Deck 9: Resource Allocation

Full screen (f)
exit full mode
Question
The tasks that logically precede a particular task in time are referred to as __________.

A)successors
B)followers
C)predecessors
D)priorities
Use Space or
up arrow
down arrow
to flip the card.
Question
The standard practice with AOA and AON is to estimate activity times under the assumption of resource loadings that are __________.

A)probabilistic
B)crashed
C)normal
D)dynamic
Question
The points between the extreme points of the relationship between time use and resource use represent __________.

A)time constrained projects
B)resource constrained projects
C)alternative trade-offs between time and resources
D)a non-feasible solution space of trade-off alternatives related to time and resource use
Question
The formula for computing the cost/time slope for each activity that can be crashed is __________.

A)(crash cost + normal cost)/ (crash time + normal time)
B)(crash cost - normal cost)/ (crash time - normal time)
C)(normal cost + crash cost)/ (normal time + crash time)
D)(normal cost - crash cost)/ (normal time - crash time)
Question
Economically speaking, crashing a project creates a technology change in the __________ for an activity.

A)deliverable demand function
B)production function
C)audit function
D)deliverable supply function
Question
The two fundamental approaches to constrained allocation problems are __________.

A)heuristic approaches and rules of thumb
B)linear programming approaches and optimization models
C)heuristic approaches and optimization models
D)goal programming and trial and error
Question
The usual purpose of the __________ scheduling heuristic is to delay cash outflows as long as possible.

A)minimum slack first
B)shortest task first
C)most successors
D)as late as possible
Question
Using the __________ heuristic method, the project team can complete the maximum number of tasks during a given period of time.

A)as soon as possible
B)as late as possible
C)shortest task first
D)minimum slack first
Question
The principal reason why a project manager is surprised by resource constraints on a project is the failure to include __________ in risk identification activities.

A)resource availability
B)resource cost
C)resource mobility
D)resource skill
Question
In CPM, __________ are specified.

A)exact levels of uncertainty associated with activities
B)an expected time, a crash time, and the standard deviation time
C)three costs
D)Two activity times and two costs
Question
The __________ heuristic provides a general solution for critical path and time and is usually the default rule for a schedule.

A)as soon as possible
B)as late as possible
C)minimum slack first
D)shortest task first
Question
The __________ technique overlaps the design and build phases of a project to expedite its completion.

A)crashing
B)fast-tracking
C)leading
D)blitzing
Question
When using heuristic solutions to build a schedule, __________ will always take precedence.

A)technological necessities
B)time constraints
C)resource constraints
D)managerial preferences
Question
Most heuristic solution methods start with the __________ and analyze resource usage period by period, resource by resource.

A)GERT schedule
B)Gantt chart
C)PERT/CPM schedule
D)Master schedule
Question
When crashing a project, our first task is to develop __________.

A)a table or graph of the cost of a project as a function of the project's possible completion dates
B)a schedule that shows the risks associated with each activity in the project
C)a list that shows the activities and the events of a project without referring to the costs
D)a table showing the noncritical activities and the cost associated with each of those activities
Question
If deterministic time estimates are used, and if project deadlines are firm, there is a high likelihood that it will __________.

A)not be necessary to crash any activities in projects
B)be necessary to crash the last few activities of most projects
C)be completed on time and within budget
D)be completed as per schedule
Question
One of the problems that Goldratt observed was that if an activity has slack time, often times the start of the task is delayed until the slack is removed. This is referred to as __________.

A)Goldratt's Law
B)Murphy's Law
C)the delay game
D)the student syndrome
Question
The methods to find an optimal solution to the constrained resource scheduling problem fall into two categories. They are __________.

A)mathematical programming and linear programming
B)mathematical programming and enumeration
C)statistical analysis and simulation
D)quantified heuristics and gaming
Question
Which of the following effects will be observed in a network if a date-constrained project is scheduled from the ending date constraint using the "as late as possible" heuristic?

A)Each activity will make use of all the slack available to it.
B)The network will not have any critical activities.
C)It would never be possible to override the "as late as possible" heuristic with a "must start no later than" date constraint.
D)Many of the activities will be scheduled prior to the start date of the project.
Question
The __________ approach to constrained resource scheduling problems is the only feasible method of attacking large, nonlinear, complex problems that tend to occur in the real world of project management.

A)goal programming
B)heuristic
C)optimization modeling
D)linear programming
Question
If the appropriate scheduling equation for task A of a project were W = D * U, and it was initialized so that W = 40d, D = 10d, and U = 4 resources, and task A is an effort-driven activity, correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are __________.
Question
The use of __________ activity time estimates may reduce the chance that crashing the project will be needed.
Question
Three important parameters used to assess the effectiveness of a scheduling system include schedule slippage, in-process inventory, and __________.
Question
When we change technology, we may also be changing the level of __________ in carrying out the activity.
Question
Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. If Bob were 100 percent available to work on task R during the entire five days, his efficiency rate is __________%.
Question
__________ times result from an attempt to expedite the activity by the application of additional resources.
Question
__________ aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances. The purpose is to create a smoother distribution of resource usage.
Question
Given a scheduling equation W = D * U, if the equation for task J is initialized so that W = 20d, D= 5d, and U = 4 resources, and task J is a non-effort-driven activity (where D is held constant when resources are changed), correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are __________.
Question
__________ describes the amounts of individual resources an existing schedule requires during specific time periods.
Question
With respect to project scheduling, __________ is the amount of work waiting to be processed because there is a shortage of some resource.
Question
Given that task A will use three carpenters and have duration of six days, task A requires __________ labor days of work.
Question
Studies have shown that the __________ scheduling heuristic method usually results in the minimum amount of project schedule slippage, best utilization of facilities, and minimum total system occupancy time.

A)as soon as possible
B)as late as possible
C)shortest task first
D)minimum slack first
Question
Thoughtless optimism, the "student syndrome," and multitasking to reduce idle time can each contribute to __________.

A)slack
B)pessimistic bias
C)optimistic bias
D)feeder buffer
Question
One cannot save __________, rather one can only spend more or less of it.
Question
Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. Bob was expected to be 100% available to work on task R during the entire five days. However, Bob left the company and will be replaced by Sam. Sam's efficiency rate is 90%. If Sam is only 70% available, Sam will require __________ hours to complete task R.
Question
In some situations, two activities are scheduled to be carried out in parallel and using the same scarce resource. If the supply of the scarce resource is not sufficient to allow both activities to be carried out simultaneously, then whichever of the two is given priority immediately lengthens the other activity's path but not its actual __________.

A)duration
B)slack
C)float
D)buffer
Question
A project task is said to be __________ if it requires a fixed amount of time and known quantities of resources.
Question
The two principles to follow when crashing a project are __________.
Question
__________ are tasks that logically follow a particular task in time.
Question
__________ refers to the amount of time past a project's due or delivery date.
Question
Describe the extreme points of the relationship between time use and resource use.
Question
Suggest some options for leveling the load placed on resources.
Question
Describe the basic procedure for resource leveling.
Question
Discuss the advantages obtained from resource leveling.
Question
List some of the common priority rules utilized when following heuristic solution methods.
Question
Discuss some other causes of the strong optimistic bias in a project schedule.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/46
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 9: Resource Allocation
1
The tasks that logically precede a particular task in time are referred to as __________.

A)successors
B)followers
C)predecessors
D)priorities
C
2
The standard practice with AOA and AON is to estimate activity times under the assumption of resource loadings that are __________.

A)probabilistic
B)crashed
C)normal
D)dynamic
C
3
The points between the extreme points of the relationship between time use and resource use represent __________.

A)time constrained projects
B)resource constrained projects
C)alternative trade-offs between time and resources
D)a non-feasible solution space of trade-off alternatives related to time and resource use
C
4
The formula for computing the cost/time slope for each activity that can be crashed is __________.

A)(crash cost + normal cost)/ (crash time + normal time)
B)(crash cost - normal cost)/ (crash time - normal time)
C)(normal cost + crash cost)/ (normal time + crash time)
D)(normal cost - crash cost)/ (normal time - crash time)
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
5
Economically speaking, crashing a project creates a technology change in the __________ for an activity.

A)deliverable demand function
B)production function
C)audit function
D)deliverable supply function
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
6
The two fundamental approaches to constrained allocation problems are __________.

A)heuristic approaches and rules of thumb
B)linear programming approaches and optimization models
C)heuristic approaches and optimization models
D)goal programming and trial and error
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
7
The usual purpose of the __________ scheduling heuristic is to delay cash outflows as long as possible.

A)minimum slack first
B)shortest task first
C)most successors
D)as late as possible
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
8
Using the __________ heuristic method, the project team can complete the maximum number of tasks during a given period of time.

A)as soon as possible
B)as late as possible
C)shortest task first
D)minimum slack first
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
9
The principal reason why a project manager is surprised by resource constraints on a project is the failure to include __________ in risk identification activities.

A)resource availability
B)resource cost
C)resource mobility
D)resource skill
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
10
In CPM, __________ are specified.

A)exact levels of uncertainty associated with activities
B)an expected time, a crash time, and the standard deviation time
C)three costs
D)Two activity times and two costs
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
11
The __________ heuristic provides a general solution for critical path and time and is usually the default rule for a schedule.

A)as soon as possible
B)as late as possible
C)minimum slack first
D)shortest task first
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
12
The __________ technique overlaps the design and build phases of a project to expedite its completion.

A)crashing
B)fast-tracking
C)leading
D)blitzing
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
13
When using heuristic solutions to build a schedule, __________ will always take precedence.

A)technological necessities
B)time constraints
C)resource constraints
D)managerial preferences
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
14
Most heuristic solution methods start with the __________ and analyze resource usage period by period, resource by resource.

A)GERT schedule
B)Gantt chart
C)PERT/CPM schedule
D)Master schedule
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
15
When crashing a project, our first task is to develop __________.

A)a table or graph of the cost of a project as a function of the project's possible completion dates
B)a schedule that shows the risks associated with each activity in the project
C)a list that shows the activities and the events of a project without referring to the costs
D)a table showing the noncritical activities and the cost associated with each of those activities
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
16
If deterministic time estimates are used, and if project deadlines are firm, there is a high likelihood that it will __________.

A)not be necessary to crash any activities in projects
B)be necessary to crash the last few activities of most projects
C)be completed on time and within budget
D)be completed as per schedule
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
17
One of the problems that Goldratt observed was that if an activity has slack time, often times the start of the task is delayed until the slack is removed. This is referred to as __________.

A)Goldratt's Law
B)Murphy's Law
C)the delay game
D)the student syndrome
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
18
The methods to find an optimal solution to the constrained resource scheduling problem fall into two categories. They are __________.

A)mathematical programming and linear programming
B)mathematical programming and enumeration
C)statistical analysis and simulation
D)quantified heuristics and gaming
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
19
Which of the following effects will be observed in a network if a date-constrained project is scheduled from the ending date constraint using the "as late as possible" heuristic?

A)Each activity will make use of all the slack available to it.
B)The network will not have any critical activities.
C)It would never be possible to override the "as late as possible" heuristic with a "must start no later than" date constraint.
D)Many of the activities will be scheduled prior to the start date of the project.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
20
The __________ approach to constrained resource scheduling problems is the only feasible method of attacking large, nonlinear, complex problems that tend to occur in the real world of project management.

A)goal programming
B)heuristic
C)optimization modeling
D)linear programming
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
21
If the appropriate scheduling equation for task A of a project were W = D * U, and it was initialized so that W = 40d, D = 10d, and U = 4 resources, and task A is an effort-driven activity, correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are __________.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
22
The use of __________ activity time estimates may reduce the chance that crashing the project will be needed.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
23
Three important parameters used to assess the effectiveness of a scheduling system include schedule slippage, in-process inventory, and __________.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
24
When we change technology, we may also be changing the level of __________ in carrying out the activity.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
25
Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. If Bob were 100 percent available to work on task R during the entire five days, his efficiency rate is __________%.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
26
__________ times result from an attempt to expedite the activity by the application of additional resources.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
27
__________ aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances. The purpose is to create a smoother distribution of resource usage.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
28
Given a scheduling equation W = D * U, if the equation for task J is initialized so that W = 20d, D= 5d, and U = 4 resources, and task J is a non-effort-driven activity (where D is held constant when resources are changed), correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are __________.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
29
__________ describes the amounts of individual resources an existing schedule requires during specific time periods.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
30
With respect to project scheduling, __________ is the amount of work waiting to be processed because there is a shortage of some resource.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
31
Given that task A will use three carpenters and have duration of six days, task A requires __________ labor days of work.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
32
Studies have shown that the __________ scheduling heuristic method usually results in the minimum amount of project schedule slippage, best utilization of facilities, and minimum total system occupancy time.

A)as soon as possible
B)as late as possible
C)shortest task first
D)minimum slack first
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
33
Thoughtless optimism, the "student syndrome," and multitasking to reduce idle time can each contribute to __________.

A)slack
B)pessimistic bias
C)optimistic bias
D)feeder buffer
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
34
One cannot save __________, rather one can only spend more or less of it.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
35
Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. Bob was expected to be 100% available to work on task R during the entire five days. However, Bob left the company and will be replaced by Sam. Sam's efficiency rate is 90%. If Sam is only 70% available, Sam will require __________ hours to complete task R.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
36
In some situations, two activities are scheduled to be carried out in parallel and using the same scarce resource. If the supply of the scarce resource is not sufficient to allow both activities to be carried out simultaneously, then whichever of the two is given priority immediately lengthens the other activity's path but not its actual __________.

A)duration
B)slack
C)float
D)buffer
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
37
A project task is said to be __________ if it requires a fixed amount of time and known quantities of resources.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
38
The two principles to follow when crashing a project are __________.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
39
__________ are tasks that logically follow a particular task in time.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
40
__________ refers to the amount of time past a project's due or delivery date.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
41
Describe the extreme points of the relationship between time use and resource use.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
42
Suggest some options for leveling the load placed on resources.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
43
Describe the basic procedure for resource leveling.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
44
Discuss the advantages obtained from resource leveling.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
45
List some of the common priority rules utilized when following heuristic solution methods.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
46
Discuss some other causes of the strong optimistic bias in a project schedule.