Deck 11: Managing Project Execution

Full screen (f)
exit full mode
Question
Project execution is part of:

A)project scope management.
B)project integration management.
C)project procurement management.
D)project execution management.
Use Space or
up arrow
down arrow
to flip the card.
Question
The process of carrying out the project plan is called:

A)project integration.
B)project performance.
C)project administration.
D)project execution.
Question
The silver bullet syndrome is a system development mistake.

A)people- related
B)process- related
C)technology- related
D)product- related
Question
Which of the following procurement activities does NOT happen during project execution?

A)Request seller responses
B)Contract administration
C)Select sellers
D)Contract closure
Question
Feature creep is a system development mistake.

A)people- related
B)technology- related
C)product- related
D)process- related
Question
Which of the following is NOT part of project integration management?

A)Develop project schedule
B)Develop preliminary scope statement
C)Develop project charter
D)Develop project management plan
Question
All of the following are people- related system development project problems EXCEPT:

A)adding people too late to a project.
B)planning to catch up.
C)unrealistic expectations.
D)weak personnel.
Question
Overestimating savings from new tools or methods is a _ system development mistake.

A)product- related
B)process- related
C)technology- related
D)people- related
Question
Which of the following is an input to project execution?

A)Project scope baseline
B)Project scope statement
C)Project baseline
D)Project management plan
Question
Having unrealistic expectations is a system development mistake.

A)process- related
B)technology- related
C)people- related
D)product- related
Question
refers to adding more requirements than necessary to an application, even before the beginning of a project.

A)Scope creep
B)Feature creep
C)The silver bullet syndrome
D)Requirements gold- plating
Question
Why is documentation important for a project?

A)It provides a record that can be audited or used as part of a legal defense.
B)It is valuable for the project team in case they need to trace how a decision was made.
C)It may be used as a source of best practices to improve other projects.
D)All of the above.
Question
is the tendency of systems requirements to change over the lifetime of the development project.

A)Feature creep
B)Scope creep
C)The silver bullet syndrome
D)Requirements gold- plating
Question
What is NOT true about managing change?

A)Every change will affect the project deliverables, schedule, and budget.
B)Every change request should be documented.
C)Most changes will not affect the project deliverables, schedule, and budget.
D)Not every request for change results in a change to the requirements.
Question
is a problem occurring when developers believe a new and usually untried technology is all that is needed to cure the ills of any development project.

A)The silver bullet syndrome
B)Scope creep
C)Feature creep
D)Requirements gold- plating
Question
All of the following are process- related system development project problems EXCEPT:

A)insufficient planning.
B)planning to catch up later.
C)unrealistic expectations.
D)overly optimistic schedules.
Question
Having overly optimistic schedules is a system development mistake.

A)product- related
B)technology- related
C)people- related
D)process- related
Question
involves evaluating project progress on a regular basis in order to determine if the project will satisfy established quality standards.

A)Monitor progress
B)Manage project quality
C)Perform quality assurance
D)Perform quality control
Question
A is a ceremonial meeting marking the beginning of a project in a public way.

A)project initiation meeting
B)project launch meeting
C)project kickoff meeting
D)project inauguration meeting
Question
Which of the following is NOT an output of project execution?

A)implemented quality changes
B)Implemented corrective actions
C)implemented preventive action
D)Implemented change requests
Question
Requirements gold- plating is a system development mistake.

A)process- related
B)product- related
C)people- related
D)technology- related
Question
________is the process of keeping track of all project tasks and the details surrounding each one.
Question
The_________ is a problem occurring when developers believe a new and usually untried technology is all that is needed to cure the ills of any development project.
Question
_________is valuable for project team members in case they need to trace how a decision was made.
Question
Having overly optimistic schedules is a_________system development mistake
Question
Overestimating savings from new tools or methods is a _________ system development mistake.
Question
Requirements gold- plating is a________ system development mistake.
Question
_________is the tendency of systems requirements to change over the lifetime of the development project.
Question
_________is the process of carrying out the project plan.
Question
The kickoff meeting does not have to be a big party.
Question
The silver bullet syndrome is a_________ system development mistake
Question
It is easier to compare reality to expectations when expectations are ________.
Question
Project execution is part of project________ management.
Question
Using new technologies can usually help to bring a project back on track, even if the technologies haven't been tried before.
Question
Unrealistic expectations is a ________system development mistake.
Question
Which of the following is NOT part of project execution?

A)Perform quality assurance
B)Develop project budget
C)Request seller responses
D)Develop project team
Question
Changes to an application typically cost 50 to 200 times less if they are made during requirements determination rather than during the physical design process.
Question
_________refers to adding more requirements than necessary to an application, even before the beginning of a project.
Question
Documentation may be used as a source of_________ to improve other projects.
Question
A _________ is a ceremonial meeting marking the beginning of a project in a public way.
Question
If something goes wrong during project execution, it helps to adding people late to the project.
Question
"Feature creep" refers to the tendency of system requirements to change over the lifetime of the development project.
Question
During the project kickoff meeting, much of the most important work gets started.
Question
Requirements gold- plating means that an application may have more requirements than it needs, even before the development begins.
Question
For IT projects, execution is where the system is developed and released.
Question
Documentation is only used as a source of best practices for other projects.
Question
Most project teams are static during a given project.
Question
What is a kickoff meeting and how/why is it held?
Question
Requests for minor changes don't have to be formally reviewed before they are implemented.
Question
Compare and contrast "feature creep" and "requirements gold- plating."
Question
Not every request for change results in a change in requirements.
Question
The average project may see a 10% change in requirements.
Question
Reports about the project and its progress should be written, rather than oral, and regular, rather than ad hoc.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/53
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 11: Managing Project Execution
1
Project execution is part of:

A)project scope management.
B)project integration management.
C)project procurement management.
D)project execution management.
B
2
The process of carrying out the project plan is called:

A)project integration.
B)project performance.
C)project administration.
D)project execution.
D
3
The silver bullet syndrome is a system development mistake.

A)people- related
B)process- related
C)technology- related
D)product- related
C
4
Which of the following procurement activities does NOT happen during project execution?

A)Request seller responses
B)Contract administration
C)Select sellers
D)Contract closure
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
5
Feature creep is a system development mistake.

A)people- related
B)technology- related
C)product- related
D)process- related
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
6
Which of the following is NOT part of project integration management?

A)Develop project schedule
B)Develop preliminary scope statement
C)Develop project charter
D)Develop project management plan
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
7
All of the following are people- related system development project problems EXCEPT:

A)adding people too late to a project.
B)planning to catch up.
C)unrealistic expectations.
D)weak personnel.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
8
Overestimating savings from new tools or methods is a _ system development mistake.

A)product- related
B)process- related
C)technology- related
D)people- related
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
9
Which of the following is an input to project execution?

A)Project scope baseline
B)Project scope statement
C)Project baseline
D)Project management plan
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
10
Having unrealistic expectations is a system development mistake.

A)process- related
B)technology- related
C)people- related
D)product- related
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
11
refers to adding more requirements than necessary to an application, even before the beginning of a project.

A)Scope creep
B)Feature creep
C)The silver bullet syndrome
D)Requirements gold- plating
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
12
Why is documentation important for a project?

A)It provides a record that can be audited or used as part of a legal defense.
B)It is valuable for the project team in case they need to trace how a decision was made.
C)It may be used as a source of best practices to improve other projects.
D)All of the above.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
13
is the tendency of systems requirements to change over the lifetime of the development project.

A)Feature creep
B)Scope creep
C)The silver bullet syndrome
D)Requirements gold- plating
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
14
What is NOT true about managing change?

A)Every change will affect the project deliverables, schedule, and budget.
B)Every change request should be documented.
C)Most changes will not affect the project deliverables, schedule, and budget.
D)Not every request for change results in a change to the requirements.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
15
is a problem occurring when developers believe a new and usually untried technology is all that is needed to cure the ills of any development project.

A)The silver bullet syndrome
B)Scope creep
C)Feature creep
D)Requirements gold- plating
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
16
All of the following are process- related system development project problems EXCEPT:

A)insufficient planning.
B)planning to catch up later.
C)unrealistic expectations.
D)overly optimistic schedules.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
17
Having overly optimistic schedules is a system development mistake.

A)product- related
B)technology- related
C)people- related
D)process- related
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
18
involves evaluating project progress on a regular basis in order to determine if the project will satisfy established quality standards.

A)Monitor progress
B)Manage project quality
C)Perform quality assurance
D)Perform quality control
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
19
A is a ceremonial meeting marking the beginning of a project in a public way.

A)project initiation meeting
B)project launch meeting
C)project kickoff meeting
D)project inauguration meeting
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
20
Which of the following is NOT an output of project execution?

A)implemented quality changes
B)Implemented corrective actions
C)implemented preventive action
D)Implemented change requests
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
21
Requirements gold- plating is a system development mistake.

A)process- related
B)product- related
C)people- related
D)technology- related
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
22
________is the process of keeping track of all project tasks and the details surrounding each one.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
23
The_________ is a problem occurring when developers believe a new and usually untried technology is all that is needed to cure the ills of any development project.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
24
_________is valuable for project team members in case they need to trace how a decision was made.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
25
Having overly optimistic schedules is a_________system development mistake
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
26
Overestimating savings from new tools or methods is a _________ system development mistake.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
27
Requirements gold- plating is a________ system development mistake.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
28
_________is the tendency of systems requirements to change over the lifetime of the development project.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
29
_________is the process of carrying out the project plan.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
30
The kickoff meeting does not have to be a big party.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
31
The silver bullet syndrome is a_________ system development mistake
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
32
It is easier to compare reality to expectations when expectations are ________.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
33
Project execution is part of project________ management.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
34
Using new technologies can usually help to bring a project back on track, even if the technologies haven't been tried before.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
35
Unrealistic expectations is a ________system development mistake.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
36
Which of the following is NOT part of project execution?

A)Perform quality assurance
B)Develop project budget
C)Request seller responses
D)Develop project team
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
37
Changes to an application typically cost 50 to 200 times less if they are made during requirements determination rather than during the physical design process.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
38
_________refers to adding more requirements than necessary to an application, even before the beginning of a project.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
39
Documentation may be used as a source of_________ to improve other projects.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
40
A _________ is a ceremonial meeting marking the beginning of a project in a public way.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
41
If something goes wrong during project execution, it helps to adding people late to the project.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
42
"Feature creep" refers to the tendency of system requirements to change over the lifetime of the development project.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
43
During the project kickoff meeting, much of the most important work gets started.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
44
Requirements gold- plating means that an application may have more requirements than it needs, even before the development begins.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
45
For IT projects, execution is where the system is developed and released.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
46
Documentation is only used as a source of best practices for other projects.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
47
Most project teams are static during a given project.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
48
What is a kickoff meeting and how/why is it held?
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
49
Requests for minor changes don't have to be formally reviewed before they are implemented.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
50
Compare and contrast "feature creep" and "requirements gold- plating."
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
51
Not every request for change results in a change in requirements.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
52
The average project may see a 10% change in requirements.
Unlock Deck
Unlock for access to all 53 flashcards in this deck.
Unlock Deck
k this deck
53
Reports about the project and its progress should be written, rather than oral, and regular, rather than ad hoc.