Deck 4: Defining the Project

Full screen (f)
exit full mode
Question
The tool used to assist in making project trade-offs between schedule, budget, and performance objectives is called a

A)Responsibility matrix
B)Work breakdown structure
C)Project priority matrix
D)Work package
E)Criterion matrix
Use Space or
up arrow
down arrow
to flip the card.
Question
All of the following are usually included in a work package except

A)What will be done?
B)The time needed to complete the work.
C)A single person who is responsible for its completion.
D)All the costs for the work package.
E)All of these are included in a work package.
Question
In reviewing the project plan, Susan sees that the first prototype is due by October 12.This would be best classified as a

A)Project target
B)Limit item
C)Milestone
D)Project objective
E)Critical goal
Question
Research shows the most frequently mentioned barrier to project success is

A)Not enough budget resources
B)Poor performance by team members
C)Weak project leadership
D)Poorly defined scope or mission
E)Political in-fighting
Question
An expected output over the life of a project would be classified as

A)A deliverable
B)A product
C)An end object
D)An objective
E)A target
Question
Which of the following is not one of the basic classifications of project priorities?

A)Profit
B)Cost
C)Time
D)Performance
E)All of these are basic classifications
Question
"To construct a high-quality, custom home within five months at costs not to exceed $150,000" is best classified as

A)A deliverable
B)A milestone
C)An objective
D)A limit
E)An exclusion
Question
Linda has just been assigned a project to develop a new advertising campaign for an established product.Her first step should be to

A)Establish project priorities
B)Define the project scope
C)Verify the budget available
D)Assign team members to work on the project
E)Determine the required completion date
Question
The method used to collect information to use through all phases of the project life cycle is called

A)Responsibility matrix
B)Organization breakdown structure
C)Work breakdown structure
D)Priority matrix
E)Work package
Question
The lowest element in the hierarchical breakdown of the WBS is

A)A deliverable
B)A work package
C)A cost account
D)A lowest sub deliverable
E)An object
Question
The highest element in the hierarchical breakdown of the WBS is

A)A work package
B)Sub deliverables
C)A cost account
D)Major deliverables
E)The project
Question
Which of the following is not one of the items that would appear on a project scope checklist?

A)Deliverables
B)Technical requirements
C)Objectives
D)Work breakdown structure
E)Reviews with customer
Question
All of the following are true about work packages except

A)Consume resources
B)Assigned to only one manager
C)Have medium to long duration
D)Definitive starts and stops dates
E)All of these are true
Question
If a project criterion indicates that the project must meet a specific date, that criterion is classified as

A)Constrained
B)Enhanced
C)Accepted
D)Limited
E)Fixed
Question
Scott has just been given a project that has a specific target date.After discussion with top management he finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets.The target date is best classified as

A)Constrain
B)Enhance
C)Accept
D)Limit
E)Optional
Question
The first step in creating the necessary information to manage a project is to

A)Establish project priorities
B)Define the project scope
C)Verify the budget available
D)Assign team members to work on the project
E)Determine the required completion date
Question
The first step of project scope definition is to

A)Analyze the strategic plan
B)Analyze the current budget plan
C)Meet with team members
D)Select team members
E)Define the overall objective to meet the customer's needs
Question
The second step in the defining of a project would be to

A)Analyze the strategic plan
B)Analyze the current budget plan
C)Establish project priorities
D)Select team members
E)Define the major objectives to meet the customer's needs
Question
Jose is looking at a document that outlines the specific tasks and subtasks required to complete the writing of a technical support manual.The method that was probably used to develop the document is most likely

A)Responsibility matrix
B)Organization breakdown structure
C)Work breakdown structure
D)Priority matrix
E)Work package
Question
The ability of 911 emergency systems to identify the caller's phone number and location are considered to be a

A)Technical requirement
B)Milestone
C)Project limit
D)Project exclusion
E)Project deliverable
Question
If a project is small or of narrow scope and does not require an elaborate system, which of the following is a good choice?

A)Responsibility matrix
B)Organization breakdown structure
C)Work breakdown structure
D)Priority matrix
E)Process breakdown structure
Question
The project scope statement indicates that the client is responsible for training the people who will be using the equipment and that the project team will train the client's trainers.This is an example of:

A)Project objectives
B)Deliverables
C)Limits and exclusions
D)Technical requirements
E)Milestones
Question
A selective outline of the project that ensures the identification of all tasks and an understanding of what is to be done is called a _______________.
Question
A project parameter such as completion date or cost is ________ if it is fixed and must be met.
Question
Creating an extranet website or an internal software database system would be most closely associated with the

A)Responsibility matrix
B)Organization breakdown structure
C)Work breakdown structure
D)Priority matrix
E)Process breakdown structure
Question
The primary purpose of the first step of defining a project is to identify the ________ for the end user and to focus project plans.
Question
In making project trade-offs, a criteria that is allowed to not meet the original target is classified as ________.
Question
The need for a computer to function in countries having different electrical systems is an example of a ________.
Question
Which of the follow is least likely to be included in a Work Package?

A)Materials
B)Labor
C)Overhead
D)Duration
E)Responsibilities
Question
The integration of project work packages within the organization's management structure is known as

A)Responsibility matrix
B)Organization breakdown structure
C)Work breakdown structure
D)Priority matrix
E)Process breakdown structure
Question
Developing a ________ provides a forum for clearly establishing priorities with customers and top management so as to create shared expectations and avoid misunderstandings.
Question
The first step in planning any project is to ________.
Question
The final step in the creation of a Work Breakdown Structure is to

A)Code the WBS for tracking
B)Assign the cost account to a manager
C)Assign the work package to a manager
D)Develop the responsibility matrix
E)All of these are included in the final step
Question
The agreement that training will be the responsibility of the customer is an example of a project ________.
Question
The intersection of the WBS and the OBS is called the

A)Responsibility matrix
B)Priority matrix
C)Work package
D)Cost account
E)Project overlap
Question
The Snapshot from Practice dealing with Big Bertha II illustrated how important a project's __________ is to the successful completion of a project.

A)Objective
B)Deliverables
C)Technical requirements
D)Milestones
E)Limits and exclusions
Question
Taking advantage of opportunities to reduce costs or accelerate the schedule are examples of project criteria being classified as ________.
Question
Which of the following is a good example of a Process Breakdown Structure?

A)New car prototype
B)New software program
C)New computer hardware
D)New sports stadium
E)New project management book
Question
The tendency for the project deliverables to expand over time-usually by changing requirements, specifications, and priorities-is called:

A)Scope erosion
B)Scope creep
C)Project bloat
D)Scope enhancement
E)Project add-ons
Question
Significant events in a project that occur at a specific point in time, are natural control points, and are easily recognized by project participants are known as ___________.
Question
Practice suggests that a work package should not exceed ________ workdays or one reporting period.
Question
The purposes of the ____________ are to provide a framework to summarize organization unit work performance, identify organization units responsible for work packages, and tie the organizational unit to cost control accounts.
Question
Once the __________ has been established, it is the basis for making trade-off decisions later in the project.
Question
Studies suggest that there is a strong correlation between project success and clear project scope definition.
Question
The most detailed element in the hierarchical breakdown of the project work to be accomplished is known as the ________.
Question
One of the items included on a project scope checklist is the reviews with the customer.
Question
A(n) ________ is a grouping of work packages for monitoring progress and responsibility.
Question
The result of subdividing the work of a project into smaller and smaller work elements is called ________.
Question
Project scope describes what you expect to deliver to your customers when the project is complete.
Question
The development of a work breakdown structure with appropriate dates and budget is usually accomplished in a single iteration.
Question
Quality and the ultimate success of a project are traditionally defined as meeting or exceeding the expectations of the customer or management.
Question
The gradual expansion of project requirements during the execution of project is known as __________.
Question
The criteria for project success include attaining objectives relating to cost, schedule, and revenue.
Question
The Work Breakdown Structure is an outline of the project with different levels of __________.
Question
The final step in the defining of a project is focused on assigning ________ to each of the work packages.
Question
The process of assigning specific work packages to a particular group or person within the organization is called ________.
Question
The ________ summarizes, in graphic format, the tasks to be accomplished and who is responsible for what on a given project.
Question
The most commonly used method for coding the WBS is __________.
Question
In a work breakdown structure the ________ is the focal point because all budgets, work assignments, time, cost, and technical performance come together at that point.
Question
In a ________ the project is organized around phases or groups of activities rather than the more conventional deliverables.
Question
The hierarchical work breakdown structure can be used to represent the need for information at various levels of management.
Question
Statements of project scope are sometimes referred to as Statements of Work or Project Charters.
Question
Basically, the WBS is an outline of the project with different levels of detail.
Question
If a project criterion should be optimized if at all possible, it is classified as being constrained.
Question
For large companies, the organization breakdown structure is used rather than the work breakdown structure.
Question
In a work breakdown structure deliverables are ignored and replaced with activities or tasks that have been grouped in phases.
Question
Identify and briefly describe the six elements on the recommended project scope checklist.
Question
Responsibility matrices are used primarily with small and medium sized projects and have limited use in large projects.
Question
Integrating a project's work packages within the organization's management structure is known as work breakdown structure.
Question
The intersection of the WBS and the OBS represents a control point, called a cost account.
Question
A typical responsibility matrix will include not only those responsible for a specific task but also those who supply support and assistance.
Question
The most commonly used scheme for coding the work breakdown structure is to use a department project number assigned by the accounting department.
Question
Identify and briefly describe the five steps in defining a project.
Question
Reviews with customers only refers to projects with external customers who are paying for the project.
Question
Scope definitions are usually brief with only one or two pages being typical for small projects.
Question
The intersection of work packages and the organization unit creates a project control point called a cost account.
Question
A work breakdown structure is frequently used on projects such as software development where the project is focused on activities rather than deliverables.
Question
In general, work packages should not exceed 10 work days.
Question
In terms of project management, what is a deliverable and give an example.
Question
In a Work Breakdown Structure for a software development project, the typical structure follows the major phases of software development.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/89
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 4: Defining the Project
1
The tool used to assist in making project trade-offs between schedule, budget, and performance objectives is called a

A)Responsibility matrix
B)Work breakdown structure
C)Project priority matrix
D)Work package
E)Criterion matrix
C
Explanation: One technique found in practice that is useful for this purpose is completing a priority matrix for the project to identify which criterion is constrained, which should be enhanced, and which can be accepted.
2
All of the following are usually included in a work package except

A)What will be done?
B)The time needed to complete the work.
C)A single person who is responsible for its completion.
D)All the costs for the work package.
E)All of these are included in a work package.
E
Explanation: Work packages are short duration tasks that have a definite start and stop point, consume resources, and represent cost.Each work package is a control point.A work package manager is responsible for seeing that the package is completed on time, within budget, and according to technical specifications.
3
In reviewing the project plan, Susan sees that the first prototype is due by October 12.This would be best classified as a

A)Project target
B)Limit item
C)Milestone
D)Project objective
E)Critical goal
C
Explanation: A milestone is a significant event in a project that occurs at a point in time.The milestone schedule shows only major segments of work; it represents first, rough-cut estimates of time, cost, and resources for the project.
4
Research shows the most frequently mentioned barrier to project success is

A)Not enough budget resources
B)Poor performance by team members
C)Weak project leadership
D)Poorly defined scope or mission
E)Political in-fighting
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
5
An expected output over the life of a project would be classified as

A)A deliverable
B)A product
C)An end object
D)An objective
E)A target
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
6
Which of the following is not one of the basic classifications of project priorities?

A)Profit
B)Cost
C)Time
D)Performance
E)All of these are basic classifications
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
7
"To construct a high-quality, custom home within five months at costs not to exceed $150,000" is best classified as

A)A deliverable
B)A milestone
C)An objective
D)A limit
E)An exclusion
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
8
Linda has just been assigned a project to develop a new advertising campaign for an established product.Her first step should be to

A)Establish project priorities
B)Define the project scope
C)Verify the budget available
D)Assign team members to work on the project
E)Determine the required completion date
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
9
The method used to collect information to use through all phases of the project life cycle is called

A)Responsibility matrix
B)Organization breakdown structure
C)Work breakdown structure
D)Priority matrix
E)Work package
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
10
The lowest element in the hierarchical breakdown of the WBS is

A)A deliverable
B)A work package
C)A cost account
D)A lowest sub deliverable
E)An object
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
11
The highest element in the hierarchical breakdown of the WBS is

A)A work package
B)Sub deliverables
C)A cost account
D)Major deliverables
E)The project
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
12
Which of the following is not one of the items that would appear on a project scope checklist?

A)Deliverables
B)Technical requirements
C)Objectives
D)Work breakdown structure
E)Reviews with customer
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
13
All of the following are true about work packages except

A)Consume resources
B)Assigned to only one manager
C)Have medium to long duration
D)Definitive starts and stops dates
E)All of these are true
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
14
If a project criterion indicates that the project must meet a specific date, that criterion is classified as

A)Constrained
B)Enhanced
C)Accepted
D)Limited
E)Fixed
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
15
Scott has just been given a project that has a specific target date.After discussion with top management he finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets.The target date is best classified as

A)Constrain
B)Enhance
C)Accept
D)Limit
E)Optional
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
16
The first step in creating the necessary information to manage a project is to

A)Establish project priorities
B)Define the project scope
C)Verify the budget available
D)Assign team members to work on the project
E)Determine the required completion date
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
17
The first step of project scope definition is to

A)Analyze the strategic plan
B)Analyze the current budget plan
C)Meet with team members
D)Select team members
E)Define the overall objective to meet the customer's needs
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
18
The second step in the defining of a project would be to

A)Analyze the strategic plan
B)Analyze the current budget plan
C)Establish project priorities
D)Select team members
E)Define the major objectives to meet the customer's needs
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
19
Jose is looking at a document that outlines the specific tasks and subtasks required to complete the writing of a technical support manual.The method that was probably used to develop the document is most likely

A)Responsibility matrix
B)Organization breakdown structure
C)Work breakdown structure
D)Priority matrix
E)Work package
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
20
The ability of 911 emergency systems to identify the caller's phone number and location are considered to be a

A)Technical requirement
B)Milestone
C)Project limit
D)Project exclusion
E)Project deliverable
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
21
If a project is small or of narrow scope and does not require an elaborate system, which of the following is a good choice?

A)Responsibility matrix
B)Organization breakdown structure
C)Work breakdown structure
D)Priority matrix
E)Process breakdown structure
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
22
The project scope statement indicates that the client is responsible for training the people who will be using the equipment and that the project team will train the client's trainers.This is an example of:

A)Project objectives
B)Deliverables
C)Limits and exclusions
D)Technical requirements
E)Milestones
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
23
A selective outline of the project that ensures the identification of all tasks and an understanding of what is to be done is called a _______________.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
24
A project parameter such as completion date or cost is ________ if it is fixed and must be met.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
25
Creating an extranet website or an internal software database system would be most closely associated with the

A)Responsibility matrix
B)Organization breakdown structure
C)Work breakdown structure
D)Priority matrix
E)Process breakdown structure
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
26
The primary purpose of the first step of defining a project is to identify the ________ for the end user and to focus project plans.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
27
In making project trade-offs, a criteria that is allowed to not meet the original target is classified as ________.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
28
The need for a computer to function in countries having different electrical systems is an example of a ________.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
29
Which of the follow is least likely to be included in a Work Package?

A)Materials
B)Labor
C)Overhead
D)Duration
E)Responsibilities
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
30
The integration of project work packages within the organization's management structure is known as

A)Responsibility matrix
B)Organization breakdown structure
C)Work breakdown structure
D)Priority matrix
E)Process breakdown structure
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
31
Developing a ________ provides a forum for clearly establishing priorities with customers and top management so as to create shared expectations and avoid misunderstandings.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
32
The first step in planning any project is to ________.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
33
The final step in the creation of a Work Breakdown Structure is to

A)Code the WBS for tracking
B)Assign the cost account to a manager
C)Assign the work package to a manager
D)Develop the responsibility matrix
E)All of these are included in the final step
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
34
The agreement that training will be the responsibility of the customer is an example of a project ________.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
35
The intersection of the WBS and the OBS is called the

A)Responsibility matrix
B)Priority matrix
C)Work package
D)Cost account
E)Project overlap
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
36
The Snapshot from Practice dealing with Big Bertha II illustrated how important a project's __________ is to the successful completion of a project.

A)Objective
B)Deliverables
C)Technical requirements
D)Milestones
E)Limits and exclusions
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
37
Taking advantage of opportunities to reduce costs or accelerate the schedule are examples of project criteria being classified as ________.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
38
Which of the following is a good example of a Process Breakdown Structure?

A)New car prototype
B)New software program
C)New computer hardware
D)New sports stadium
E)New project management book
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
39
The tendency for the project deliverables to expand over time-usually by changing requirements, specifications, and priorities-is called:

A)Scope erosion
B)Scope creep
C)Project bloat
D)Scope enhancement
E)Project add-ons
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
40
Significant events in a project that occur at a specific point in time, are natural control points, and are easily recognized by project participants are known as ___________.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
41
Practice suggests that a work package should not exceed ________ workdays or one reporting period.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
42
The purposes of the ____________ are to provide a framework to summarize organization unit work performance, identify organization units responsible for work packages, and tie the organizational unit to cost control accounts.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
43
Once the __________ has been established, it is the basis for making trade-off decisions later in the project.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
44
Studies suggest that there is a strong correlation between project success and clear project scope definition.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
45
The most detailed element in the hierarchical breakdown of the project work to be accomplished is known as the ________.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
46
One of the items included on a project scope checklist is the reviews with the customer.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
47
A(n) ________ is a grouping of work packages for monitoring progress and responsibility.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
48
The result of subdividing the work of a project into smaller and smaller work elements is called ________.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
49
Project scope describes what you expect to deliver to your customers when the project is complete.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
50
The development of a work breakdown structure with appropriate dates and budget is usually accomplished in a single iteration.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
51
Quality and the ultimate success of a project are traditionally defined as meeting or exceeding the expectations of the customer or management.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
52
The gradual expansion of project requirements during the execution of project is known as __________.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
53
The criteria for project success include attaining objectives relating to cost, schedule, and revenue.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
54
The Work Breakdown Structure is an outline of the project with different levels of __________.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
55
The final step in the defining of a project is focused on assigning ________ to each of the work packages.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
56
The process of assigning specific work packages to a particular group or person within the organization is called ________.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
57
The ________ summarizes, in graphic format, the tasks to be accomplished and who is responsible for what on a given project.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
58
The most commonly used method for coding the WBS is __________.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
59
In a work breakdown structure the ________ is the focal point because all budgets, work assignments, time, cost, and technical performance come together at that point.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
60
In a ________ the project is organized around phases or groups of activities rather than the more conventional deliverables.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
61
The hierarchical work breakdown structure can be used to represent the need for information at various levels of management.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
62
Statements of project scope are sometimes referred to as Statements of Work or Project Charters.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
63
Basically, the WBS is an outline of the project with different levels of detail.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
64
If a project criterion should be optimized if at all possible, it is classified as being constrained.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
65
For large companies, the organization breakdown structure is used rather than the work breakdown structure.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
66
In a work breakdown structure deliverables are ignored and replaced with activities or tasks that have been grouped in phases.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
67
Identify and briefly describe the six elements on the recommended project scope checklist.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
68
Responsibility matrices are used primarily with small and medium sized projects and have limited use in large projects.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
69
Integrating a project's work packages within the organization's management structure is known as work breakdown structure.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
70
The intersection of the WBS and the OBS represents a control point, called a cost account.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
71
A typical responsibility matrix will include not only those responsible for a specific task but also those who supply support and assistance.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
72
The most commonly used scheme for coding the work breakdown structure is to use a department project number assigned by the accounting department.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
73
Identify and briefly describe the five steps in defining a project.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
74
Reviews with customers only refers to projects with external customers who are paying for the project.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
75
Scope definitions are usually brief with only one or two pages being typical for small projects.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
76
The intersection of work packages and the organization unit creates a project control point called a cost account.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
77
A work breakdown structure is frequently used on projects such as software development where the project is focused on activities rather than deliverables.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
78
In general, work packages should not exceed 10 work days.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
79
In terms of project management, what is a deliverable and give an example.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
80
In a Work Breakdown Structure for a software development project, the typical structure follows the major phases of software development.
Unlock Deck
Unlock for access to all 89 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 89 flashcards in this deck.