Deck 14: Project Closure

Full screen (f)
exit full mode
Question
The section of the final project report that new project teams are likely to find most useful is the:

A)Analysis
B)Recommendations
C)Classification of project
D)Lessons learned
E)Strategic objectives
Use Space or
up arrow
down arrow
to flip the card.
Question
Under which heading of the Wrap-up closure checklist should the question "Has an in-depth project review and evaluation interview with the customer been conducted?" be answered.

A)Team
B)Vendors/contractors
C)Customer/Users
D)Equipment and facilities
E)Profit and loss statement
Question
When a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change this is an example of:

A)Normal
B)Premature
C)Perpetual
D)Failed Project
E)Changed Priority
Question
What is not a wrap-up closure activity?

A)Facilities
B)Vendors
C)Customer
D)Profit report
E)Report
Question
The most common circumstance for project closure is simply a ________ project.

A)Completed
B)Overdue
C)Overbudget
D)Under achiveing
E)All the above are correct
Question
Closing out _________ is often messy and filled with untied ends.

A)Project review meetings
B)Reports
C)Invoices
D)Teams
E)Contracts
Question
Releasing the project team typically occurs _________ during the closure phase.

A)Gradually
B)Rarely
C)Without bombast
D)Rapidly
E)All at once
Question
Project mission and objectives, procedures and systems used, and organization resources used typically appear in the _____ section of the final project report.

A)Analysis
B)Recommendations
C)Classification of project
D)Lessons learned
E)Strategic objectives
Question
Many projects will fail because of circumstances beyond the control of the project team is called:

A)Normal
B)Premature
C)Perpetual
D)Failed Project
E)Changed Priority
Question
Which is not part of the team portion of the Wrap-up closure checklist?

A)Has a schedule for reducing project staff been developed and accepted?
B)Has staff been offered outplacement services and career counseling activities?
C)Have performance reviews for team members been conducted?
D)Has staff been released or notified of new assignments?
E)All are included.
Question
In the Snapshot from Practice, New Balls Goes Flat in NBA, is an example of a project gone wrong when the _______ is/are not consulted.

A)Manufacture
B)Equipment and facilities managers
C)End-users
D)Project manager
E)The Fans
Question
The content of the final report typically includes the following topics:

A)Lessons learned
B)Review and analysis
C)Recommendations
D)Executive summary
E)All the above are correct
Question
Implementing closedown includes the following major activities except:

A)Getting delivery acceptance from the customer.
B)Shutting down resources and releasing to new uses.
C)Closing accounts and seeing all bills are paid.
D)E-mail the project team that the project is complete.
E)Creating a final report.
Question
Items technical in nature and focus on solutions to problems that surfaced would typically appear in the _____ section of the final project report.

A)Analysis
B)Recommendations
C)Classification of project
D)Lessons learned
E)Strategic objectives
Question
This type of closure occurs when the project may never seem to end.This is considered to be ___________ closure.

A)Normal
B)Premature
C)Perpetual
D)Changed Priority
E)Failed Project
Question
When the project may be completed early with some parts of the project eliminated this is considered to be ___________ closure.

A)Normal
B)Premature
C)Perpetual
D)Changed Priority
E)Failed Project
Question
Under which heading of the Wrap-up closure checklist should the question "Have project accounts been finalized and all billing closed?" be answered.

A)Team
B)Vendors/contractors
C)Customer/Users
D)Equipment and facilities
E)Profit and loss statement
Question
__________ of lessons learned are designed to improve performance on current and future projects.

A)Retrospectives
B)Corrective action plans
C)Introspective
D)Culmination
E)Evolution
Question
Information on the project type, size, number of staff, and technology level would be included in which section of the audit report?

A)Analysis
B)Recommendations
C)Classification of project
D)Lessons learned
E)Strategic objectives
Question
Corrective actions that should take place (such as shifting to more resilient building material) would typically appear in the _____ section of the final project report.

A)Analysis
B)Recommendations
C)Classification of project
D)Lessons learned
E)Strategic objectives
Question
The project closure process includes all of the following except:

A)Shutting down resources and releasing to new uses
B)Reassigning project team members
C)Conduct an audit
D)Getting delivery acceptance from the customer
E)Closing accounts and seeing all bills are paid
Question
________ is the most common circumstance for project closure is simply a completed project.
Question
A schedule for reducing project staff been developed and accepted is a question that is asked in the completion of the ___________.
Question
In the Snapshot from Practice, the results of analyzing the Katrina hurricane resulted in a new evaluation plan from:

A)The state legislature
B)The governor of Louisiana
C)The city of New Orleans
D)The Red Cross
E)The national guard
Question
The ________ section of the final project report includes succinct, factual review statements of the project such as, project mission and objectives, procedures and systems used, and organizational resources used.
Question
____________ are usually easy to identify and easy for a review group to close down.
Question
Projects in process may need to be altered or canceled.Thus, a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change.This is called __________.
Question
____________ begins with a review of the strategic intent of the project, selection criteria, project charter, project objectives, project scope, and acceptance criteria.

A)Process Review
B)Project Overview
C)Analysis
D)Recommendations
E)Directing
Question
In the Research Highlight, Chaos: Software Projects, the criterion which was deemed the most important for project success was

A)Realistic expectations
B)Hard-working, focused staff
C)User involvement
D)Proper planning
E)Clear vision and objectives
Question
The most common circumstance for project closure is:

A)Premature completion with some features eliminated
B)Project completion meeting costs, schedule, and quality
C)Project completion after modification of costs, schedule, or quality
D)Project termination due to technical difficulties
E)Perpetual projects that seem to go on and on before completion
Question
The ________ section of the final project report are often technical in nature and focus on solutions to problems that surfaced.
Question
The project may be completed early with some parts of the project eliminated is known as _________.
Question
Perhaps _________ are the most valuable contribution of the closure process.
Question
In organizations where projects are managed within a ____________, the team member's area manager, not the project manager, is responsible for assessing performance.

A)Functional organization
B)Matrix organization
C)Flat organization
D)Both A and C are correct
E)A, B, and C are all correct
Question
More and more companies are discarding the traditional superior-subordinate performance feedback process and replacing it with:

A)Critical incidences review
B)Management by objectives
C)The 360-degree feedback
D)Both B and C are correct
E)A, B, and C are all correct
Question
Some organizations have project closure checklists of over _____ wrap-up tasks!
Question
The typical mechanism for evaluation of teams is normally:

A)A survey completed by the team members
B)A personal interview of each team member
C)An analysis by an outside consultant
D)A survey completed by members of top management
E)A survey completed by the internal or external customers
Question
Performance evaluations of project teams should:

A)Provide the basis for individual development
B)Provide the basis for participation on future projects
C)Provide the basis for salary increases
D)Both A and C are correct
E)A, B, and C are all correct
Question
The summary simply highlights the key findings and facts relating to the project implementation is called the ___________.
Question
Project closures can fall into all of the following categories except:

A)Premature
B)Perpetual
C)Failed
D)Changed priority
E)All of these are categories for project closure
Question
The most common reason given for not creating lessons learned is _________.
Question
In a Perpetual project the most common circumstance for project closure is simply a completed project.
Question
A __________ is a guide who leads the project team through an analysis of project activities that went well, what needs improvement, and development of a follow-up action plan with goals and accountability.
Question
In some ____________, project managers conduct the performance reviews, while area managers are responsible for pay reviews.
Question
Project managers should be ________ giving team members feedback throughout the project so that individual team members can have a pretty good idea how well they have performed and how the manager feels before the formal meeting.
Question
An upbeat, festive celebration brings closure to the enjoyable experiences everyone has had and the need to say good-bye is considered to be a ____________.
Question
When a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change this is an example of change changed priority.
Question
Part of the content of the final report typically includes profit made on the project.
Question
In a Premature projects, the project may be completed early with some parts of the project eliminated.
Question
_________ are binary; either you have reached requirements completion or you have not.
Question
__________ represent an analysis carried out during and shortly after the project life cycle; they attempt to capture positive and negative project learning.
Question
Retrospectives of lessons learned are designed to improve performance on current and future projects.
Question
The Standish Group International's market research on software projects, called Chaos showed that ___ percent of all software projects are cancelled before completion.
Question
A completed ___________ is a good example of the need to work out the details in advance.
Question
A project closure is considered ________ if it never seems to end due to constant "add-ons" in attempt to improve the project outcome.
Question
The project manager's challenge is to keep the project team focused on the remaining project activities and delivery to the customer until the project is complete.
Question
The ________ feedback approach gathers anonymous feedback solicited from others is compared with the individual's self-evaluations, the individual may form a more realistic picture of her strengths and weaknesses.
Question
The purpose of ____________ is to assess how well the project team, team members, and project manager performed.
Question
The _________ of projects by characteristics allows prospective readers, teams, and project managers to be selective in the search and use of report content.
Question
A ________ is a methodology that analyzes a past project event to determine what worked and what didn't, develops lessons learned, and creates an action plan that ensures lessons learned are used to improve management of future projects.
Question
Identify the three major deliverables for project closure.
Question
Some organizations rely simply on an informal discussion between the project manager and the project member while other organizations require project managers to submit written evaluations that describe and assess an individual's performance on a project.
Question
How does the project managers meet the challenge to keep the project team focused on the remaining project activities and delivery to the customer until the project is complete?
Question
What are the six major activities implementing project closedown?
Question
Lessons learned from the Katrina disaster are not limited to the military.Almost every agency and support group, such as individuals, communities, churches, and other groups, has developed lessons learned from their project response experience.
Question
A 360-degree performance evaluation includes feedback from peers, project managers, subordinates, and even customers.
Question
Implementing closedown includes getting delivery acceptance from the customer.
Question
Project Summary is the summary that simply highlights the key findings and facts relating to the project implementation.
Question
A project closure where the project is completed early with some parts of the project eliminated would be classified as project failure.
Question
Analysis examines in detail the underlying causes of problems, issues, and successes.
Question
The most common circumstance for project closure is simply a completed project such as building a new facility or creating a customized information system.
Question
Project managers should, when possible, draw comparisons to other team members when conducting individual team member reviews.
Question
Performance evaluations of project team members are typically well done because the evaluations are conducted by the team member's home department.
Question
The key requirement in selection of the facilitator is one who is the end-user.
Question
Identify the four areas of the project closure checklist.
Question
The maximum items on a checklist for closing a project are 50.
Question
Evaluation of individuals implies measurement against all team members.
Question
Retrospective methodology is one positive step toward ensuring lessons learned are developed and implemented.
Question
Performance appraisals generally fulfill five important functions.
Question
The ideal scenario is to have the team member's next assignment ready when project completion is announced.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/88
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 14: Project Closure
1
The section of the final project report that new project teams are likely to find most useful is the:

A)Analysis
B)Recommendations
C)Classification of project
D)Lessons learned
E)Strategic objectives
D
Explanation: In practice, new project teams studying past project reports similar to the project they are about to start have found past review reports very useful.
2
Under which heading of the Wrap-up closure checklist should the question "Has an in-depth project review and evaluation interview with the customer been conducted?" be answered.

A)Team
B)Vendors/contractors
C)Customer/Users
D)Equipment and facilities
E)Profit and loss statement
C
3
When a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change this is an example of:

A)Normal
B)Premature
C)Perpetual
D)Failed Project
E)Changed Priority
E
Explanation: Organizations' priorities often change and strategy shifts directions.For example, during the 2008-10 financial crisis organizations shifted their focus from money making projects to cost savings projects.The oversight group continually revises project selection priorities to reflect changes in organizational direction.Projects in process may need to be altered or canceled.Thus, a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change.When priorities change, projects in process may need to be altered or canceled.
4
What is not a wrap-up closure activity?

A)Facilities
B)Vendors
C)Customer
D)Profit report
E)Report
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
5
The most common circumstance for project closure is simply a ________ project.

A)Completed
B)Overdue
C)Overbudget
D)Under achiveing
E)All the above are correct
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
6
Closing out _________ is often messy and filled with untied ends.

A)Project review meetings
B)Reports
C)Invoices
D)Teams
E)Contracts
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
7
Releasing the project team typically occurs _________ during the closure phase.

A)Gradually
B)Rarely
C)Without bombast
D)Rapidly
E)All at once
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
8
Project mission and objectives, procedures and systems used, and organization resources used typically appear in the _____ section of the final project report.

A)Analysis
B)Recommendations
C)Classification of project
D)Lessons learned
E)Strategic objectives
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
9
Many projects will fail because of circumstances beyond the control of the project team is called:

A)Normal
B)Premature
C)Perpetual
D)Failed Project
E)Changed Priority
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
10
Which is not part of the team portion of the Wrap-up closure checklist?

A)Has a schedule for reducing project staff been developed and accepted?
B)Has staff been offered outplacement services and career counseling activities?
C)Have performance reviews for team members been conducted?
D)Has staff been released or notified of new assignments?
E)All are included.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
11
In the Snapshot from Practice, New Balls Goes Flat in NBA, is an example of a project gone wrong when the _______ is/are not consulted.

A)Manufacture
B)Equipment and facilities managers
C)End-users
D)Project manager
E)The Fans
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
12
The content of the final report typically includes the following topics:

A)Lessons learned
B)Review and analysis
C)Recommendations
D)Executive summary
E)All the above are correct
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
13
Implementing closedown includes the following major activities except:

A)Getting delivery acceptance from the customer.
B)Shutting down resources and releasing to new uses.
C)Closing accounts and seeing all bills are paid.
D)E-mail the project team that the project is complete.
E)Creating a final report.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
14
Items technical in nature and focus on solutions to problems that surfaced would typically appear in the _____ section of the final project report.

A)Analysis
B)Recommendations
C)Classification of project
D)Lessons learned
E)Strategic objectives
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
15
This type of closure occurs when the project may never seem to end.This is considered to be ___________ closure.

A)Normal
B)Premature
C)Perpetual
D)Changed Priority
E)Failed Project
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
16
When the project may be completed early with some parts of the project eliminated this is considered to be ___________ closure.

A)Normal
B)Premature
C)Perpetual
D)Changed Priority
E)Failed Project
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
17
Under which heading of the Wrap-up closure checklist should the question "Have project accounts been finalized and all billing closed?" be answered.

A)Team
B)Vendors/contractors
C)Customer/Users
D)Equipment and facilities
E)Profit and loss statement
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
18
__________ of lessons learned are designed to improve performance on current and future projects.

A)Retrospectives
B)Corrective action plans
C)Introspective
D)Culmination
E)Evolution
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
19
Information on the project type, size, number of staff, and technology level would be included in which section of the audit report?

A)Analysis
B)Recommendations
C)Classification of project
D)Lessons learned
E)Strategic objectives
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
20
Corrective actions that should take place (such as shifting to more resilient building material) would typically appear in the _____ section of the final project report.

A)Analysis
B)Recommendations
C)Classification of project
D)Lessons learned
E)Strategic objectives
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
21
The project closure process includes all of the following except:

A)Shutting down resources and releasing to new uses
B)Reassigning project team members
C)Conduct an audit
D)Getting delivery acceptance from the customer
E)Closing accounts and seeing all bills are paid
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
22
________ is the most common circumstance for project closure is simply a completed project.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
23
A schedule for reducing project staff been developed and accepted is a question that is asked in the completion of the ___________.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
24
In the Snapshot from Practice, the results of analyzing the Katrina hurricane resulted in a new evaluation plan from:

A)The state legislature
B)The governor of Louisiana
C)The city of New Orleans
D)The Red Cross
E)The national guard
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
25
The ________ section of the final project report includes succinct, factual review statements of the project such as, project mission and objectives, procedures and systems used, and organizational resources used.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
26
____________ are usually easy to identify and easy for a review group to close down.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
27
Projects in process may need to be altered or canceled.Thus, a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change.This is called __________.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
28
____________ begins with a review of the strategic intent of the project, selection criteria, project charter, project objectives, project scope, and acceptance criteria.

A)Process Review
B)Project Overview
C)Analysis
D)Recommendations
E)Directing
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
29
In the Research Highlight, Chaos: Software Projects, the criterion which was deemed the most important for project success was

A)Realistic expectations
B)Hard-working, focused staff
C)User involvement
D)Proper planning
E)Clear vision and objectives
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
30
The most common circumstance for project closure is:

A)Premature completion with some features eliminated
B)Project completion meeting costs, schedule, and quality
C)Project completion after modification of costs, schedule, or quality
D)Project termination due to technical difficulties
E)Perpetual projects that seem to go on and on before completion
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
31
The ________ section of the final project report are often technical in nature and focus on solutions to problems that surfaced.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
32
The project may be completed early with some parts of the project eliminated is known as _________.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
33
Perhaps _________ are the most valuable contribution of the closure process.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
34
In organizations where projects are managed within a ____________, the team member's area manager, not the project manager, is responsible for assessing performance.

A)Functional organization
B)Matrix organization
C)Flat organization
D)Both A and C are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
35
More and more companies are discarding the traditional superior-subordinate performance feedback process and replacing it with:

A)Critical incidences review
B)Management by objectives
C)The 360-degree feedback
D)Both B and C are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
36
Some organizations have project closure checklists of over _____ wrap-up tasks!
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
37
The typical mechanism for evaluation of teams is normally:

A)A survey completed by the team members
B)A personal interview of each team member
C)An analysis by an outside consultant
D)A survey completed by members of top management
E)A survey completed by the internal or external customers
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
38
Performance evaluations of project teams should:

A)Provide the basis for individual development
B)Provide the basis for participation on future projects
C)Provide the basis for salary increases
D)Both A and C are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
39
The summary simply highlights the key findings and facts relating to the project implementation is called the ___________.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
40
Project closures can fall into all of the following categories except:

A)Premature
B)Perpetual
C)Failed
D)Changed priority
E)All of these are categories for project closure
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
41
The most common reason given for not creating lessons learned is _________.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
42
In a Perpetual project the most common circumstance for project closure is simply a completed project.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
43
A __________ is a guide who leads the project team through an analysis of project activities that went well, what needs improvement, and development of a follow-up action plan with goals and accountability.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
44
In some ____________, project managers conduct the performance reviews, while area managers are responsible for pay reviews.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
45
Project managers should be ________ giving team members feedback throughout the project so that individual team members can have a pretty good idea how well they have performed and how the manager feels before the formal meeting.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
46
An upbeat, festive celebration brings closure to the enjoyable experiences everyone has had and the need to say good-bye is considered to be a ____________.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
47
When a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change this is an example of change changed priority.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
48
Part of the content of the final report typically includes profit made on the project.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
49
In a Premature projects, the project may be completed early with some parts of the project eliminated.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
50
_________ are binary; either you have reached requirements completion or you have not.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
51
__________ represent an analysis carried out during and shortly after the project life cycle; they attempt to capture positive and negative project learning.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
52
Retrospectives of lessons learned are designed to improve performance on current and future projects.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
53
The Standish Group International's market research on software projects, called Chaos showed that ___ percent of all software projects are cancelled before completion.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
54
A completed ___________ is a good example of the need to work out the details in advance.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
55
A project closure is considered ________ if it never seems to end due to constant "add-ons" in attempt to improve the project outcome.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
56
The project manager's challenge is to keep the project team focused on the remaining project activities and delivery to the customer until the project is complete.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
57
The ________ feedback approach gathers anonymous feedback solicited from others is compared with the individual's self-evaluations, the individual may form a more realistic picture of her strengths and weaknesses.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
58
The purpose of ____________ is to assess how well the project team, team members, and project manager performed.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
59
The _________ of projects by characteristics allows prospective readers, teams, and project managers to be selective in the search and use of report content.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
60
A ________ is a methodology that analyzes a past project event to determine what worked and what didn't, develops lessons learned, and creates an action plan that ensures lessons learned are used to improve management of future projects.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
61
Identify the three major deliverables for project closure.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
62
Some organizations rely simply on an informal discussion between the project manager and the project member while other organizations require project managers to submit written evaluations that describe and assess an individual's performance on a project.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
63
How does the project managers meet the challenge to keep the project team focused on the remaining project activities and delivery to the customer until the project is complete?
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
64
What are the six major activities implementing project closedown?
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
65
Lessons learned from the Katrina disaster are not limited to the military.Almost every agency and support group, such as individuals, communities, churches, and other groups, has developed lessons learned from their project response experience.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
66
A 360-degree performance evaluation includes feedback from peers, project managers, subordinates, and even customers.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
67
Implementing closedown includes getting delivery acceptance from the customer.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
68
Project Summary is the summary that simply highlights the key findings and facts relating to the project implementation.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
69
A project closure where the project is completed early with some parts of the project eliminated would be classified as project failure.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
70
Analysis examines in detail the underlying causes of problems, issues, and successes.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
71
The most common circumstance for project closure is simply a completed project such as building a new facility or creating a customized information system.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
72
Project managers should, when possible, draw comparisons to other team members when conducting individual team member reviews.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
73
Performance evaluations of project team members are typically well done because the evaluations are conducted by the team member's home department.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
74
The key requirement in selection of the facilitator is one who is the end-user.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
75
Identify the four areas of the project closure checklist.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
76
The maximum items on a checklist for closing a project are 50.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
77
Evaluation of individuals implies measurement against all team members.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
78
Retrospective methodology is one positive step toward ensuring lessons learned are developed and implemented.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
79
Performance appraisals generally fulfill five important functions.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
80
The ideal scenario is to have the team member's next assignment ready when project completion is announced.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 88 flashcards in this deck.