Deck 9: Reducing Project Duration

Full screen (f)
exit full mode
Question
In selecting the best activity to reduce you would first select the activity with the

A)Earliest start time
B)Steepest slope
C)Least steep slope
D)Longest duration
E)Largest crash time
Use Space or
up arrow
down arrow
to flip the card.
Question
The shortest possible time an activity can be completed realistically is called ___ time.

A)Expedited
B)Accelerated
C)Crash
D)Optimistic
E)Optimal
Question
Total project costs include all of the following except:

A)Supervision
B)Administration
C)Project manager's salary
D)Interest
E)All of these are included in total project costs
Question
Cost slope can be determined by dividing the

A)Run by the rise
B)Rise by the run
C)Crash cost by the normal cost
D)Normal cost by the crash cost
E)Both B and C are correct
Question
An activity's crash costs include ____ costs.

A)Direct
B)Indirect
C)Overhead
D)Both A and B are correct
E)A, B, and C are correct
Question
Intense global competition and rapid technological advances create pressure on developing projects rapidly.This is an example of reducing project duration caused by:

A)Imposed project deadlines
B)Time to market
C)Unforeseen project delays
D)High overhead
E)Incentive contracts
Question
The president of a software company remarks in a speech that new technologically advanced software will be available in one year.This is an example of reducing project duration caused by:

A)Imposed project deadlines
B)Time to market
C)Unforeseen project delays
D)High overhead
E)Incentive contracts
Question
Creating a Project Cost-Duration graph is useful:

A)During the pre-project planning phase
B)After the project has begun
C)After the completion of the project
D)Both A and B are correct
E)A, B, and C are all correct
Question
Project costs are generally classified as ____ costs.

A)Direct
B)Indirect
C)Overhead
D)Both A and B are correct
E)A, B, and C are all correct
Question
____ costs are incurred when completing an activity in its realistically shortest time.

A)Normal
B)Reserve
C)Crash
D)Accelerated
E)Expedited
Question
Which of the following is not considered a project indirect cost?

A)Supervision
B)Consultants
C)Equipment
D)Interest
E)All of these are considered project indirect costs
Question
A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion.This is an example of reducing project duration caused by:

A)Imposed project deadlines
B)Time to market
C)Unforeseen project delays
D)High overhead
E)Incentive contracts
Question
An activity's cost slope represents an activity's

A)Total cost per unit of time
B)Cost per unit of time
C)Indirect cost per unit of time
D)Both B and C are correct
E)A, B, and C are all correct
Question
The most common response for meeting unattainable deadlines is to

A)Reduce or scale back the scope of the project.
B)Decrease the critical paths
C)Crash all elements of the project
D)Change the time to market statement
E)B, and C are correct
Question
The optimum duration for a project is at the point where:

A)Direct costs are the lowest
B)Indirect costs are the lowest
C)Direct costs equal indirect costs
D)Total project costs are the lowest
E)The project changes from time-constrained to resource-constrained
Question
Adverse weather, design flaws, and equipment breakdown can create negative slack.This is an example of reducing project duration caused by:

A)Imposed project deadlines
B)Time to market
C)Unforeseen project delays
D)High overhead
E)Incentive contracts
Question
Which of the following correctly calculates an activity's cost slope?

A)(normal cost-crash cost)/(normal time-crash time)
B)(crash cost-normal cost)/(normal time-crash time)
C)(normal time-crash time)/(crash cost-normal cost)
D)(normal time-crash time)/(normal cost-crash cost)
E)(crash cost-normal cost)/(crash time-normal time)
Question
The less steep the cost slope of an activity, the

A)Less it costs to shorten one time period
B)More it costs to shorten one time period
C)Smaller the crash time
D)Larger the crash time
E)Cannot be determined by the information given
Question
Low-cost, realistic, efficient methods for completing an activity under normal conditions are supported by ____ time.

A)Normal
B)Budget
C)Optimized
D)Expected
E)Target
Question
Crashing a project should occur:

A)As early as possible
B)As late as possible
C)Midway through the project
D)Both A and C are correct
E)Cannot be determined with the information given
Question
The relationship between cost and time for various durations is assumed to be:

A)Linear
B)Curvilinear
C)Variable
D)Conversely related
E)Exponentially related
Question
Which of the following is the easiest method for shortening project time?

A)Assigning additional staff and equipment
B)Subcontract work
C)Schedule overtime
D)Reduce project scope
E)Reduce the quality
Question
The project direct-cost line near the normal point is usually:

A)Sloped steeply
B)Relatively flat
C)Rising
D)Falling
E)Gently sloped
Question
The Snapshot from Practice which detailed the Northridge earthquake demonstrated the importance of reducing a project's ______.
Question
If a network has several critical or near-critical paths it is deemed to be:

A)Well planned
B)The lowest cost alternative
C)Resource-constrained
D)Sensitive
E)Insensitive
Question
Intense global competition and rapid technological advances combine to create a(n) ________ imposed project duration date.
Question
The most common method for shortening project time is to

A)Subcontract activities
B)Compromise the quality
C)Add additional staff and equipment
D)Work overtime
E)Reduce the project scope
Question
The Snapshot from Practice "Cell-Phone Wars" is an excellent example of reducing project duration due to:

A)Imposed project deadlines
B)Time to market
C)Unforeseen project delays
D)High overhead
E)Incentive contracts
Question
Sometimes very high ________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.
Question
Which of the following is not one of the techniques for accelerating project completion?

A)Assigning additional staff and equipment
B)Establish a core team
C)Do it twice-fast and correctly
D)Reduce project scope
E)All of these are acceptable techniques
Question
One way of reducing project costs is identifying tasks that _________ can do themselves.

A)Vendors
B)Suppliers
C)Customers
D)Company employees
E)Project teams
Question
A common method for shortening the project time is to:

A)Adding resources
B)Schedule overtime
C)Subcontract an activity
D)Both A and B are correct
E)A, B, and C are all correct
Question
Which of the following is/are included in a Project Cost-Duration Graph?

A)Total indirect cost
B)Total direct cost
C)Total project cost
D)Both A and B are correct
E)A, B, and C are all correct
Question
According to Brooks' Law, adding more people to a late project is most likely to have which of the following impact?

A)Keep the project from slipping any further
B)Get the project back on schedule
C)Make the project slips further
D)Both A and B are correct
E)None of these relate to Brooks' Law
Question
Which of the following is not one of the more commonly used options for cutting project costs?

A)Reduce project scope
B)Have owner take more responsibility
C)Moving the completion date further out
D)Brainstorming cost savings options
E)Outsourcing project activities
Question
Which of the following is the most common method for shortening project time?

A)Assigning additional staff and equipment
B)Subcontract work
C)Schedule overtime
D)Reduce project scope
E)Reduce the quality
Question
A positive situation where moving toward the optimum time can result in very real, large savings-this occurs when the network is:

A)Insensitive
B)Sensitive
C)Ahead of schedule
D)Shifting to the critical chain
E)Implementing a fast-tracking system
Question
When the project team is salaried, which of the following is the preferred choice for accelerating project completion?

A)Assigning additional staff and equipment
B)Subcontract work
C)Schedule overtime
D)Work longer hours
E)Both C and D are preferred choices
Question
The ________ project cost is the sum of the indirect and direct costs.
Question
When a politician makes a public statement that a new building will be available in two years, a(n) ________ duration has reduced the project duration.
Question
Because direct costs are assumed to be developed from normal methods and time, any reduction in activity time should ________ the cost of the activity.
Question
In the "I'll Bet You..." Snapshot from Practice, the draftsman won ___________ for making a very difficult deadline.
Question
Subtracting an activity's crash time from the normal time will calculate an activity's ________.
Question
The easiest way to add more resources to a project is not to add more people, but to schedule ________.
Question
To shorten the duration of a project the project manager should limit the choices of activities to just those which ________.
Question
An activity's ________ is calculated by dividing the rise by the run.
Question
The ________ time for an activity represents low-costs, realistic, efficient methods for completing the activity under typical conditions.
Question
A network is considered to be ________ if it has a predominate critical path with no other path close in terms of slack.
Question
The easiest way to add more labor to a project is not to add more people, but to add ___________.
Question
Costs such as supervision, administration, consultants, and interest are examples of ________ project costs.
Question
According to ________, adding more manpower to a late software project makes it later.
Question
When considering whether to move the project to its optimum cost-time position, the manager should also consider ________.
Question
Shortening an activity is called ________.
Question
___________ is probably the most common response for meeting unattainable deadlines.
Question
A rule of thumb for moderate- to high-technology firms is that a six-month delay in bringing a product to market can result in a gross profit loss of about 35 percent.
Question
Costs such as labor, materials, equipment, or contractors are examples of ________ project costs.
Question
Direct costs are assignable directly to a project ________.
Question
Subtracting an activity's normal cost from the crash cost will calculate an activity's ________.
Question
The direct costs for completing an activity as early as possible is called its ________.
Question
____________ is the rearranging of the project network logic so that critical activities are done in parallel rather than sequentially.
Question
Crash cost is the incremental cost incurred when an activity is reduced in duration.
Question
The accuracy of crash times and costs is frequently rough at best, when compared with normal time and cost.
Question
Shortening an activity's duration is termed crashing.
Question
Expected time for an activity represents low-cost, realistic, efficient methods for completing the activity under anticipated conditions.
Question
Crashing a more expensive activity may be wise if fewer inherent risks are involved.
Question
Incentive contracts can make reduction of project time rewarding-usually for both the project contractor and owner.
Question
Managers have several effective methods for crashing specific project activities when resources are not constrained.
Question
A project network is classified as sensitive if it has a large number of interacting paths.
Question
While the relationship between normal and crash times is really curvilinear, the assumption that it is linear is seldom a concern for practicing managers.
Question
Direct costs are so named because they can be assigned directly to a work package and activity.
Question
The higher the slope of an activity the greater the cost to reduce its duration.
Question
Because direct costs are assumed to be developed from normal methods and time, any reduction in activity time should add to the costs of the activity.
Question
The cost slope of an activity is calculated by dividing the run by the rise.
Question
Creating a Project Cost-Duration Graph in the pre-project planning phase without an imposed duration is the best time to use this tool.
Question
Crash time is the greatest time reduction possible under realistic conditions.
Question
Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest.
Question
The sum of the costs of all the work packages represents the total direct costs for the project.
Question
Imposed project durations almost always leads to a higher-cost project than one planned with detailed scheduling of all the project's activities.
Question
Collecting crash times for a moderate-size project is relatively easy.
Question
The total cost for each possible duration of a project is the sum of labor, materials, and equipment.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/94
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 9: Reducing Project Duration
1
In selecting the best activity to reduce you would first select the activity with the

A)Earliest start time
B)Steepest slope
C)Least steep slope
D)Longest duration
E)Largest crash time
C
Explanation: The less steep the cost slope of an activity, the less it costs to shorten one time period.
2
The shortest possible time an activity can be completed realistically is called ___ time.

A)Expedited
B)Accelerated
C)Crash
D)Optimistic
E)Optimal
C
Explanation: The shortest possible time an activity can realistically be completed in is called its crash time.
3
Total project costs include all of the following except:

A)Supervision
B)Administration
C)Project manager's salary
D)Interest
E)All of these are included in total project costs
E
Explanation: Direct costs commonly represent labor, materials, equipment, and sometimes subcontractors.Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest.
4
Cost slope can be determined by dividing the

A)Run by the rise
B)Rise by the run
C)Crash cost by the normal cost
D)Normal cost by the crash cost
E)Both B and C are correct
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
5
An activity's crash costs include ____ costs.

A)Direct
B)Indirect
C)Overhead
D)Both A and B are correct
E)A, B, and C are correct
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
6
Intense global competition and rapid technological advances create pressure on developing projects rapidly.This is an example of reducing project duration caused by:

A)Imposed project deadlines
B)Time to market
C)Unforeseen project delays
D)High overhead
E)Incentive contracts
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
7
The president of a software company remarks in a speech that new technologically advanced software will be available in one year.This is an example of reducing project duration caused by:

A)Imposed project deadlines
B)Time to market
C)Unforeseen project delays
D)High overhead
E)Incentive contracts
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
8
Creating a Project Cost-Duration graph is useful:

A)During the pre-project planning phase
B)After the project has begun
C)After the completion of the project
D)Both A and B are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
9
Project costs are generally classified as ____ costs.

A)Direct
B)Indirect
C)Overhead
D)Both A and B are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
10
____ costs are incurred when completing an activity in its realistically shortest time.

A)Normal
B)Reserve
C)Crash
D)Accelerated
E)Expedited
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
11
Which of the following is not considered a project indirect cost?

A)Supervision
B)Consultants
C)Equipment
D)Interest
E)All of these are considered project indirect costs
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
12
A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion.This is an example of reducing project duration caused by:

A)Imposed project deadlines
B)Time to market
C)Unforeseen project delays
D)High overhead
E)Incentive contracts
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
13
An activity's cost slope represents an activity's

A)Total cost per unit of time
B)Cost per unit of time
C)Indirect cost per unit of time
D)Both B and C are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
14
The most common response for meeting unattainable deadlines is to

A)Reduce or scale back the scope of the project.
B)Decrease the critical paths
C)Crash all elements of the project
D)Change the time to market statement
E)B, and C are correct
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
15
The optimum duration for a project is at the point where:

A)Direct costs are the lowest
B)Indirect costs are the lowest
C)Direct costs equal indirect costs
D)Total project costs are the lowest
E)The project changes from time-constrained to resource-constrained
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
16
Adverse weather, design flaws, and equipment breakdown can create negative slack.This is an example of reducing project duration caused by:

A)Imposed project deadlines
B)Time to market
C)Unforeseen project delays
D)High overhead
E)Incentive contracts
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
17
Which of the following correctly calculates an activity's cost slope?

A)(normal cost-crash cost)/(normal time-crash time)
B)(crash cost-normal cost)/(normal time-crash time)
C)(normal time-crash time)/(crash cost-normal cost)
D)(normal time-crash time)/(normal cost-crash cost)
E)(crash cost-normal cost)/(crash time-normal time)
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
18
The less steep the cost slope of an activity, the

A)Less it costs to shorten one time period
B)More it costs to shorten one time period
C)Smaller the crash time
D)Larger the crash time
E)Cannot be determined by the information given
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
19
Low-cost, realistic, efficient methods for completing an activity under normal conditions are supported by ____ time.

A)Normal
B)Budget
C)Optimized
D)Expected
E)Target
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
20
Crashing a project should occur:

A)As early as possible
B)As late as possible
C)Midway through the project
D)Both A and C are correct
E)Cannot be determined with the information given
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
21
The relationship between cost and time for various durations is assumed to be:

A)Linear
B)Curvilinear
C)Variable
D)Conversely related
E)Exponentially related
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
22
Which of the following is the easiest method for shortening project time?

A)Assigning additional staff and equipment
B)Subcontract work
C)Schedule overtime
D)Reduce project scope
E)Reduce the quality
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
23
The project direct-cost line near the normal point is usually:

A)Sloped steeply
B)Relatively flat
C)Rising
D)Falling
E)Gently sloped
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
24
The Snapshot from Practice which detailed the Northridge earthquake demonstrated the importance of reducing a project's ______.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
25
If a network has several critical or near-critical paths it is deemed to be:

A)Well planned
B)The lowest cost alternative
C)Resource-constrained
D)Sensitive
E)Insensitive
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
26
Intense global competition and rapid technological advances combine to create a(n) ________ imposed project duration date.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
27
The most common method for shortening project time is to

A)Subcontract activities
B)Compromise the quality
C)Add additional staff and equipment
D)Work overtime
E)Reduce the project scope
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
28
The Snapshot from Practice "Cell-Phone Wars" is an excellent example of reducing project duration due to:

A)Imposed project deadlines
B)Time to market
C)Unforeseen project delays
D)High overhead
E)Incentive contracts
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
29
Sometimes very high ________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
30
Which of the following is not one of the techniques for accelerating project completion?

A)Assigning additional staff and equipment
B)Establish a core team
C)Do it twice-fast and correctly
D)Reduce project scope
E)All of these are acceptable techniques
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
31
One way of reducing project costs is identifying tasks that _________ can do themselves.

A)Vendors
B)Suppliers
C)Customers
D)Company employees
E)Project teams
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
32
A common method for shortening the project time is to:

A)Adding resources
B)Schedule overtime
C)Subcontract an activity
D)Both A and B are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
33
Which of the following is/are included in a Project Cost-Duration Graph?

A)Total indirect cost
B)Total direct cost
C)Total project cost
D)Both A and B are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
34
According to Brooks' Law, adding more people to a late project is most likely to have which of the following impact?

A)Keep the project from slipping any further
B)Get the project back on schedule
C)Make the project slips further
D)Both A and B are correct
E)None of these relate to Brooks' Law
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
35
Which of the following is not one of the more commonly used options for cutting project costs?

A)Reduce project scope
B)Have owner take more responsibility
C)Moving the completion date further out
D)Brainstorming cost savings options
E)Outsourcing project activities
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
36
Which of the following is the most common method for shortening project time?

A)Assigning additional staff and equipment
B)Subcontract work
C)Schedule overtime
D)Reduce project scope
E)Reduce the quality
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
37
A positive situation where moving toward the optimum time can result in very real, large savings-this occurs when the network is:

A)Insensitive
B)Sensitive
C)Ahead of schedule
D)Shifting to the critical chain
E)Implementing a fast-tracking system
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
38
When the project team is salaried, which of the following is the preferred choice for accelerating project completion?

A)Assigning additional staff and equipment
B)Subcontract work
C)Schedule overtime
D)Work longer hours
E)Both C and D are preferred choices
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
39
The ________ project cost is the sum of the indirect and direct costs.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
40
When a politician makes a public statement that a new building will be available in two years, a(n) ________ duration has reduced the project duration.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
41
Because direct costs are assumed to be developed from normal methods and time, any reduction in activity time should ________ the cost of the activity.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
42
In the "I'll Bet You..." Snapshot from Practice, the draftsman won ___________ for making a very difficult deadline.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
43
Subtracting an activity's crash time from the normal time will calculate an activity's ________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
44
The easiest way to add more resources to a project is not to add more people, but to schedule ________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
45
To shorten the duration of a project the project manager should limit the choices of activities to just those which ________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
46
An activity's ________ is calculated by dividing the rise by the run.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
47
The ________ time for an activity represents low-costs, realistic, efficient methods for completing the activity under typical conditions.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
48
A network is considered to be ________ if it has a predominate critical path with no other path close in terms of slack.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
49
The easiest way to add more labor to a project is not to add more people, but to add ___________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
50
Costs such as supervision, administration, consultants, and interest are examples of ________ project costs.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
51
According to ________, adding more manpower to a late software project makes it later.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
52
When considering whether to move the project to its optimum cost-time position, the manager should also consider ________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
53
Shortening an activity is called ________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
54
___________ is probably the most common response for meeting unattainable deadlines.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
55
A rule of thumb for moderate- to high-technology firms is that a six-month delay in bringing a product to market can result in a gross profit loss of about 35 percent.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
56
Costs such as labor, materials, equipment, or contractors are examples of ________ project costs.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
57
Direct costs are assignable directly to a project ________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
58
Subtracting an activity's normal cost from the crash cost will calculate an activity's ________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
59
The direct costs for completing an activity as early as possible is called its ________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
60
____________ is the rearranging of the project network logic so that critical activities are done in parallel rather than sequentially.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
61
Crash cost is the incremental cost incurred when an activity is reduced in duration.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
62
The accuracy of crash times and costs is frequently rough at best, when compared with normal time and cost.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
63
Shortening an activity's duration is termed crashing.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
64
Expected time for an activity represents low-cost, realistic, efficient methods for completing the activity under anticipated conditions.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
65
Crashing a more expensive activity may be wise if fewer inherent risks are involved.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
66
Incentive contracts can make reduction of project time rewarding-usually for both the project contractor and owner.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
67
Managers have several effective methods for crashing specific project activities when resources are not constrained.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
68
A project network is classified as sensitive if it has a large number of interacting paths.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
69
While the relationship between normal and crash times is really curvilinear, the assumption that it is linear is seldom a concern for practicing managers.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
70
Direct costs are so named because they can be assigned directly to a work package and activity.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
71
The higher the slope of an activity the greater the cost to reduce its duration.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
72
Because direct costs are assumed to be developed from normal methods and time, any reduction in activity time should add to the costs of the activity.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
73
The cost slope of an activity is calculated by dividing the run by the rise.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
74
Creating a Project Cost-Duration Graph in the pre-project planning phase without an imposed duration is the best time to use this tool.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
75
Crash time is the greatest time reduction possible under realistic conditions.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
76
Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
77
The sum of the costs of all the work packages represents the total direct costs for the project.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
78
Imposed project durations almost always leads to a higher-cost project than one planned with detailed scheduling of all the project's activities.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
79
Collecting crash times for a moderate-size project is relatively easy.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
80
The total cost for each possible duration of a project is the sum of labor, materials, and equipment.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 94 flashcards in this deck.