Deck 13: Project Evaluation and Control

Full screen (f)
exit full mode
Question
The degree to which anyone who will be ultimately making use of the product of the project is personally involved in the implementation process is the __________ critical success factor in the Project Implementation Profile.
Use Space or
up arrow
down arrow
to flip the card.
Question
Positive variance on an S-curve represents significant project progress.
Question
The project implementation profile assesses the performance of the project team with respect to 10 critical success factors and can be used on an on-going project.
Question
The schedule performance index is the ratio of the actual cost to the earned value.
Question
A(n) __________ identifies the stage of completion of each task has attained by a specified date within the project.
Question
Once an activity has been started it is immediately valued at 50% completed under the __________.
Question
The budgeted cost of the work that has been performed to date is the __________.
Question
The one factor that earned value management considers that an S-curve does not include is performance.
Question
Earned value management allows a project manager to monitor the project's __________, __________, and __________.
Question
Your organization is in the midst of a project in uncharted waters; nothing you have attempted before comes close to many of the activities that are necessary to bring this project to completion. Your earned value management should probably be tracked closely with a percentage complete rule in increments of 5 to 10 percent.
Question
The earned value of a project is the cumulative total costs incurred in accomplishing the various work packages.
Question
Gap analysis refers to any measurement process that first determines the goals and then the degree to which the actual performance lives up to those goals.
Question
It is possible to measure both positive and negative deviations from the schedule baseline with the tracking Gantt chart.
Question
The data collected from the various evaluation and control techniques represents important __________ measures of the project.
Question
The project costs plotted against the elapsed time in weeks is known as the __________.
Question
The __________ allows the project manager to calculate the project's budget to completion.
Question
The classic S-curve is a plot of cumulative cost versus elapsed time in weeks.
Question
The Project Implementation Profile allows teams to make mid-course correction and improvement of the __________.
Question
Five weeks in the semester you have completed 0% of your project management class under the 0/100 rule.
Question
If the actual cost line on an S-curve undercuts the budgeted cost line, the project has a(n) __________ variance.
Question
The classic project S-curve is a plot of:

A) labor hours versus money expended.
B) money expended versus elapsed time.
C) elapsed time versus labor hours.
D) number of personnel versus days behind schedule.
Question
Earned value management is also known as:

A) the golden triangle method (GTM).
B) the achieved value method (AVM).
C) the program evaluation and review method (PERM).
D) earned value analysis (EVA).
Question
Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the best statement. <strong>Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the best statement.  </strong> A) The project never experiences negative variance. B) With regards to budget, the project starts badly but finishes well C) With regards to budget, the project starts well but finishes badly. D) The project is in a constant state of positive variance. <div style=padding-top: 35px>

A) The project never experiences negative variance.
B) With regards to budget, the project starts badly but finishes well
C) With regards to budget, the project starts well but finishes badly.
D) The project is in a constant state of positive variance.
Question
A project manager that uses milestones as a project control device is using a(n):

A) proactive control system.
B) predictive control system.
C) feedback control system.
D) reactive control system.
Question
A tracking Gantt chart does NOT allow for:

A) looking at today's activity progress and determining whether a single activity is behind schedule.
B) future projections of the project's status.
C) looking at today's activity progress and determining whether the entire project is behind schedule.
D) looking at today's activity progress and determining whether a single activity is ahead of schedule.
Question
It is possible to measure:

A) only positive deviations from the schedule baseline with a tracking Gantt chart.
B) only negative deviations from the schedule baseline with a tracking Gantt chart.
C) both positive and negative deviations from the schedule baseline with the tracking Gantt chart.
D) both positive and negative deviations from the budget with the tracking Gantt chart.
Question
Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the best statement. <strong>Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the best statement.  </strong> A) The project is further ahead of budget from weeks 36 through 40 than from weeks 8 through 12. B) The project never experiences negative variance. C) The project is further behind budget from weeks 0 through 16 than from 24 through 40. D) The project is in a constant state of positive variance. <div style=padding-top: 35px>

A) The project is further ahead of budget from weeks 36 through 40 than from weeks 8 through 12.
B) The project never experiences negative variance.
C) The project is further behind budget from weeks 0 through 16 than from 24 through 40.
D) The project is in a constant state of positive variance.
Question
A measurement process that determines the project goals and then the degree to which the actual performance lives up to these goals is:

A) a metric system.
B) goal-performance linkage.
C) five degrees of separation.
D) gap analysis.
Question
Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks. <strong>Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks.  </strong> A) More time passes from weeks 5 to 10 than from weeks 20 to 25. B) More time passes from $50,000 to $60,000 than from $5,000 to $10,000. C) More money is spent from weeks 0 to 10 than from weeks 30 to 40. D) The total amount spent on the project at the end of the 40<sup>th</sup> week is approximately $110,000. <div style=padding-top: 35px>

A) More time passes from weeks 5 to 10 than from weeks 20 to 25.
B) More time passes from $50,000 to $60,000 than from $5,000 to $10,000.
C) More money is spent from weeks 0 to 10 than from weeks 30 to 40.
D) The total amount spent on the project at the end of the 40th week is approximately $110,000.
Question
How does a tracking Gantt chart's appearance differ from a standard Gantt chart?

A) The tracking Gantt chart has a plot against time on the X1 axis and shows progress against budget on the X2 axis.
B) The tracking Gantt chart is composed of dollar signs that show the relative expense of the activity in comparison with other activities.
C) Each bar in the tracking Gantt chart shows who is responsible for completion of the activity in question.
D) Each bar in the tracking Gantt chart varies from 100% solid if the activity is completed to 100% alternative pattern if the activity has not begun.
Question
A tracking Gantt chart does NOT show:

A) the reason an activity has slipped.
B) which activities are ahead of schedule.
C) which activities are on schedule.
D) which activities are behind schedule.
Question
Measurement mechanisms should include a clear definition of:

A) the project baseline.
B) the reporting relationships among members of the project team.
C) what to measure.
D) trigger points.
Question
An excellent way to coordinate schedules with vendors and suppliers is through the use of:

A) milestones.
B) S-curves that plot expenditures against time.
C) S-curves that plot planned expenditures against time.
D) a tracking Gantt chart.
Question
Milestones are generally considered to be:

A) demotivators for the project team.
B) key project review gates.
C) the end of the project for all team members except the project manager.
D) points where two or more activities merge.
Question
A tracking Gantt chart:

A) monitors costs and budget expenditures.
B) identifies key points in the project's progress.
C) identifies the stage of completion for each task.
D) identifies the performance to budget for the overall project by a certain date.
Question
An S-curve CANNOT be used to:

A) determine whether the project is ahead of budget.
B) determine when the project is behind budget.
C) determine the cause of positive variance.
D) determine whether there is negative variance.
Question
Project goal setting includes setting a baseline plan, which is predicated on:

A) the progress measurement.
B) an accurate work breakdown structure.
C) the type of gap analysis the project team plans to use.
D) the budget and schedule limitations.
Question
Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks. <strong>Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks.  </strong> A) The total project costs in week 10 are less than budgeted. B) The total project costs in week 10 exceed the budgeted cost. C) The project cost more from weeks 25 through 30 than it did in weeks 10 through 15. D) The total amount spent on the project at the end of the 20<sup>th</sup> week is approximately $30,000. <div style=padding-top: 35px>

A) The total project costs in week 10 are less than budgeted.
B) The total project costs in week 10 exceed the budgeted cost.
C) The project cost more from weeks 25 through 30 than it did in weeks 10 through 15.
D) The total amount spent on the project at the end of the 20th week is approximately $30,000.
Question
The first step in the control cycle is:

A) setting a goal.
B) measuring progress.
C) comparing actual with planned performance.
D) taking action.
Question
If significant deviations from the project plan are detected, corrective action is taken and then:

A) the monitoring and control cycle begins anew.
B) project goals are adjusted to reflect current reality.
C) the project stakeholders are informed of the budget or time difficulties.
D) the critical chain is reviewed for task dependency.
Question
At the end of week 20, this project has cost $79,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars. <strong>At the end of week 20, this project has cost $79,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars.  </strong> A) 1.11 B) 0.82 C) 0.94 D) 0.90 <div style=padding-top: 35px>

A) 1.11
B) 0.82
C) 0.94
D) 0.90
Question
Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. <strong>Use the data to calculate the earned value for the project. All amounts are in thousands of dollars.  </strong> A) $65,500 B) $69,550 C) $71,100 D) $76,125 <div style=padding-top: 35px>

A) $65,500
B) $69,550
C) $71,100
D) $76,125
Question
Earned value is:

A) the total budget for the project.
B) a cost estimate of the budgeted resources across the project's life cycle.
C) the real budgeted value of the work that has actually been performed to date.
D) the cumulative total costs incurred in accomplishing the various project work packages.
Question
At the end of week 10, this project has cost $9,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars. <strong>At the end of week 10, this project has cost $9,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars.  </strong> A) 2.5 B) 2.1 C) 1.8 D) 1.5 <div style=padding-top: 35px>

A) 2.5
B) 2.1
C) 1.8
D) 1.5
Question
The earned value divided by the actual, cumulative cost of the work to date is the:

A) cost performance index.
B) budgeted cost at completion index.
C) budget efficiency index.
D) schedule performance index.
Question
Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. <strong>Use the data to calculate the earned value for the project. All amounts are in thousands of dollars.  </strong> A) $38,500 B) $43,250 C) $54,750 D) $100,000 <div style=padding-top: 35px>

A) $38,500
B) $43,250
C) $54,750
D) $100,000
Question
In earned value management analysis, the cumulative amount of the budget becomes the:

A) planned value.
B) scheduled value.
C) cost basis.
D) cost driver.
Question
Earned value management jointly considers the impact of:

A) time, cost, and planned cost.
B) project performance, planned performance, and cost.
C) performance, cost, and time.
D) planned cost, planned performance, and time.
Question
Which of these tools allows a project team to make future projections of project status based on its current state?

A) tracking Gantt chart
B) milestone chart
C) S-curve
D) earned value management
Question
The project baseline is established by combining data from the:

A) work breakdown structure and the project budget.
B) time-phased project budget and the PERT chart.
C) S-curve and the project budget.
D) time-phased project budget and the work breakdown structure.
Question
A project manager can calculate the projected budget to completion by using the:

A) budgeted cost at completion index.
B) budget efficiency index.
C) cost performance index.
D) schedule performance index.
Question
Take the factors considered by earned value analysis and subtract those considered by project S-curves. The factor(s) you have remaining are:

A) performance and cost.
B) cost and schedule.
C) time.
D) performance.
Question
Planned value is:

A) the total budget for the project.
B) a cost estimate of the budgeted resources across the project's life cycle.
C) the real budgeted value of the work that has actually been performed to date.
D) the cumulative total costs incurred in accomplishing the various project work packages.
Question
The earned value to date divided by the planned value of work scheduled to be performed is the:

A) cost performance index.
B) budgeted cost at completion index.
C) budget efficiency index.
D) schedule performance index.
Question
Use the data to calculate the schedule performance index for the project for the end of week 20. All amounts are in thousands of dollars. <strong>Use the data to calculate the schedule performance index for the project for the end of week 20. All amounts are in thousands of dollars.  </strong> A) 1.14 B) 0.88 C) 0.94 D) 0.81 <div style=padding-top: 35px>

A) 1.14
B) 0.88
C) 0.94
D) 0.81
Question
A project manager can calculate the projected schedule of the project to completion by using the:

A) cost performance index.
B) schedule performance index.
C) budgeted cost at completion index.
D) budget efficiency index.
Question
Use the data to calculate the schedule performance index for the project for the end of week 10. All amounts are in thousands of dollars. <strong>Use the data to calculate the schedule performance index for the project for the end of week 10. All amounts are in thousands of dollars.  </strong> A) 1.24 B) 0.93 C) 0.81 D) 0.76 <div style=padding-top: 35px>

A) 1.24
B) 0.93
C) 0.81
D) 0.76
Question
Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. <strong>Use the data to calculate the earned value for the project. All amounts are in thousands of dollars.  </strong> A) $38,500 B) $46,550 C) $56,750 D) $61,125 <div style=padding-top: 35px>

A) $38,500
B) $46,550
C) $56,750
D) $61,125
Question
The first step in earned value management is to:

A) create the activity and resource usage schedules.
B) develop a time-phased budget that shows expenditures across the project's life.
C) total the actual costs of doing each task to arrive at the actual cost of work performed.
D) clearly define each activity that will be performed including its resource needs and budget.
Question
Take the factors considered by earned value analysis and subtract those considered by tracking Gantt charts. The factor(s) you have remaining are:

A) cost.
B) cost and schedule.
C) schedule and performance.
D) performance.
Question
The budget variance is calculated as:

A) earned value minus planned value.
B) planned value minus actual cost.
C) earned value minus actual cost.
D) cost minus planned value.
Question
A recurring problem with establishing accurate or meaningful EVM results has to do with:

A) the 0/100 rule.
B) over-reliance on the S-curve.
C) the need to recognize the human factor.
D) the need to satisfy stakeholders within budget and time parameters.
Question
Use the earned value table for Project Terrace to determine their schedule variance if all dollar amounts are in hundreds. <strong>Use the earned value table for Project Terrace to determine their schedule variance if all dollar amounts are in hundreds.  </strong> A) $100 B) $120 C) $1,200 D) $200 <div style=padding-top: 35px>

A) $100
B) $120
C) $1,200
D) $200
Question
In the build-up stage of a successful project, it is important that:

A) an adequate budget exists.
B) top management support exists.
C) the project personnel are in a state of flux.
D) there is a clear sense of earned value management.
Question
Use the earned value table for Project Terrace to calculate their schedule performance index if all dollar amounts are in hundreds. <strong>Use the earned value table for Project Terrace to calculate their schedule performance index if all dollar amounts are in hundreds.  </strong> A) 0.90 B) 0.80 C) 1.12 D) 1.20 <div style=padding-top: 35px>

A) 0.90
B) 0.80
C) 1.12
D) 1.20
Question
Each activity contained a series of milestones that represented a previously agreed-upon amount of work. Once the low graffiti was erased, 35% of the activity had been completed and once the mid-level graffiti was erased, 70% of the activity had been completed. This project manager was clearly in the:

A) percentage complete camp.
B) micromanagement camp.
C) 35/70 camp.
D) 3K specifications camp.
Question
Funding problems are a key success inhibitor in the:

A) build-up phase.
B) close-out phase.
C) main phase.
D) formation phase.
Question
Use the earned value table for Project Terrace to calculate their estimated time to completion (all dollar amounts are in hundreds). <strong>Use the earned value table for Project Terrace to calculate their estimated time to completion (all dollar amounts are in hundreds).  </strong> A) 14.2 days B) 15.0 days C) 18.4 days D) 16.8 days <div style=padding-top: 35px>

A) 14.2 days
B) 15.0 days
C) 18.4 days
D) 16.8 days
Question
One of these things is NOT like the others (that happen to directly predict project success). The one that's different is:

A) lack of budgetary pressure.
B) adequacy of project structure and control.
C) project coordination and relations among stakeholders.
D) the tenure of the project manager.
Question
In the formation stage, failed projects are more likely to have:

A) technical limitations.
B) personal ambition.
C) clear objectives.
D) team motivation.
Question
If an activity's progress is defined as 0% until the moment is complete, the project manager is using:

A) the 50/50 rule.
B) the all or nothing rule.
C) the 0/100 rule.
D) the Do Not Pass Go rule.
Question
The critical success factor that relates to the underlying purpose for the project is the:

A) project mission.
B) technical acceptance.
C) technical tasks.
D) client consultation.
Question
Project Terrace has an actual cost of $3,000, but their earned value (all dollar amounts are in hundreds) table appears below. What is their cost variance? <strong>Project Terrace has an actual cost of $3,000, but their earned value (all dollar amounts are in hundreds) table appears below. What is their cost variance?  </strong> A) $250 B) -$250 C) 1.08 D) 0.92 <div style=padding-top: 35px>

A) $250
B) -$250
C) 1.08
D) 0.92
Question
In earned value management, schedule variance is defined as:

A) the difference between the earned value and the actual cost.
B) the difference between the earned value and the planned value.
C) the difference between the actual cost and the planned value.
D) the difference between the cost and schedule performance indices multiplied by the budgeted cost at completion.
Question
An unmotivated team is a key success inhibitor in every project stage with the exception of the:

A) main phase.
B) formation phase.
C) close-out phase.
D) build-up phase.
Question
Very short work packages would be better managed by:

A) the percentage complete rule.
B) the 0/100 rule.
C) the caveat emptor rule.
D) the prior knowledge rule.
Question
Earned value management at the portfolio level requires:

A) a single project manager with a single metric system.
B) aggregation of all earned value measures across the firm's entire project portfolio.
C) only positive variances for both budget and schedule.
D) only negative variances for both budget and schedule.
Question
Once an activity is begun, it is assumed to be half done under the:

A) "once begun, half done" rule.
B) minimal effort rule.
C) midway rule.
D) 50/50 rule.
Question
Use the earned value table for Project Terrace to calculate their estimated cost to completion (all dollar amounts are in hundreds). <strong>Use the earned value table for Project Terrace to calculate their estimated cost to completion (all dollar amounts are in hundreds).  </strong> A) $4,285 B) $4,800 C) $4,532 D) $3,604 <div style=padding-top: 35px>

A) $4,285
B) $4,800
C) $4,532
D) $3,604
Question
Use the earned value table for Project Terrace to determine the earned value (all dollar amounts are in hundreds). <strong>Use the earned value table for Project Terrace to determine the earned value (all dollar amounts are in hundreds).  </strong> A) $325 B) $7600 C) $4800 D) $3250 <div style=padding-top: 35px>

A) $325
B) $7600
C) $4800
D) $3250
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/98
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 13: Project Evaluation and Control
1
The degree to which anyone who will be ultimately making use of the product of the project is personally involved in the implementation process is the __________ critical success factor in the Project Implementation Profile.
client consultation
2
Positive variance on an S-curve represents significant project progress.
False
3
The project implementation profile assesses the performance of the project team with respect to 10 critical success factors and can be used on an on-going project.
True
4
The schedule performance index is the ratio of the actual cost to the earned value.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
5
A(n) __________ identifies the stage of completion of each task has attained by a specified date within the project.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
6
Once an activity has been started it is immediately valued at 50% completed under the __________.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
7
The budgeted cost of the work that has been performed to date is the __________.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
8
The one factor that earned value management considers that an S-curve does not include is performance.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
9
Earned value management allows a project manager to monitor the project's __________, __________, and __________.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
10
Your organization is in the midst of a project in uncharted waters; nothing you have attempted before comes close to many of the activities that are necessary to bring this project to completion. Your earned value management should probably be tracked closely with a percentage complete rule in increments of 5 to 10 percent.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
11
The earned value of a project is the cumulative total costs incurred in accomplishing the various work packages.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
12
Gap analysis refers to any measurement process that first determines the goals and then the degree to which the actual performance lives up to those goals.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
13
It is possible to measure both positive and negative deviations from the schedule baseline with the tracking Gantt chart.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
14
The data collected from the various evaluation and control techniques represents important __________ measures of the project.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
15
The project costs plotted against the elapsed time in weeks is known as the __________.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
16
The __________ allows the project manager to calculate the project's budget to completion.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
17
The classic S-curve is a plot of cumulative cost versus elapsed time in weeks.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
18
The Project Implementation Profile allows teams to make mid-course correction and improvement of the __________.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
19
Five weeks in the semester you have completed 0% of your project management class under the 0/100 rule.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
20
If the actual cost line on an S-curve undercuts the budgeted cost line, the project has a(n) __________ variance.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
21
The classic project S-curve is a plot of:

A) labor hours versus money expended.
B) money expended versus elapsed time.
C) elapsed time versus labor hours.
D) number of personnel versus days behind schedule.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
22
Earned value management is also known as:

A) the golden triangle method (GTM).
B) the achieved value method (AVM).
C) the program evaluation and review method (PERM).
D) earned value analysis (EVA).
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
23
Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the best statement. <strong>Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the best statement.  </strong> A) The project never experiences negative variance. B) With regards to budget, the project starts badly but finishes well C) With regards to budget, the project starts well but finishes badly. D) The project is in a constant state of positive variance.

A) The project never experiences negative variance.
B) With regards to budget, the project starts badly but finishes well
C) With regards to budget, the project starts well but finishes badly.
D) The project is in a constant state of positive variance.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
24
A project manager that uses milestones as a project control device is using a(n):

A) proactive control system.
B) predictive control system.
C) feedback control system.
D) reactive control system.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
25
A tracking Gantt chart does NOT allow for:

A) looking at today's activity progress and determining whether a single activity is behind schedule.
B) future projections of the project's status.
C) looking at today's activity progress and determining whether the entire project is behind schedule.
D) looking at today's activity progress and determining whether a single activity is ahead of schedule.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
26
It is possible to measure:

A) only positive deviations from the schedule baseline with a tracking Gantt chart.
B) only negative deviations from the schedule baseline with a tracking Gantt chart.
C) both positive and negative deviations from the schedule baseline with the tracking Gantt chart.
D) both positive and negative deviations from the budget with the tracking Gantt chart.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
27
Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the best statement. <strong>Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the best statement.  </strong> A) The project is further ahead of budget from weeks 36 through 40 than from weeks 8 through 12. B) The project never experiences negative variance. C) The project is further behind budget from weeks 0 through 16 than from 24 through 40. D) The project is in a constant state of positive variance.

A) The project is further ahead of budget from weeks 36 through 40 than from weeks 8 through 12.
B) The project never experiences negative variance.
C) The project is further behind budget from weeks 0 through 16 than from 24 through 40.
D) The project is in a constant state of positive variance.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
28
A measurement process that determines the project goals and then the degree to which the actual performance lives up to these goals is:

A) a metric system.
B) goal-performance linkage.
C) five degrees of separation.
D) gap analysis.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
29
Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks. <strong>Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks.  </strong> A) More time passes from weeks 5 to 10 than from weeks 20 to 25. B) More time passes from $50,000 to $60,000 than from $5,000 to $10,000. C) More money is spent from weeks 0 to 10 than from weeks 30 to 40. D) The total amount spent on the project at the end of the 40<sup>th</sup> week is approximately $110,000.

A) More time passes from weeks 5 to 10 than from weeks 20 to 25.
B) More time passes from $50,000 to $60,000 than from $5,000 to $10,000.
C) More money is spent from weeks 0 to 10 than from weeks 30 to 40.
D) The total amount spent on the project at the end of the 40th week is approximately $110,000.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
30
How does a tracking Gantt chart's appearance differ from a standard Gantt chart?

A) The tracking Gantt chart has a plot against time on the X1 axis and shows progress against budget on the X2 axis.
B) The tracking Gantt chart is composed of dollar signs that show the relative expense of the activity in comparison with other activities.
C) Each bar in the tracking Gantt chart shows who is responsible for completion of the activity in question.
D) Each bar in the tracking Gantt chart varies from 100% solid if the activity is completed to 100% alternative pattern if the activity has not begun.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
31
A tracking Gantt chart does NOT show:

A) the reason an activity has slipped.
B) which activities are ahead of schedule.
C) which activities are on schedule.
D) which activities are behind schedule.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
32
Measurement mechanisms should include a clear definition of:

A) the project baseline.
B) the reporting relationships among members of the project team.
C) what to measure.
D) trigger points.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
33
An excellent way to coordinate schedules with vendors and suppliers is through the use of:

A) milestones.
B) S-curves that plot expenditures against time.
C) S-curves that plot planned expenditures against time.
D) a tracking Gantt chart.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
34
Milestones are generally considered to be:

A) demotivators for the project team.
B) key project review gates.
C) the end of the project for all team members except the project manager.
D) points where two or more activities merge.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
35
A tracking Gantt chart:

A) monitors costs and budget expenditures.
B) identifies key points in the project's progress.
C) identifies the stage of completion for each task.
D) identifies the performance to budget for the overall project by a certain date.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
36
An S-curve CANNOT be used to:

A) determine whether the project is ahead of budget.
B) determine when the project is behind budget.
C) determine the cause of positive variance.
D) determine whether there is negative variance.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
37
Project goal setting includes setting a baseline plan, which is predicated on:

A) the progress measurement.
B) an accurate work breakdown structure.
C) the type of gap analysis the project team plans to use.
D) the budget and schedule limitations.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
38
Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks. <strong>Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks.  </strong> A) The total project costs in week 10 are less than budgeted. B) The total project costs in week 10 exceed the budgeted cost. C) The project cost more from weeks 25 through 30 than it did in weeks 10 through 15. D) The total amount spent on the project at the end of the 20<sup>th</sup> week is approximately $30,000.

A) The total project costs in week 10 are less than budgeted.
B) The total project costs in week 10 exceed the budgeted cost.
C) The project cost more from weeks 25 through 30 than it did in weeks 10 through 15.
D) The total amount spent on the project at the end of the 20th week is approximately $30,000.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
39
The first step in the control cycle is:

A) setting a goal.
B) measuring progress.
C) comparing actual with planned performance.
D) taking action.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
40
If significant deviations from the project plan are detected, corrective action is taken and then:

A) the monitoring and control cycle begins anew.
B) project goals are adjusted to reflect current reality.
C) the project stakeholders are informed of the budget or time difficulties.
D) the critical chain is reviewed for task dependency.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
41
At the end of week 20, this project has cost $79,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars. <strong>At the end of week 20, this project has cost $79,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars.  </strong> A) 1.11 B) 0.82 C) 0.94 D) 0.90

A) 1.11
B) 0.82
C) 0.94
D) 0.90
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
42
Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. <strong>Use the data to calculate the earned value for the project. All amounts are in thousands of dollars.  </strong> A) $65,500 B) $69,550 C) $71,100 D) $76,125

A) $65,500
B) $69,550
C) $71,100
D) $76,125
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
43
Earned value is:

A) the total budget for the project.
B) a cost estimate of the budgeted resources across the project's life cycle.
C) the real budgeted value of the work that has actually been performed to date.
D) the cumulative total costs incurred in accomplishing the various project work packages.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
44
At the end of week 10, this project has cost $9,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars. <strong>At the end of week 10, this project has cost $9,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars.  </strong> A) 2.5 B) 2.1 C) 1.8 D) 1.5

A) 2.5
B) 2.1
C) 1.8
D) 1.5
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
45
The earned value divided by the actual, cumulative cost of the work to date is the:

A) cost performance index.
B) budgeted cost at completion index.
C) budget efficiency index.
D) schedule performance index.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
46
Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. <strong>Use the data to calculate the earned value for the project. All amounts are in thousands of dollars.  </strong> A) $38,500 B) $43,250 C) $54,750 D) $100,000

A) $38,500
B) $43,250
C) $54,750
D) $100,000
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
47
In earned value management analysis, the cumulative amount of the budget becomes the:

A) planned value.
B) scheduled value.
C) cost basis.
D) cost driver.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
48
Earned value management jointly considers the impact of:

A) time, cost, and planned cost.
B) project performance, planned performance, and cost.
C) performance, cost, and time.
D) planned cost, planned performance, and time.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
49
Which of these tools allows a project team to make future projections of project status based on its current state?

A) tracking Gantt chart
B) milestone chart
C) S-curve
D) earned value management
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
50
The project baseline is established by combining data from the:

A) work breakdown structure and the project budget.
B) time-phased project budget and the PERT chart.
C) S-curve and the project budget.
D) time-phased project budget and the work breakdown structure.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
51
A project manager can calculate the projected budget to completion by using the:

A) budgeted cost at completion index.
B) budget efficiency index.
C) cost performance index.
D) schedule performance index.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
52
Take the factors considered by earned value analysis and subtract those considered by project S-curves. The factor(s) you have remaining are:

A) performance and cost.
B) cost and schedule.
C) time.
D) performance.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
53
Planned value is:

A) the total budget for the project.
B) a cost estimate of the budgeted resources across the project's life cycle.
C) the real budgeted value of the work that has actually been performed to date.
D) the cumulative total costs incurred in accomplishing the various project work packages.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
54
The earned value to date divided by the planned value of work scheduled to be performed is the:

A) cost performance index.
B) budgeted cost at completion index.
C) budget efficiency index.
D) schedule performance index.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
55
Use the data to calculate the schedule performance index for the project for the end of week 20. All amounts are in thousands of dollars. <strong>Use the data to calculate the schedule performance index for the project for the end of week 20. All amounts are in thousands of dollars.  </strong> A) 1.14 B) 0.88 C) 0.94 D) 0.81

A) 1.14
B) 0.88
C) 0.94
D) 0.81
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
56
A project manager can calculate the projected schedule of the project to completion by using the:

A) cost performance index.
B) schedule performance index.
C) budgeted cost at completion index.
D) budget efficiency index.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
57
Use the data to calculate the schedule performance index for the project for the end of week 10. All amounts are in thousands of dollars. <strong>Use the data to calculate the schedule performance index for the project for the end of week 10. All amounts are in thousands of dollars.  </strong> A) 1.24 B) 0.93 C) 0.81 D) 0.76

A) 1.24
B) 0.93
C) 0.81
D) 0.76
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
58
Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. <strong>Use the data to calculate the earned value for the project. All amounts are in thousands of dollars.  </strong> A) $38,500 B) $46,550 C) $56,750 D) $61,125

A) $38,500
B) $46,550
C) $56,750
D) $61,125
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
59
The first step in earned value management is to:

A) create the activity and resource usage schedules.
B) develop a time-phased budget that shows expenditures across the project's life.
C) total the actual costs of doing each task to arrive at the actual cost of work performed.
D) clearly define each activity that will be performed including its resource needs and budget.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
60
Take the factors considered by earned value analysis and subtract those considered by tracking Gantt charts. The factor(s) you have remaining are:

A) cost.
B) cost and schedule.
C) schedule and performance.
D) performance.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
61
The budget variance is calculated as:

A) earned value minus planned value.
B) planned value minus actual cost.
C) earned value minus actual cost.
D) cost minus planned value.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
62
A recurring problem with establishing accurate or meaningful EVM results has to do with:

A) the 0/100 rule.
B) over-reliance on the S-curve.
C) the need to recognize the human factor.
D) the need to satisfy stakeholders within budget and time parameters.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
63
Use the earned value table for Project Terrace to determine their schedule variance if all dollar amounts are in hundreds. <strong>Use the earned value table for Project Terrace to determine their schedule variance if all dollar amounts are in hundreds.  </strong> A) $100 B) $120 C) $1,200 D) $200

A) $100
B) $120
C) $1,200
D) $200
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
64
In the build-up stage of a successful project, it is important that:

A) an adequate budget exists.
B) top management support exists.
C) the project personnel are in a state of flux.
D) there is a clear sense of earned value management.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
65
Use the earned value table for Project Terrace to calculate their schedule performance index if all dollar amounts are in hundreds. <strong>Use the earned value table for Project Terrace to calculate their schedule performance index if all dollar amounts are in hundreds.  </strong> A) 0.90 B) 0.80 C) 1.12 D) 1.20

A) 0.90
B) 0.80
C) 1.12
D) 1.20
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
66
Each activity contained a series of milestones that represented a previously agreed-upon amount of work. Once the low graffiti was erased, 35% of the activity had been completed and once the mid-level graffiti was erased, 70% of the activity had been completed. This project manager was clearly in the:

A) percentage complete camp.
B) micromanagement camp.
C) 35/70 camp.
D) 3K specifications camp.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
67
Funding problems are a key success inhibitor in the:

A) build-up phase.
B) close-out phase.
C) main phase.
D) formation phase.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
68
Use the earned value table for Project Terrace to calculate their estimated time to completion (all dollar amounts are in hundreds). <strong>Use the earned value table for Project Terrace to calculate their estimated time to completion (all dollar amounts are in hundreds).  </strong> A) 14.2 days B) 15.0 days C) 18.4 days D) 16.8 days

A) 14.2 days
B) 15.0 days
C) 18.4 days
D) 16.8 days
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
69
One of these things is NOT like the others (that happen to directly predict project success). The one that's different is:

A) lack of budgetary pressure.
B) adequacy of project structure and control.
C) project coordination and relations among stakeholders.
D) the tenure of the project manager.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
70
In the formation stage, failed projects are more likely to have:

A) technical limitations.
B) personal ambition.
C) clear objectives.
D) team motivation.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
71
If an activity's progress is defined as 0% until the moment is complete, the project manager is using:

A) the 50/50 rule.
B) the all or nothing rule.
C) the 0/100 rule.
D) the Do Not Pass Go rule.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
72
The critical success factor that relates to the underlying purpose for the project is the:

A) project mission.
B) technical acceptance.
C) technical tasks.
D) client consultation.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
73
Project Terrace has an actual cost of $3,000, but their earned value (all dollar amounts are in hundreds) table appears below. What is their cost variance? <strong>Project Terrace has an actual cost of $3,000, but their earned value (all dollar amounts are in hundreds) table appears below. What is their cost variance?  </strong> A) $250 B) -$250 C) 1.08 D) 0.92

A) $250
B) -$250
C) 1.08
D) 0.92
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
74
In earned value management, schedule variance is defined as:

A) the difference between the earned value and the actual cost.
B) the difference between the earned value and the planned value.
C) the difference between the actual cost and the planned value.
D) the difference between the cost and schedule performance indices multiplied by the budgeted cost at completion.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
75
An unmotivated team is a key success inhibitor in every project stage with the exception of the:

A) main phase.
B) formation phase.
C) close-out phase.
D) build-up phase.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
76
Very short work packages would be better managed by:

A) the percentage complete rule.
B) the 0/100 rule.
C) the caveat emptor rule.
D) the prior knowledge rule.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
77
Earned value management at the portfolio level requires:

A) a single project manager with a single metric system.
B) aggregation of all earned value measures across the firm's entire project portfolio.
C) only positive variances for both budget and schedule.
D) only negative variances for both budget and schedule.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
78
Once an activity is begun, it is assumed to be half done under the:

A) "once begun, half done" rule.
B) minimal effort rule.
C) midway rule.
D) 50/50 rule.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
79
Use the earned value table for Project Terrace to calculate their estimated cost to completion (all dollar amounts are in hundreds). <strong>Use the earned value table for Project Terrace to calculate their estimated cost to completion (all dollar amounts are in hundreds).  </strong> A) $4,285 B) $4,800 C) $4,532 D) $3,604

A) $4,285
B) $4,800
C) $4,532
D) $3,604
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
80
Use the earned value table for Project Terrace to determine the earned value (all dollar amounts are in hundreds). <strong>Use the earned value table for Project Terrace to determine the earned value (all dollar amounts are in hundreds).  </strong> A) $325 B) $7600 C) $4800 D) $3250

A) $325
B) $7600
C) $4800
D) $3250
Unlock Deck
Unlock for access to all 98 flashcards in this deck.