The delivered-equipment cost for setting up a production and assembly line for high-sensitivity, gas-damped accelerometers is $650,000. If the direct cost and indirect cost factors are 1.82 and 0.31, respectively, and both factors apply to delivered-equipment cost, the total plant cost estimate is approximately:
A) $2,034,500
B) $1,734,500
C) $1,384,500
D) $1,183,000
A) $2,034,500
B) $1,734,500
C) $1,384,500
D) $1,183,000
Explanation
f is the factor for each cost ...