Deck 3: Master Scheduling

Full screen (f)
exit full mode
Question
Events that make it necessary to alter the MPS include:

A) problems in production
B) scarce components
C) demand changes
D) all of the above
Use Space or
up arrow
down arrow
to flip the card.
Question
Master production scheduling's functions include:

A) to plan capacity requirements
B) to form the link between production planning and what manufacturing builds
C) to plan material requirements
D) all of the above
Question
Why is the MPS such a vital link in the production planning system?
Question
Daisy's dog food manufactures a premium line of pet food. The most popular is the beef delight and the sales department has prepared a forecast for six weeks. The opening inventory is 30 cases. Prepare a MPS. The dog food is manufactured in lots of 100 cases. Daisy's dog food manufactures a premium line of pet food. The most popular is the beef delight and the sales department has prepared a forecast for six weeks. The opening inventory is 30 cases. Prepare a MPS. The dog food is manufactured in lots of 100 cases.  <div style=padding-top: 35px>
Question
Calculate the available to promise using the following data. There are 100 units on hand. Calculate the available to promise using the following data. There are 100 units on hand.  <div style=padding-top: 35px>
Question
What is the final assembly schedule FAS)?
Question
How is the MPS judged?
Question
Discuss the possible errors in customer orders?
Question
Bruce Pet Supplies assembles cat toys from fabric which it purchases from an outside supplier. The sales department has prepared the following forecast for the "evil rat," the most popular stuffed toy. The rats are sewn and stuffed in lots of 200 and the opening inventory is 300 rats. Completed the projected available balance and the master production schedule. Bruce Pet Supplies assembles cat toys from fabric which it purchases from an outside supplier. The sales department has prepared the following forecast for the evil rat, the most popular stuffed toy. The rats are sewn and stuffed in lots of 200 and the opening inventory is 300 rats. Completed the projected available balance and the master production schedule.  <div style=padding-top: 35px>
Question
Using the MPS, sales and distribution can determine the __________.

A) MRP
B) MPS
C) JIT
D) ERP
Question
The MPS must be realistic and based on what production can and will do. If it is not,

A) overloading of plant resources could result
B) underloading of plant resources could result
C) unreliable schedules will result in poor delivery performance
D) all of the above
Question
The _________ is calculated based on whether the period is before or after the demand time fence.

A) schedule receipt
B) projected available balance
C) available to promise
D) forecast demand
Question
What are the results of changes to production schedules?
Question
Changes to the master production schedule will occur when:

A) machines break down or new machines are added, changing capacity
B) customers cancel or change orders
C) suppliers have problems and miss delivery dates
D) all of the above
Question
Senior managements approval is usually required to make changes with the __________ .

A) slushy zone
B) frozen zone
C) time fence
D) demand time fence
Question
The _________is the number of periods, beginning with period 1, in which changes are not excepted due to excessive cost caused by schedule disruptions.

A) available to promise
B) demand time fence
C) forecast demand
D) projected available balance
Question
Any changes can be made to the MRP as long as it is within the limits set by the production plan in the _________ .

A) liquid zone
B) frozen zone
C) demand time fence
D) slushy zone
Question
The planning horizon must cover a period less than the time required to accomplish the plan.
Question
A _________is an order that has been issued, either to manufacturing or to a supplier.

A) delivery promise
B) master production schedule
C) scheduled receipt
D) available to promise
Question
EnviroGuard manufacturing makes two garden hoses. The production plan and the MPS are developed on a quarterly basis. Forecasts for the product group follows. The opening inventory is 270 units and the company want to reduce this to 150 units at the end of the year. Develop a production plan. EnviroGuard manufacturing makes two garden hoses. The production plan and the MPS are developed on a quarterly basis. Forecasts for the product group follows. The opening inventory is 270 units and the company want to reduce this to 150 units at the end of the year. Develop a production plan.  <div style=padding-top: 35px>
Question
The planning horizon is the time span for which plans are made.
Question
If the total planned production of all items in the family and the total ending inventory do not agree with the production plan, some adjustment to the individual plans must be made so the total production is the same.
Question
The production plan limits the MPS. Therefore the total of the items int he MPS should be different from the total shown on the production plan.
Question
The planning horizon for a final assembly schedule must include time to assemble a customer's order and also should include the time necessary to manufacture the components.
Question
The production plan and the MPS uncouple the sales forecast from manufacturing by establishing a manufacturing plan.
Question
The MPS is built from forecasts and actual demand for individual end items.
Question
The MPS is a plan of what it to be produced and when. As such, it tells sales and manufacturing when goods will be available for delivery.
Question
In each of the manufacturing environments - make- to- stock, make- to- order, and assemble- to- order - master scheduling should take place where the largest number of product options exist.
Question
The term "master schedule" refers to the process of arriving at the master production schedule.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/29
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 3: Master Scheduling
1
Events that make it necessary to alter the MPS include:

A) problems in production
B) scarce components
C) demand changes
D) all of the above
D
2
Master production scheduling's functions include:

A) to plan capacity requirements
B) to form the link between production planning and what manufacturing builds
C) to plan material requirements
D) all of the above
D
3
Why is the MPS such a vital link in the production planning system?
It forms the link between production planning and what manufacturing will actually build. It forms the basis for calculating the capacity and resources needed. The MPS drives the material requirements plan. As a schedule of items to be built, the MPS and bills of material determine what components are needed from manufacturing and purchasing. It also keeps priorities valid. The MPS is a priority plan for manufacturing.
4
Daisy's dog food manufactures a premium line of pet food. The most popular is the beef delight and the sales department has prepared a forecast for six weeks. The opening inventory is 30 cases. Prepare a MPS. The dog food is manufactured in lots of 100 cases. Daisy's dog food manufactures a premium line of pet food. The most popular is the beef delight and the sales department has prepared a forecast for six weeks. The opening inventory is 30 cases. Prepare a MPS. The dog food is manufactured in lots of 100 cases.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
5
Calculate the available to promise using the following data. There are 100 units on hand. Calculate the available to promise using the following data. There are 100 units on hand.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
6
What is the final assembly schedule FAS)?
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
7
How is the MPS judged?
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
8
Discuss the possible errors in customer orders?
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
9
Bruce Pet Supplies assembles cat toys from fabric which it purchases from an outside supplier. The sales department has prepared the following forecast for the "evil rat," the most popular stuffed toy. The rats are sewn and stuffed in lots of 200 and the opening inventory is 300 rats. Completed the projected available balance and the master production schedule. Bruce Pet Supplies assembles cat toys from fabric which it purchases from an outside supplier. The sales department has prepared the following forecast for the evil rat, the most popular stuffed toy. The rats are sewn and stuffed in lots of 200 and the opening inventory is 300 rats. Completed the projected available balance and the master production schedule.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
10
Using the MPS, sales and distribution can determine the __________.

A) MRP
B) MPS
C) JIT
D) ERP
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
11
The MPS must be realistic and based on what production can and will do. If it is not,

A) overloading of plant resources could result
B) underloading of plant resources could result
C) unreliable schedules will result in poor delivery performance
D) all of the above
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
12
The _________ is calculated based on whether the period is before or after the demand time fence.

A) schedule receipt
B) projected available balance
C) available to promise
D) forecast demand
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
13
What are the results of changes to production schedules?
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
14
Changes to the master production schedule will occur when:

A) machines break down or new machines are added, changing capacity
B) customers cancel or change orders
C) suppliers have problems and miss delivery dates
D) all of the above
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
15
Senior managements approval is usually required to make changes with the __________ .

A) slushy zone
B) frozen zone
C) time fence
D) demand time fence
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
16
The _________is the number of periods, beginning with period 1, in which changes are not excepted due to excessive cost caused by schedule disruptions.

A) available to promise
B) demand time fence
C) forecast demand
D) projected available balance
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
17
Any changes can be made to the MRP as long as it is within the limits set by the production plan in the _________ .

A) liquid zone
B) frozen zone
C) demand time fence
D) slushy zone
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
18
The planning horizon must cover a period less than the time required to accomplish the plan.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
19
A _________is an order that has been issued, either to manufacturing or to a supplier.

A) delivery promise
B) master production schedule
C) scheduled receipt
D) available to promise
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
20
EnviroGuard manufacturing makes two garden hoses. The production plan and the MPS are developed on a quarterly basis. Forecasts for the product group follows. The opening inventory is 270 units and the company want to reduce this to 150 units at the end of the year. Develop a production plan. EnviroGuard manufacturing makes two garden hoses. The production plan and the MPS are developed on a quarterly basis. Forecasts for the product group follows. The opening inventory is 270 units and the company want to reduce this to 150 units at the end of the year. Develop a production plan.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
21
The planning horizon is the time span for which plans are made.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
22
If the total planned production of all items in the family and the total ending inventory do not agree with the production plan, some adjustment to the individual plans must be made so the total production is the same.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
23
The production plan limits the MPS. Therefore the total of the items int he MPS should be different from the total shown on the production plan.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
24
The planning horizon for a final assembly schedule must include time to assemble a customer's order and also should include the time necessary to manufacture the components.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
25
The production plan and the MPS uncouple the sales forecast from manufacturing by establishing a manufacturing plan.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
26
The MPS is built from forecasts and actual demand for individual end items.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
27
The MPS is a plan of what it to be produced and when. As such, it tells sales and manufacturing when goods will be available for delivery.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
28
In each of the manufacturing environments - make- to- stock, make- to- order, and assemble- to- order - master scheduling should take place where the largest number of product options exist.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
29
The term "master schedule" refers to the process of arriving at the master production schedule.