Deck 10: Managing Projects in a Global Ecosystem

Full screen (f)
exit full mode
Question
This development methodology is more traditional and more structured than other approaches.

A) Agile programming
B) Prototyping
C) Open source deployment
D) Software development life cycle (SDLC)
E) Critical path method (CPM)
Use Space or
up arrow
down arrow
to flip the card.
Question
All of the following are indications that the project is successful EXCEPT:

A) Customers receive a significant benefit from the project.
B) The project meets its return on investment goal.
C) The project meets the established time and budget criteria.
D) The project prepares the organization for future success and growth.
E) The project profits are high and last for a very short time period.
Question
Which one of the following software products is NOT an open source software release?

A) PERL
B) Open Office
C) Linux
D) Mozilla
E) Microsoft Office
Question
An organization may convert from an old system to a new system by choosing to run both the old and new systems at the same time until the new system is fully accepted.This is known as __________.

A) Cutover
B) Parallel conversion
C) Direct cutover
D) Agile development
E) SDLC
Question
This is a temporary endeavor undertaken to create a unique product,service or result.

A) project
B) event
C) scope
D) requirement
E) system
Question
Which one of the following is NOT one of the four essential elements of any project?

A) Common project vocabulary
B) Project team
C) System evaluation
D) Project cycle plan
E) Project management
Question
What is at the center of the project triangle?

A) Agility
B) Quality
C) Speed
D) Cost
E) Focus
Question
The project triangle includes 3 sides - time,scope and ________.

A) cost
B) product
C) event
D) quality
E) requirements
Question
A successful project begins with a ____________ that articulates the purpose and details of the project and identifies stakeholders and the required resources.

A) project plan
B) Gantt chart
C) business plan
D) dashboard
E) strategy
Question
To maintain balance in a project with a fixed budget and a well-defined scope,a project team will require flexibility ________.

A) with the deadline.
B) in spending.
C) with project quality.
D) with assumed risks.
E) in achieving the goals of the business case.
Question
This project cycle plan tends to be used for projects that have direct relationships between time and resources.

A) PERT
B) Gantt
C) CPM
D) NPV
E) Flowchart
Question
In today's hypercompetitive business environment,firms that have strong project management skills have a higher likelihood of success because they are able to:

A) Spend money wisely.
B) Adapt processes and systems and therefore innovate faster than their competitors.
C) Optimize business processes.
D) Change and adapt in a slow yet methodical manner, reducing risk.
E) Utilize social and mobile platforms.
Question
To reduce risk,a project should have which one of the following qualities.

A) High complexity
B) High clarity
C) Big in size
D) Large in budget
E) Lots of programmers.
Question
What type of software is released under a license approved by the Open Source Initiative (OSI)?

A) System Architecture Software (SAS)
B) Open System Software (OSS)
C) Shareware Software (SS)
D) Open Source Software (OSS)
E) Source System Software (SSS)
Question
What does PMO stand for?

A) Project Maintenance Office
B) Project Mission and Objectives
C) Product Maintenance Office
D) Project Mission Office
E) Project Management Office
Question
Increasing project success requires gaining commitment from stakeholders.All of the following help to sustain that commitment for the life of the project EXCEPT:

A) Continually reminding stakeholders of the project benefits
B) Placing key stakeholders on the project team
C) Encouraging the project sponsor to provide public support for the project
D) Surprising the stakeholders by keeping the system's workings a secret
E) Assigning the right leader to be the project sponsor
Question
Open source software __________.

A) is free.
B) requires an organization pay a per user fee.
C) is costly.
D) is not allowed to be modified.
E) is provided by software vendors like Microsoft and SAP.
Question
To help with organization and complexity,a project manager will break a project up into:

A) Variables
B) Business processes
C) Subprojects
D) Infrastructure
E) Work
Question
This project cycle plan chart looks very much like a bar chart and is easy for management to read because of its visual nature.

A) PERT
B) Gantt
C) CPM
D) NPV
E) Flowchart
Question
Scope may be divided into product scope and __________ scope.

A) project
B) cost
C) time
D) time
E) sequence
Question
To transform resources into profits,organizations combine two types of work - operations and ________.
Question
A research firm found that a majority of software projects are delivered late or over budget or simply fail to meet expectations.
Question
These are the individuals and organizations that are involved in or may be affected by a given project.
Question
This plan organizes the discrete project activities and orders them along a timeline,identifying the critical beginning and ending dates as well as necessary time and resources.
Question
Agile development tends to be _______-oriented rather than process-oriented.
Question
This is the term used to describe Web apps that are created by combining existing applications,data,and infrastructure.
Question
All projects today involve both information technology and information flow components.
Question
To support a common language and improve communication,a project manager should develop a collection of acronyms and make frequent use of them.
Question
The maintenance and review phase is the longest phase of the software development lifecycle.
Question
What is the name given to the department that develops project management skills,boosts efficiency for projects,and improves project delivery?
Question
Explain why in a project only two of the three project elements (cost,time and scoop)can be optimized and the third must be adjusted to maintain balance.
Question
List one example of open source software.
Question
This is the term used to identify a project whose scope increases after it has started.
Question
The riskiest approach to system implementation is a parallel conversion.
Question
A good project manager defines a realistic project scope and then manages the project so that it can be completed on time and within _________.
Question
Small projects are often low in complexity,low in clarity and also low in risk.
Question
What are the three outside elements of the project triangle?
Question
Open source software is free but often an organization will have to pay for training and technical support for the software.
Question
Adding more people to a project can be helpful,but most projects are not made more efficient by simply adding labor.
Question
Project risk is a function of these 3 determinants.
Question
Match the activity to the SDLC project phase to which it belongs.
Match the activity to the SDLC project phase to which it belongs.  <div style=padding-top: 35px>
Question
Identify the following qualities as either being associated with operations or project work.
Identify the following qualities as either being associated with operations or project work.  <div style=padding-top: 35px>
Question
Identify an example of project management software and the features/functionality you would expect it to provide.
Question
Match the three major project periods to Lewins' phases of the change model.
Match the three major project periods to Lewins' phases of the change model.  <div style=padding-top: 35px>
Question
Match the development methodology with its characteristics.
Match the development methodology with its characteristics.  <div style=padding-top: 35px>
Question
Why does the addition of more people to a project not speed up the project efforts?
Question
Explain why IT projects are seen as just business projects involving significant amounts of technology.
Question
List some strategies a manager should consider when trying to manage a project's technical complexity.
Question
Classify the following organizational activity as either operations or a project.
Classify the following organizational activity as either operations or a project.  <div style=padding-top: 35px>
Question
Match the description to the SDLC project phase it represents.
Match the description to the SDLC project phase it represents.  <div style=padding-top: 35px>
Question
How do companies manage risk? What are the factors that contribute to a high-risk project?
Matching
Question
Match the project responsibility as being that of the project manager or the project sponsor.
Match the project responsibility as being that of the project manager or the project sponsor.  <div style=padding-top: 35px>
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/52
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 10: Managing Projects in a Global Ecosystem
1
This development methodology is more traditional and more structured than other approaches.

A) Agile programming
B) Prototyping
C) Open source deployment
D) Software development life cycle (SDLC)
E) Critical path method (CPM)
D
2
All of the following are indications that the project is successful EXCEPT:

A) Customers receive a significant benefit from the project.
B) The project meets its return on investment goal.
C) The project meets the established time and budget criteria.
D) The project prepares the organization for future success and growth.
E) The project profits are high and last for a very short time period.
E
3
Which one of the following software products is NOT an open source software release?

A) PERL
B) Open Office
C) Linux
D) Mozilla
E) Microsoft Office
E
4
An organization may convert from an old system to a new system by choosing to run both the old and new systems at the same time until the new system is fully accepted.This is known as __________.

A) Cutover
B) Parallel conversion
C) Direct cutover
D) Agile development
E) SDLC
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
5
This is a temporary endeavor undertaken to create a unique product,service or result.

A) project
B) event
C) scope
D) requirement
E) system
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
6
Which one of the following is NOT one of the four essential elements of any project?

A) Common project vocabulary
B) Project team
C) System evaluation
D) Project cycle plan
E) Project management
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
7
What is at the center of the project triangle?

A) Agility
B) Quality
C) Speed
D) Cost
E) Focus
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
8
The project triangle includes 3 sides - time,scope and ________.

A) cost
B) product
C) event
D) quality
E) requirements
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
9
A successful project begins with a ____________ that articulates the purpose and details of the project and identifies stakeholders and the required resources.

A) project plan
B) Gantt chart
C) business plan
D) dashboard
E) strategy
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
10
To maintain balance in a project with a fixed budget and a well-defined scope,a project team will require flexibility ________.

A) with the deadline.
B) in spending.
C) with project quality.
D) with assumed risks.
E) in achieving the goals of the business case.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
11
This project cycle plan tends to be used for projects that have direct relationships between time and resources.

A) PERT
B) Gantt
C) CPM
D) NPV
E) Flowchart
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
12
In today's hypercompetitive business environment,firms that have strong project management skills have a higher likelihood of success because they are able to:

A) Spend money wisely.
B) Adapt processes and systems and therefore innovate faster than their competitors.
C) Optimize business processes.
D) Change and adapt in a slow yet methodical manner, reducing risk.
E) Utilize social and mobile platforms.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
13
To reduce risk,a project should have which one of the following qualities.

A) High complexity
B) High clarity
C) Big in size
D) Large in budget
E) Lots of programmers.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
14
What type of software is released under a license approved by the Open Source Initiative (OSI)?

A) System Architecture Software (SAS)
B) Open System Software (OSS)
C) Shareware Software (SS)
D) Open Source Software (OSS)
E) Source System Software (SSS)
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
15
What does PMO stand for?

A) Project Maintenance Office
B) Project Mission and Objectives
C) Product Maintenance Office
D) Project Mission Office
E) Project Management Office
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
16
Increasing project success requires gaining commitment from stakeholders.All of the following help to sustain that commitment for the life of the project EXCEPT:

A) Continually reminding stakeholders of the project benefits
B) Placing key stakeholders on the project team
C) Encouraging the project sponsor to provide public support for the project
D) Surprising the stakeholders by keeping the system's workings a secret
E) Assigning the right leader to be the project sponsor
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
17
Open source software __________.

A) is free.
B) requires an organization pay a per user fee.
C) is costly.
D) is not allowed to be modified.
E) is provided by software vendors like Microsoft and SAP.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
18
To help with organization and complexity,a project manager will break a project up into:

A) Variables
B) Business processes
C) Subprojects
D) Infrastructure
E) Work
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
19
This project cycle plan chart looks very much like a bar chart and is easy for management to read because of its visual nature.

A) PERT
B) Gantt
C) CPM
D) NPV
E) Flowchart
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
20
Scope may be divided into product scope and __________ scope.

A) project
B) cost
C) time
D) time
E) sequence
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
21
To transform resources into profits,organizations combine two types of work - operations and ________.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
22
A research firm found that a majority of software projects are delivered late or over budget or simply fail to meet expectations.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
23
These are the individuals and organizations that are involved in or may be affected by a given project.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
24
This plan organizes the discrete project activities and orders them along a timeline,identifying the critical beginning and ending dates as well as necessary time and resources.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
25
Agile development tends to be _______-oriented rather than process-oriented.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
26
This is the term used to describe Web apps that are created by combining existing applications,data,and infrastructure.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
27
All projects today involve both information technology and information flow components.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
28
To support a common language and improve communication,a project manager should develop a collection of acronyms and make frequent use of them.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
29
The maintenance and review phase is the longest phase of the software development lifecycle.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
30
What is the name given to the department that develops project management skills,boosts efficiency for projects,and improves project delivery?
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
31
Explain why in a project only two of the three project elements (cost,time and scoop)can be optimized and the third must be adjusted to maintain balance.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
32
List one example of open source software.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
33
This is the term used to identify a project whose scope increases after it has started.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
34
The riskiest approach to system implementation is a parallel conversion.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
35
A good project manager defines a realistic project scope and then manages the project so that it can be completed on time and within _________.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
36
Small projects are often low in complexity,low in clarity and also low in risk.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
37
What are the three outside elements of the project triangle?
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
38
Open source software is free but often an organization will have to pay for training and technical support for the software.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
39
Adding more people to a project can be helpful,but most projects are not made more efficient by simply adding labor.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
40
Project risk is a function of these 3 determinants.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
41
Match the activity to the SDLC project phase to which it belongs.
Match the activity to the SDLC project phase to which it belongs.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
42
Identify the following qualities as either being associated with operations or project work.
Identify the following qualities as either being associated with operations or project work.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
43
Identify an example of project management software and the features/functionality you would expect it to provide.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
44
Match the three major project periods to Lewins' phases of the change model.
Match the three major project periods to Lewins' phases of the change model.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
45
Match the development methodology with its characteristics.
Match the development methodology with its characteristics.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
46
Why does the addition of more people to a project not speed up the project efforts?
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
47
Explain why IT projects are seen as just business projects involving significant amounts of technology.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
48
List some strategies a manager should consider when trying to manage a project's technical complexity.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
49
Classify the following organizational activity as either operations or a project.
Classify the following organizational activity as either operations or a project.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
50
Match the description to the SDLC project phase it represents.
Match the description to the SDLC project phase it represents.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
51
How do companies manage risk? What are the factors that contribute to a high-risk project?
Matching
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
52
Match the project responsibility as being that of the project manager or the project sponsor.
Match the project responsibility as being that of the project manager or the project sponsor.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 52 flashcards in this deck.