Deck 4: Planning Projects, part I Project Integration, scope, time, and Cost Management
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/100
Play
Full screen (f)
Deck 4: Planning Projects, part I Project Integration, scope, time, and Cost Management
1
The project sponsor and project champion should be the same person on any project.
False
2
The goal of the activity definition process is to replace the scope statement.
False
3
The contents of scope statements can vary.
True
4
The project management plan typically provides detailed cost projections by WBS by month.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
5
The tasks in a WBS must be developed as a sequential list of steps.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
6
People are more likely to perform well if they know what they are supposed to do and when.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
7
The project team should review an activity list and activity attributes with project stakeholders.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
8
As more information becomes available and decisions are made related to project scope,the project team should update the project scope statement.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
9
The WBS is a peripheral document in project management.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
10
Discretionary dependencies are defined by the project team.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
11
Specifications on a WBS represent work that needs to be done to complete the project.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
12
The project manager monitors and controls work packages at the lowest level of the WBS.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
13
You need a detailed project schedule before you can develop a cost baseline.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
14
Activity sequencing involves reviewing the activity list and attributes,project scope statement,and milestone list to determine the relationships or dependencies between activities.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
15
There is usually no cost or duration associated with a milestone.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
16
Project teams rarely estimate completion dates for milestones early in the scheduling process.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
17
The format of the WBS dictionary can vary based on project needs.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
18
The project charter,preliminary scope statement,and current project management plan are key inputs to the scope management plan.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
19
Work that is not included in the scope statement should be performed as needed.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
20
Every item on a WBS needs to be on the network diagram.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
21
There can be more than one critical path on a project.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
22
The precedence diagramming method uses only finish-to-start dependencies.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
23
The main planning tasks performed as part of project scope management include scope planning,scope definition,and ____.
A) scope evaluation
B) scope reduction
C) creating the WBS
D) scope expansion
A) scope evaluation
B) scope reduction
C) creating the WBS
D) scope expansion
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
24
After you determine the reason for a dependency between activities,you must determine the type of dependency.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
25
Duration relates to the time estimate,not the effort estimate.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
26
The main purpose of project planning is to guide project ____.
A) initiation
B) execution
C) review
D) evaluation
A) initiation
B) execution
C) review
D) evaluation
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
27
The critical path is the shortest path through the network diagram.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
28
The main output of scope planning is a ____ management plan,which is a document that includes descriptions of how the team will prepare the scope statement,create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope.
A) scope
B) project
C) program
D) portfolio
A) scope
B) project
C) program
D) portfolio
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
29
The term "____" is used to describe each level of work in the WBS.
A) activity
B) module
C) task
D) node
A) activity
B) module
C) task
D) node
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
30
The PMBOK Guide lists over ____ documents that project teams can produce as part of project planning.
A) 50
B) 75
C) 100
D) 125
A) 50
B) 75
C) 100
D) 125
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
31
A large percentage of total project costs are often labor costs.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
32
Project management ____ facilitate communication among stakeholders and provide a baseline for progress measurement and project control.
A) charters
B) plans
C) contracts
D) compacts
A) charters
B) plans
C) contracts
D) compacts
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
33
Project ____ management involves coordinating all the project management knowledge areas throughout a project's life span.
A) union
B) synthesis
C) unification
D) integration
A) union
B) synthesis
C) unification
D) integration
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
34
Planning includes tasks related to each of the ____ project management knowledge areas.
A) four
B) five
C) nine
D) sixteen
A) four
B) five
C) nine
D) sixteen
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
35
Scope statements should include,at a minimum,a description of the project,including its overall objectives and justification; detailed descriptions of all project ____; characteristics and requirements of products and services produced as part of the project; and project success criteria.
A) stakeholders
B) volunteers
C) meetings
D) deliverables
A) stakeholders
B) volunteers
C) meetings
D) deliverables
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
36
The WBS is a required input to the cost budgeting process.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
37
The project team develops a preliminary scope statement during project ____.
A) review
B) initiation
C) orientation
D) development
A) review
B) initiation
C) orientation
D) development
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
38
It is poor practice to use more than one approach for creating a cost estimate.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
39
Most project teams use the most pessimistic time to estimate activity durations.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
40
A key output of the resource estimating process is documentation of activity resource requirements.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
41
Performance in meeting project scope goals is based on the scope ____.
A) definition
B) revision
C) baseline
D) statement
A) definition
B) revision
C) baseline
D) statement
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
42
There are ____ basic reasons for creating dependencies among project activities.
A) three
B) four
C) five
D) six
A) three
B) four
C) five
D) six
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
43
____ dependencies are inherent in the nature of the work being performed on a project.
A) Embedded
B) Absolute
C) Mandatory
D) Compulsory
A) Embedded
B) Absolute
C) Mandatory
D) Compulsory
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
44
A three-point estimate is an estimate that includes a(n)____,most likely,and pessimistic estimate,such as three weeks,four weeks,and five weeks,respectively.
A) optimistic
B) unusual
C) remote
D) conditional
A) optimistic
B) unusual
C) remote
D) conditional
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
45
____ dependencies involve relationships between project and nonproject activities.
A) Internal
B) External
C) Ancillary
D) Miscellaneous
A) Internal
B) External
C) Ancillary
D) Miscellaneous
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
46
Activity ____ provide schedule-related information about each activity,such as predecessors,successors,logical relationships,leads and lags,resource requirements,constraints,imposed dates,and assumptions related to the activity.
A) features
B) characteristics
C) properties
D) attributes
A) features
B) characteristics
C) properties
D) attributes
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
47
The Just-In-Time Training project team decided to use the project management process groups for the level ____ tasks in its WBS.
A) 0
B) 1
C) 2
D) 3
A) 0
B) 1
C) 2
D) 3
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
48
Duration estimates are provided as a ____ number,such as four weeks; as a range,such as three to five weeks; or as a three-point estimate.
A) continuous
B) random
C) fractional
D) discrete
A) continuous
B) random
C) fractional
D) discrete
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
49
In an AOA network diagram,____ occur when two or more activities follow a single node.
A) drives
B) flares
C) bursts
D) runs
A) drives
B) flares
C) bursts
D) runs
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
50
Project management software uses the ____ format to represent the WBS.
A) tabular
B) binary
C) flexible
D) chart
A) tabular
B) binary
C) flexible
D) chart
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
51
In an AOA network diagram,a(n)____ occurs when two or more nodes precede a single node.
A) merge
B) join
C) union
D) intersection
A) merge
B) join
C) union
D) intersection
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
52
After defining project activities,the next step in project time management is activity ____.
A) organization
B) sequencing
C) segmenting
D) ordering
A) organization
B) sequencing
C) segmenting
D) ordering
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
53
The main groupings for the work in a WBS chart are listed in the second tier of boxes,called level ____.
A) 0
B) 1
C) 2
D) 3
A) 0
B) 1
C) 2
D) 3
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
54
The project team begins to develop a ____ by first clearly defining all the activities it needs to perform.
A) charter
B) schedule
C) scope
D) work flow diagram
A) charter
B) schedule
C) scope
D) work flow diagram
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
55
The project manager should work with his or her team and ____ to determine the level of detail needed in the WBS dictionary.
A) client
B) customer
C) auditor
D) sponsor
A) client
B) customer
C) auditor
D) sponsor
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
56
What is the PERT weighted average based on an optimistic estimate of six days,a most likely estimate of eight days,and a pessimistic time of twelve days?
A) six
B) eight
C) eleven
D) twelve
A) six
B) eight
C) eleven
D) twelve
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
57
In the context of a network diagram,a ____ is simply the starting and ending point of an activity.
A) cell
B) vertex
C) source
D) node
A) cell
B) vertex
C) source
D) node
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
58
Tasks in a WBS that are decomposed into smaller tasks are called ____ tasks.
A) micro
B) tentative
C) summary
D) definitive
A) micro
B) tentative
C) summary
D) definitive
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
59
To define the ____ of the project accurately,it is very important to ensure consistency between the project charter,scope statement,WBS,Gantt chart,and related documents.
A) scope
B) charter
C) vision
D) parameters
A) scope
B) charter
C) vision
D) parameters
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
60
____ includes the actual amount of time spent working on an activity plus elapsed time.
A) Extension
B) Duration
C) Period
D) Length
A) Extension
B) Duration
C) Period
D) Length
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
61
The approved project scope statement and its associated WBS and WBS dictionary form the scope ____________________.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
62
You need to plan the project ____________________ and determine what activities need to be done before you can develop a detailed project schedule.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
63
A work ____________________ is a task at the lowest level of the WBS.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
64
Project ____________________ management involves defining and controlling what work is or is not included in a project.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
65
The main disadvantage of ____ is that it can end up lengthening the project schedule,because starting some tasks too soon often increases project risk and results in rework.
A) reviewing
B) crashing
C) extending
D) fast tracking
A) reviewing
B) crashing
C) extending
D) fast tracking
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
66
Project ____ management includes the processes required to ensure that a project team completes a project within an approved budget.
A) control
B) delivery
C) cost
D) outlays
A) control
B) delivery
C) cost
D) outlays
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
67
____ estimates,also called top-down estimates,use the actual cost of a previous,similar project as the basis for estimating the cost of the current project.
A) Homologous
B) Analogous
C) Sequential
D) Parallel
A) Homologous
B) Analogous
C) Sequential
D) Parallel
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
68
____ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost.
A) Crashing
B) Deflating
C) Compacting
D) Minimizing
A) Crashing
B) Deflating
C) Compacting
D) Minimizing
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
69
A(n)____________________ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
70
A WBS ____________________ is a document that describes WBS tasks in detail.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
71
____ estimates involve estimating individual activities and summing them to get a project total.
A) Bottom-up
B) Provisional
C) Ad hoc
D) Temporary
A) Bottom-up
B) Provisional
C) Ad hoc
D) Temporary
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
72
A(n)____ path for a project is the series of activities that determine the earliest time by which the project can be completed.
A) integral
B) incidental
C) critical
D) vital
A) integral
B) incidental
C) critical
D) vital
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
73
Slack or ____ is the amount of time an activity may be delayed without delaying a succeeding activity or the project finish date.
A) leeway
B) float
C) redundancy
D) space
A) leeway
B) float
C) redundancy
D) space
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
74
____ development uses the results of all the preceding project time management processes to determine the start and end dates of project activities and of the entire project.
A) Task
B) Schedule
C) Work Package
D) Activity
A) Task
B) Schedule
C) Work Package
D) Activity
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
75
The main output of scope definition is the scope ____________________.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
76
A cost baseline is a(n)____ budget that project managers use to measure and monitor cost performance.
A) incidental
B) basic
C) time-phased
D) incremental
A) incidental
B) basic
C) time-phased
D) incremental
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
77
A(n)____________________ is a starting point,a measurement,or an observation that is documented so that it can be used for future comparison.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
78
To create a good WBS,you must understand both the project and its scope,and incorporate the needs and knowledge of the ____________________.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
79
Project ____________________ involves devising and maintaining a workable scheme to ensure that the project meets its scope,time,and cost goals as well as organizational needs.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
80
Cost ____ involves allocating the overall cost estimate to individual tasks over time to establish a baseline for measuring performance.
A) estimating
B) account
C) allowance
D) budgeting
A) estimating
B) account
C) allowance
D) budgeting
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck