arrow
Go to http://www.people.hbs.edu/besty/projfinportal/ and find employment opportunities in project finance. What role does finance play in projects?
Essay
Answer:
Tags
Choose question tag
close menu
arrow
A construction firm has been commissioned to renew a portion of the Alaska crude-oil pipeline that has fallen into a state of disrepair. The project activities with the estimated times and their relationships are shown below: img a. Prepare a project network. b. List the critical path activities and the expected project duration. c. Determine the scheduling times and total slack for all activities. d. In the contract, a bonus of $100,000 per day will be paid for each day the project is completed earlier than its expected duration. Evaluate the following alternatives to shorten the project duration and then make a recommendation: 1. Crash activity B by 4 days at a cost of $100,000. 2. Crash activity G by 1 day at a cost of $50,000. 3. Crash activity O by 2 days at a cost of $150,000. 4. Crash activity O by 2 days by drawing resources from activity N, thereby extending the time of N by 2 days.
Essay
Answer:
Tags
Choose question tag
close menu
arrow
An electric utility is planning its annual project of shutting down one of its steam boilers for maintenance and repair. An analysis of this project has identified the following principal activities and their expected times and relationships. img a. Prepare a project network diagram. b. Calculate the scheduling times and total slack for each activity. c. List the critical path activities and project duration. d. Assuming that one worker is required for each activity, prepare a resource-leveled schedule. What is the maximum number of workers required to finish the project on time?
Essay
Answer:
Tags
Choose question tag
close menu
arrow
Using Microsoft Project for Windows, prepare a network and identify the critical path activities, the expected project duration, and scheduling times for all activities.
Essay
Answer:
Tags
Choose question tag
close menu
arrow
The following project network and table provide the normal times and costs as well as the crash times and costs for the activities required to complete a project. Crash the completion time to the minimum level. img img
Essay
Answer:
Tags
Choose question tag
close menu
Showing 1 - 20 of 22