Cornerstones of Cost Management 2nd Edition by Don Hansen ,Maryanne Mowen
Edition 2ISBN: 978-1111824402
Cornerstones of Cost Management 2nd Edition by Don Hansen ,Maryanne Mowen
Edition 2ISBN: 978-1111824402 Exercise 27
A manufacturing cell within a value stream is structured with four processes and associated processing times (for one unit):
Molding: 6 minutes
Grinding: 5 minutes
Polishing: 5 minutes
Finishing: 4 minutes
How many units can the cell produce per hour (on a continuous running basis)?
a. 3 units per hour
b. 12 units per hour
c. 15 units per hour
d. 10 units per hour
Molding: 6 minutes
Grinding: 5 minutes
Polishing: 5 minutes
Finishing: 4 minutes
How many units can the cell produce per hour (on a continuous running basis)?
a. 3 units per hour
b. 12 units per hour
c. 15 units per hour
d. 10 units per hour
Explanation
Correct option is (d):
Justification:
...
Cornerstones of Cost Management 2nd Edition by Don Hansen ,Maryanne Mowen