Deck 10: Monitoring and Information Systems

Full screen (f)
exit full mode
Question
According to the authors,the key items to be planned,monitored,and controlled are __________.

A)schedule,budget,and financial stability
B)schedule,quality,performance,and customer satisfaction
C)schedule,budget,and feasibility
D)schedule,budget,and performance
Use Space or
up arrow
down arrow
to flip the card.
Question
Reports for __________ have a need for detailed information about individual tasks and the factors affecting such tasks.

A)top executives
B)lower-level personnel
C)all the stakeholders
D)project managers
Question
For project management,there are three distinct types of reports.Which of the following would be used in response to a special problem?

A)Daily
B)Routine
C)Exception
D)Special analysis
Question
Monitoring,as an activity,should be kept distinct from __________,which is the process of making judgments about the quality and effectiveness of project performance.

A)collecting
B)reporting
C)evaluation
D)recording
Question
Vague or incomplete project requirements are an example of which telltale sign that a project is in trouble?

A)Muddy waters
B)Mysterious stakeholders
C)Unconstrained constraints
D)Scope creep
Question
The project __________ describes what is being done,when and the planned level of resource usage for each task,work-package or element in the project.

A)WBS
B)risk management plan
C)schedule
D)quality report
Question
An appropriate and common secondary user for monitoring includes __________.

A)auditing,learning from mistakes,and reporting progress and status
B)exercising effective control over the project
C)evaluating current status of the project
D)fixing the blame when things go wrong
Question
The earned value rule that divides the actual task time-to-date by the scheduled time for the task to calculate percent complete is called the __________ rule.

A)50-50
B)0-100 percent
C)critical input use
D)proportionality
Question
The most common mistake made when monitoring data is to gather information that is clearly related to project performance but __________.

A)is so volatile that trends cannot be detected
B)has little or no probability of changing significantly between collection periods
C)is too unusual to use
D)cannot be captured in the mechanized PMIS
Question
For each factor to be measured during monitoring; performance criteria,standards,and __________ should be established.

A)data collection procedures
B)mechanized systems
C)automated systems
D)audit checks
Question
Unfortunately,it is common to focus monitoring activities on data that are easily __________ but not necessarily important.

A)gathered
B)purchased
C)analyzed
D)reported
Question
A status report that is vague or contains overly optimistic language like "very soon" or "marginal increase" in costs is referred to as

A)suspicious
B)paralyzed
C)incomplete
D)risky
Question
The first step in setting up a monitoring system is to __________.

A)collect existing data to see what data is relevant and available
B)collect every available piece of information so it can be analyzed
C)use whatever information is available
D)identify the key factors to be controlled
Question
For project management,there are three distinct types of reports.Which of the following is not one of those three types?

A)Daily
B)Routine
C)Exception
D)Special analysis
Question
What is the most likely project report to be issued periodically?

A)Milestone report
B)Resource report
C)Variances report for senior financial management
D)Progress reports for senior management
Question
What is the relationship between management level and report details?

A)Senior management receives more reports than lower levels
B)Senior management receives the reports as lower levels
C)Senior management receives fewer reports than lower levels
D)There is no relationship
Question
The project control process should be viewed as a(n)__________,with revised plans and schedules (if warranted)following corrective actions.The project control process should run continuously until the project is completed.

A)closed loop system
B)open loop system
C)open environment
D)earned value plan
Question
The best sources of items to be monitored are the project risk management plan,change of scope orders,and __________.

A)schedule
B)WBS
C)quality report
D)resource report
Question
__________ is collecting,recording,and reporting information concerning any and all aspects of project performance that the project manager or others in the organization wish to know.

A)Initiating
B)Planning
C)Controlling
D)Monitoring
Question
Monitoring,as an activity,should be kept distinct from __________,which uses data supplied by monitoring to bring actual performance into approximate congruence with planned performance.

A)recording
B)controlling
C)collecting
D)reporting
Question
In earned value Analysis,the 0 - 100 percent rule allows __________.

A)100 percent credit before starting work and 0 percent credit after the completion
B)0 percent credit when work begins and 100 percent credit when the project is complete
C)0 percent credit when work begins and 100 percent credit at completion of the activity
D)0 percent credit at completion of the activity and 100 percent credit at formal acceptance during scope verification
Question
In earned value Analysis,EAC refers to the __________.

A)estimated cost at completion
B)estimated actual cost
C)eliminated annual cost
D)estimated annual cost
Question
In earned value analysis,(EV / AC)(EV / PV)= __________.

A)CV
B)TPI
C)CSI
D)SV
Question
If CPI = 1.05,then __________ is favorable.

A)time variance
B)schedule variance
C)cost variance
D)performance variance
Question
There are several conventions used to aid in estimating percentage completion.Which of the following is the most conservative?

A)50-50 rule
B)0-100 percent rule
C)Critical input use
D)Proportionality
Question
If EV = $500,AC = $475,PV = $450; SV = ________.

A)$50
B)$25
C)90%
D)95%
Question
If EV = $500,AC = $450,PV = $475; CPI = __________.

A)1)05
B)1)11
C))95
D))90
Question
There are several conventions used to aid in estimating percentage completion.Which of the following is the most popular?

A)50-50 rule
B)0-100 percent rule
C)Critical input use
D)Proportionality
Question
In earned value analysis,the __________ is computed as the earned value minus the actual cost of work performed.

A)schedule variance
B)cost variance
C)time variance
D)CPI
Question
If EV = $500,AC = $475,PV = $450; CV = ________.

A)-$50
B)$50
C)90%
D)95%
Question
Which of the following conventions has the characteristic of the project always seeming to be running late,until the very end when it seems to suddenly catch up?

A)The 50-50 rule
B)The 0-100 percent rule
C)Critical input use rule
D)The proportionality rule
Question
In earned value analysis,if the cost variance is (-$10,000),__________.

A)the cost variance is favorable
B)the cost variance is unfavorable
C)the scheduled variance is favorable
D)the scheduled cost avoidance is unfavorable
Question
If EV = $500,AC = $450,PV = $475; SPI = __________.

A)1)05
B)1)11
C))95
D))90
Question
In earned value Analysis,the 50-50 rule assumes that __________.

A)50 percent is earned when the task is half done and 50 percent is earned at completion
B)50 percent is earned when the task begins and 50 percent is earned at completion
C)50 percent is earned when the task begins and 50 percent is earned at the halfway stage
D)50 percent is earned when the project is planned and 50 percent is earned when the project is over
Question
__________ can often give the project manager early warning signals of potential problems in a project and help understand the relationships of individual tasks to one another and to the overall project.

A)Detailed and timely reports
B)Executive summaries
C)Scope change reports
D)The WBS
Question
EV - PV = __________.

A)SV
B)CV
C)CPI
D)TV
Question
If CSI is less than 1,it is indicative of a(n)__________.

A)problem
B)good project
C)efficient project
D)budget error
Question
In earned value analysis,(CPI)(SPI)= __________.

A)CV
B)TPI
C)CSI
D)SV
Question
Which of the following is not a common difficulty in the design of project reports?

A)Providing too much detail
B)Having too many interface modules
C)Poor correspondence to the parent firm's reporting system
D)Poor correspondence between the planning and monitoring systems
Question
In earned value Analysis,BAC refers to the __________.

A)budgeted annual cost
B)budget at completion
C)budget at close-out
D)big annual cost
Question
(BAC + EV) / CPI = __________.

A)EAC
B)TPI
C)CPI
D)ETC
Question
Identify the main complaints associated with meetings.
Question
Suggest some practical measures that can be used to improve the perception about the benefits of meetings.
Question
Alderton suggests telltale signs of project trouble.Match these terms for these signs with their descriptions.

A)Muddy waters
B)Unconstrained constraints
C)Suspicious status reports
D)Discord and drama
1)Knowing how much leeway there is in your schedule and budget for each task,and where delays or cost overruns can be made up,keeps a project out of trouble.
2)Vague or overly optimistic language such as "very soon" or "marginal increase" in costs also indicates trouble ahead.
3)Unhappy team members can cause major trouble in the project.
4)The scope is not well defined or well understood." Vague or incomplete project requirements are a major red flag.
Question
When using earned value analysis,identify the three conditions that can exist with respect to the completion of activities in a project.
Question
Describe the three common difficulties in designing project reports.
Question
List the four conventions used to aid in estimating percent completion.
Question
There are several conventions used to aid in estimating percent completion.Match each rule with its description.

A)50-50 rule
B)0-100 percent rule
C)Critical input use
D)Proportionality
1)This commonly used rule is also based on percentages,but uses time (or cost)as the critical input.
2)This rule assigns task progress according to the amount of an important input that has been used.
3)This rule allows no credit for work until the task is complete.
4)Fifty percent completion is assumed when the task is begun,and the remaining 50 percent when the work is complete.
Question
ST-AT =

A)TV
B)EV
C)CV
D)SV
Question
Identify some of the benefits when timely reports are delivered to the proper people by the project management information system.
Question
Conceptually,EAC represents the amount spent to date plus __________.

A)the delay costs
B)BAC
C)CV
D)ETC
Question
List and describe five telltale signs of project trouble it is wise to monitor.
Question
ETC + AC = __________.

A)BAC
B)EAC
C)SPI
D)CPI
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/53
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 10: Monitoring and Information Systems
1
According to the authors,the key items to be planned,monitored,and controlled are __________.

A)schedule,budget,and financial stability
B)schedule,quality,performance,and customer satisfaction
C)schedule,budget,and feasibility
D)schedule,budget,and performance
D
2
Reports for __________ have a need for detailed information about individual tasks and the factors affecting such tasks.

A)top executives
B)lower-level personnel
C)all the stakeholders
D)project managers
B
3
For project management,there are three distinct types of reports.Which of the following would be used in response to a special problem?

A)Daily
B)Routine
C)Exception
D)Special analysis
D
4
Monitoring,as an activity,should be kept distinct from __________,which is the process of making judgments about the quality and effectiveness of project performance.

A)collecting
B)reporting
C)evaluation
D)recording
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
5
Vague or incomplete project requirements are an example of which telltale sign that a project is in trouble?

A)Muddy waters
B)Mysterious stakeholders
C)Unconstrained constraints
D)Scope creep
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
6
The project __________ describes what is being done,when and the planned level of resource usage for each task,work-package or element in the project.

A)WBS
B)risk management plan
C)schedule
D)quality report
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
7
An appropriate and common secondary user for monitoring includes __________.

A)auditing,learning from mistakes,and reporting progress and status
B)exercising effective control over the project
C)evaluating current status of the project
D)fixing the blame when things go wrong
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
8
The earned value rule that divides the actual task time-to-date by the scheduled time for the task to calculate percent complete is called the __________ rule.

A)50-50
B)0-100 percent
C)critical input use
D)proportionality
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
9
The most common mistake made when monitoring data is to gather information that is clearly related to project performance but __________.

A)is so volatile that trends cannot be detected
B)has little or no probability of changing significantly between collection periods
C)is too unusual to use
D)cannot be captured in the mechanized PMIS
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
10
For each factor to be measured during monitoring; performance criteria,standards,and __________ should be established.

A)data collection procedures
B)mechanized systems
C)automated systems
D)audit checks
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
11
Unfortunately,it is common to focus monitoring activities on data that are easily __________ but not necessarily important.

A)gathered
B)purchased
C)analyzed
D)reported
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
12
A status report that is vague or contains overly optimistic language like "very soon" or "marginal increase" in costs is referred to as

A)suspicious
B)paralyzed
C)incomplete
D)risky
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
13
The first step in setting up a monitoring system is to __________.

A)collect existing data to see what data is relevant and available
B)collect every available piece of information so it can be analyzed
C)use whatever information is available
D)identify the key factors to be controlled
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
14
For project management,there are three distinct types of reports.Which of the following is not one of those three types?

A)Daily
B)Routine
C)Exception
D)Special analysis
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
15
What is the most likely project report to be issued periodically?

A)Milestone report
B)Resource report
C)Variances report for senior financial management
D)Progress reports for senior management
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
16
What is the relationship between management level and report details?

A)Senior management receives more reports than lower levels
B)Senior management receives the reports as lower levels
C)Senior management receives fewer reports than lower levels
D)There is no relationship
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
17
The project control process should be viewed as a(n)__________,with revised plans and schedules (if warranted)following corrective actions.The project control process should run continuously until the project is completed.

A)closed loop system
B)open loop system
C)open environment
D)earned value plan
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
18
The best sources of items to be monitored are the project risk management plan,change of scope orders,and __________.

A)schedule
B)WBS
C)quality report
D)resource report
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
19
__________ is collecting,recording,and reporting information concerning any and all aspects of project performance that the project manager or others in the organization wish to know.

A)Initiating
B)Planning
C)Controlling
D)Monitoring
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
20
Monitoring,as an activity,should be kept distinct from __________,which uses data supplied by monitoring to bring actual performance into approximate congruence with planned performance.

A)recording
B)controlling
C)collecting
D)reporting
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
21
In earned value Analysis,the 0 - 100 percent rule allows __________.

A)100 percent credit before starting work and 0 percent credit after the completion
B)0 percent credit when work begins and 100 percent credit when the project is complete
C)0 percent credit when work begins and 100 percent credit at completion of the activity
D)0 percent credit at completion of the activity and 100 percent credit at formal acceptance during scope verification
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
22
In earned value Analysis,EAC refers to the __________.

A)estimated cost at completion
B)estimated actual cost
C)eliminated annual cost
D)estimated annual cost
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
23
In earned value analysis,(EV / AC)(EV / PV)= __________.

A)CV
B)TPI
C)CSI
D)SV
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
24
If CPI = 1.05,then __________ is favorable.

A)time variance
B)schedule variance
C)cost variance
D)performance variance
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
25
There are several conventions used to aid in estimating percentage completion.Which of the following is the most conservative?

A)50-50 rule
B)0-100 percent rule
C)Critical input use
D)Proportionality
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
26
If EV = $500,AC = $475,PV = $450; SV = ________.

A)$50
B)$25
C)90%
D)95%
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
27
If EV = $500,AC = $450,PV = $475; CPI = __________.

A)1)05
B)1)11
C))95
D))90
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
28
There are several conventions used to aid in estimating percentage completion.Which of the following is the most popular?

A)50-50 rule
B)0-100 percent rule
C)Critical input use
D)Proportionality
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
29
In earned value analysis,the __________ is computed as the earned value minus the actual cost of work performed.

A)schedule variance
B)cost variance
C)time variance
D)CPI
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
30
If EV = $500,AC = $475,PV = $450; CV = ________.

A)-$50
B)$50
C)90%
D)95%
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
31
Which of the following conventions has the characteristic of the project always seeming to be running late,until the very end when it seems to suddenly catch up?

A)The 50-50 rule
B)The 0-100 percent rule
C)Critical input use rule
D)The proportionality rule
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
32
In earned value analysis,if the cost variance is (-$10,000),__________.

A)the cost variance is favorable
B)the cost variance is unfavorable
C)the scheduled variance is favorable
D)the scheduled cost avoidance is unfavorable
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
33
If EV = $500,AC = $450,PV = $475; SPI = __________.

A)1)05
B)1)11
C))95
D))90
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
34
In earned value Analysis,the 50-50 rule assumes that __________.

A)50 percent is earned when the task is half done and 50 percent is earned at completion
B)50 percent is earned when the task begins and 50 percent is earned at completion
C)50 percent is earned when the task begins and 50 percent is earned at the halfway stage
D)50 percent is earned when the project is planned and 50 percent is earned when the project is over
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
35
__________ can often give the project manager early warning signals of potential problems in a project and help understand the relationships of individual tasks to one another and to the overall project.

A)Detailed and timely reports
B)Executive summaries
C)Scope change reports
D)The WBS
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
36
EV - PV = __________.

A)SV
B)CV
C)CPI
D)TV
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
37
If CSI is less than 1,it is indicative of a(n)__________.

A)problem
B)good project
C)efficient project
D)budget error
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
38
In earned value analysis,(CPI)(SPI)= __________.

A)CV
B)TPI
C)CSI
D)SV
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
39
Which of the following is not a common difficulty in the design of project reports?

A)Providing too much detail
B)Having too many interface modules
C)Poor correspondence to the parent firm's reporting system
D)Poor correspondence between the planning and monitoring systems
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
40
In earned value Analysis,BAC refers to the __________.

A)budgeted annual cost
B)budget at completion
C)budget at close-out
D)big annual cost
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
41
(BAC + EV) / CPI = __________.

A)EAC
B)TPI
C)CPI
D)ETC
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
42
Identify the main complaints associated with meetings.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
43
Suggest some practical measures that can be used to improve the perception about the benefits of meetings.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
44
Alderton suggests telltale signs of project trouble.Match these terms for these signs with their descriptions.

A)Muddy waters
B)Unconstrained constraints
C)Suspicious status reports
D)Discord and drama
1)Knowing how much leeway there is in your schedule and budget for each task,and where delays or cost overruns can be made up,keeps a project out of trouble.
2)Vague or overly optimistic language such as "very soon" or "marginal increase" in costs also indicates trouble ahead.
3)Unhappy team members can cause major trouble in the project.
4)The scope is not well defined or well understood." Vague or incomplete project requirements are a major red flag.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
45
When using earned value analysis,identify the three conditions that can exist with respect to the completion of activities in a project.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
46
Describe the three common difficulties in designing project reports.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
47
List the four conventions used to aid in estimating percent completion.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
48
There are several conventions used to aid in estimating percent completion.Match each rule with its description.

A)50-50 rule
B)0-100 percent rule
C)Critical input use
D)Proportionality
1)This commonly used rule is also based on percentages,but uses time (or cost)as the critical input.
2)This rule assigns task progress according to the amount of an important input that has been used.
3)This rule allows no credit for work until the task is complete.
4)Fifty percent completion is assumed when the task is begun,and the remaining 50 percent when the work is complete.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
49
ST-AT =

A)TV
B)EV
C)CV
D)SV
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
50
Identify some of the benefits when timely reports are delivered to the proper people by the project management information system.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
51
Conceptually,EAC represents the amount spent to date plus __________.

A)the delay costs
B)BAC
C)CV
D)ETC
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
52
List and describe five telltale signs of project trouble it is wise to monitor.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
53
ETC + AC = __________.

A)BAC
B)EAC
C)SPI
D)CPI
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 53 flashcards in this deck.