Exercise 6

On average, the manufacturing (processing) time spent per order is approximately four days. In addition, a typical order spends four days moving from process to process, three days in storage, and two days in inspection. For an average order, what is the manufacturing cycle efficiency?

Step-by-step solution
Verified
like image
like image

Step 1 of 2

The formula for manufacturing cycle efficiency is as follows:

    <div class=answer> The formula for manufacturing cycle efficiency is as follows: