Deck 11: The Core Skills
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/16
Play
Full screen (f)
Deck 11: The Core Skills
1
It is commonly understood that there is a difference between managers and leaders.
True
2
Technical competencies largely deployed within the delivery domain need to be understood by project leaders working in the owner and supplier domains.
True
3
Planning stops at the Define stage as greater levels of detail as the WBS is developed, budgets are finalized and schedule refined.
False
4
What fundamental question does process of planning answer:
A) What needs to be done in a project?
B) Who will deliver a project?
C) How much will a project cost?
D) How are we going to deliver the outputs specified in the Project Execution Plan?
A) What needs to be done in a project?
B) Who will deliver a project?
C) How much will a project cost?
D) How are we going to deliver the outputs specified in the Project Execution Plan?
Unlock Deck
Unlock for access to all 16 flashcards in this deck.
Unlock Deck
k this deck
5
Matching
Earned Value Analysis takes into consideration three measures and questions a project manager asks:
-Earned Value (EV)
A) Actual spend to date. How much did we spend to complete the work?
B) Budgeted cost of work completed at specific point in the schedule. How much work have we actually completed?
C) What ought to have been spent at a specific point in the schedule according to the budget. How much work did we plan to complete?
Earned Value Analysis takes into consideration three measures and questions a project manager asks:
-Earned Value (EV)
A) Actual spend to date. How much did we spend to complete the work?
B) Budgeted cost of work completed at specific point in the schedule. How much work have we actually completed?
C) What ought to have been spent at a specific point in the schedule according to the budget. How much work did we plan to complete?
Unlock Deck
Unlock for access to all 16 flashcards in this deck.
Unlock Deck
k this deck
6
Matching
Earned Value Analysis takes into consideration three measures and questions a project manager asks:
-Planned Value (PV)
A) Actual spend to date. How much did we spend to complete the work?
B) Budgeted cost of work completed at specific point in the schedule. How much work have we actually completed?
C) What ought to have been spent at a specific point in the schedule according to the budget. How much work did we plan to complete?
Earned Value Analysis takes into consideration three measures and questions a project manager asks:
-Planned Value (PV)
A) Actual spend to date. How much did we spend to complete the work?
B) Budgeted cost of work completed at specific point in the schedule. How much work have we actually completed?
C) What ought to have been spent at a specific point in the schedule according to the budget. How much work did we plan to complete?
Unlock Deck
Unlock for access to all 16 flashcards in this deck.
Unlock Deck
k this deck
7
Matching
We measure execution performance by comparing current performance against the Project Execution Plan. This comparison results in one of the three options for action:
-Continue with the plan unchanged
A) if the original plan is no longer achievable due to new information becoming available.
B) if performance aligns with the PEP
C) if the plan and performance do not align
We measure execution performance by comparing current performance against the Project Execution Plan. This comparison results in one of the three options for action:
-Continue with the plan unchanged
A) if the original plan is no longer achievable due to new information becoming available.
B) if performance aligns with the PEP
C) if the plan and performance do not align
Unlock Deck
Unlock for access to all 16 flashcards in this deck.
Unlock Deck
k this deck
8
Matching
We measure execution performance by comparing current performance against the Project Execution Plan. This comparison results in one of the three options for action:
-Take corrective action
A) if the original plan is no longer achievable due to new information becoming available.
B) if performance aligns with the PEP
C) if the plan and performance do not align
We measure execution performance by comparing current performance against the Project Execution Plan. This comparison results in one of the three options for action:
-Take corrective action
A) if the original plan is no longer achievable due to new information becoming available.
B) if performance aligns with the PEP
C) if the plan and performance do not align
Unlock Deck
Unlock for access to all 16 flashcards in this deck.
Unlock Deck
k this deck
9
Matching
We measure execution performance by comparing current performance against the Project Execution Plan. This comparison results in one of the three options for action:
-Revise the PEP
A) if the original plan is no longer achievable due to new information becoming available.
B) if performance aligns with the PEP
C) if the plan and performance do not align
We measure execution performance by comparing current performance against the Project Execution Plan. This comparison results in one of the three options for action:
-Revise the PEP
A) if the original plan is no longer achievable due to new information becoming available.
B) if performance aligns with the PEP
C) if the plan and performance do not align
Unlock Deck
Unlock for access to all 16 flashcards in this deck.
Unlock Deck
k this deck
10
Graphical scheduling technique that acts as boundary objects between teams:
A) Critical path method
B) Critical chain
C) Gantt charts
D) Critical space analysis
A) Critical path method
B) Critical chain
C) Gantt charts
D) Critical space analysis
Unlock Deck
Unlock for access to all 16 flashcards in this deck.
Unlock Deck
k this deck
11
Budget estimation is a linear and completely accurate process carried out at the beginning of a project.
Unlock Deck
Unlock for access to all 16 flashcards in this deck.
Unlock Deck
k this deck
12
Matching
Four methods for estimating costs can be broadly identified:
-Ballpark
A) where cost estimates are developed by comparing to past similar projects to provide outside view with the aim of reducing the variance
B) where estimates are established from preliminary engineering work with an accuracy range of approx.70 percentage points
C) which provides estimates based on the work during the Define stage with an accuracy range of approx.38 percentage points
D) usually used early in the life cycle when there is very limited information or time to prepare with an accuracy range of approx.90 percentage points
Four methods for estimating costs can be broadly identified:
-Ballpark
A) where cost estimates are developed by comparing to past similar projects to provide outside view with the aim of reducing the variance
B) where estimates are established from preliminary engineering work with an accuracy range of approx.70 percentage points
C) which provides estimates based on the work during the Define stage with an accuracy range of approx.38 percentage points
D) usually used early in the life cycle when there is very limited information or time to prepare with an accuracy range of approx.90 percentage points
Unlock Deck
Unlock for access to all 16 flashcards in this deck.
Unlock Deck
k this deck
13
Matching
Four methods for estimating costs can be broadly identified:
-The PDP
A) where cost estimates are developed by comparing to past similar projects to provide outside view with the aim of reducing the variance
B) where estimates are established from preliminary engineering work with an accuracy range of approx.70 percentage points
C) which provides estimates based on the work during the Define stage with an accuracy range of approx.38 percentage points
D) usually used early in the life cycle when there is very limited information or time to prepare with an accuracy range of approx.90 percentage points
Four methods for estimating costs can be broadly identified:
-The PDP
A) where cost estimates are developed by comparing to past similar projects to provide outside view with the aim of reducing the variance
B) where estimates are established from preliminary engineering work with an accuracy range of approx.70 percentage points
C) which provides estimates based on the work during the Define stage with an accuracy range of approx.38 percentage points
D) usually used early in the life cycle when there is very limited information or time to prepare with an accuracy range of approx.90 percentage points
Unlock Deck
Unlock for access to all 16 flashcards in this deck.
Unlock Deck
k this deck
14
Matching
Four methods for estimating costs can be broadly identified:
-Comparative
A) where cost estimates are developed by comparing to past similar projects to provide outside view with the aim of reducing the variance
B) where estimates are established from preliminary engineering work with an accuracy range of approx.70 percentage points
C) which provides estimates based on the work during the Define stage with an accuracy range of approx.38 percentage points
D) usually used early in the life cycle when there is very limited information or time to prepare with an accuracy range of approx.90 percentage points
Four methods for estimating costs can be broadly identified:
-Comparative
A) where cost estimates are developed by comparing to past similar projects to provide outside view with the aim of reducing the variance
B) where estimates are established from preliminary engineering work with an accuracy range of approx.70 percentage points
C) which provides estimates based on the work during the Define stage with an accuracy range of approx.38 percentage points
D) usually used early in the life cycle when there is very limited information or time to prepare with an accuracy range of approx.90 percentage points
Unlock Deck
Unlock for access to all 16 flashcards in this deck.
Unlock Deck
k this deck
15
Matching
Four methods for estimating costs can be broadly identified:
-The PEP
A) where cost estimates are developed by comparing to past similar projects to provide outside view with the aim of reducing the variance
B) where estimates are established from preliminary engineering work with an accuracy range of approx.70 percentage points
C) which provides estimates based on the work during the Define stage with an accuracy range of approx.38 percentage points
D) usually used early in the life cycle when there is very limited information or time to prepare with an accuracy range of approx.90 percentage points
Four methods for estimating costs can be broadly identified:
-The PEP
A) where cost estimates are developed by comparing to past similar projects to provide outside view with the aim of reducing the variance
B) where estimates are established from preliminary engineering work with an accuracy range of approx.70 percentage points
C) which provides estimates based on the work during the Define stage with an accuracy range of approx.38 percentage points
D) usually used early in the life cycle when there is very limited information or time to prepare with an accuracy range of approx.90 percentage points
Unlock Deck
Unlock for access to all 16 flashcards in this deck.
Unlock Deck
k this deck
16
Managing conformance is an iterative process that needs to be tailored to each project.
Unlock Deck
Unlock for access to all 16 flashcards in this deck.
Unlock Deck
k this deck