Exercise 45

If a customer order is placed on May 1 and the company expects to begin processing it on May 10, and the order is shipped on May 20, the cycle time is then how many days long?

Step-by-step solution
Verified
like image
like image

Step 1 of 2

Manufacturing cycle:

Manufacturing cycle is the process when a product is started to be manufactured to reach the product to the consumer. There are some steps which is included in the manufacturing cycle that is design and development, organize, manufacturing, selling and reach the product to the customer with services.


Step 2 of 2