Deck 13: Understanding Task Dependencies, Resource Allocation, and Progress Tracking

Full screen (f)
exit full mode
Question
By default, every task in Microsoft Project is set to start:

A)finish no later than.
B)as late as possible.
C)as soon as possible.
D)finish no earlier than.
Use Space or
up arrow
down arrow
to flip the card.
Question
For task durations, the default in Microsoft Project is:

A)months.
B)days.
C)weeks.
D)hours.
Question
In Microsoft Project, defining the project's working time is a ________ step process.

A)four
B)five
C)three
D)six
Question
What is NOT among the calendar templates offered in Microsoft Project?

A)24 Hour
B)Flex time
C)Night Shift
D)Standard
Question
Microsoft Project determines the start and finish dates and times for each task based on the project's:

A)working on nonworking times.
B)estimated start date.
C)task parameters.
D)all of the above.
Question
The most time- consuming method of tracking progress in Microsoft Project is:

A)always track by entering the percent of work complete.
B)always track by entering the actual work done and work remaining.
C)always track by entering the percent of work remaining.
D)always track by entering the hours of work done per time period.
Question
In the earned value report, Microsoft Project uses________ to indicate the planned value (PV).

A)BCWS
B)BCWP
C)ACWS
D)ACWP
Question
The default view in Microsoft Project is the ________ view.

A)Network Diagram
B)tabular
C)Task Pane
D)Gantt chart
Question
Which dependency option is NOT available in the Schedule Tasks pane?

A)Start to finish
B)Start to start
C)Finish to start
D)Finish to finish
Question
What is not among the options in the "Change Working Time" dialog?

A)Full time
B)Use default
C)Nonworking time
D)Nondefault working time
Question
In the earned value report, Microsoft Project uses ________ to indicate the earned value (EV).

A)BCWS
B)ACWS
C)ACWP
D)BCWP
Question
In the earned value report, Microsoft Project uses________ to indicate the actual cost (AC).

A)BCWP
B)ACWP
C)ACWS
D)BCWS
Question
A red bar in the resource graph view indicates that the resource is________ .
Question
What is NOT an option for assigning an extra resource to a task?

A)Increase the work required for the task to keep the duration constant
B)Increase the duration to keep the work the same
C)Keep both the hours of work and the duration constant
D)Reduce the duration to keep the work the same
Question
What is NOT among the options for entering resources?

A)Enter resources manually
B)Add resources from the company Address Book
C)Add resources from a Web site
D)Add resources from the company directory
Question
The________ is a toolbar that includes the most often used tools in Microsoft Project.
Question
The fastest method of tracking progress in Microsoft Project is:

A)always track by entering the actual work done and work remaining.
B)always track by entering the hours of work done per time period.
C)always track by entering the percent of work complete.
D)always track by entering the percent of work remaining.
Question
In Microsoft Project, the correct sequence of defining a project's working time is:

A)select calendar template, manipulate days of the week, specify number of hours per day, specify non- working time, and verify calendar.
B)select calendar template, specify non- working time, manipulate days of the week, specify number of hours per day, and verify calendar.
C)select calendar template, specify non- working time, specify number of hours per day, manipulate days of the week, and verify calendar.
D)select calendar template, manipulate days of the week, specify non- working time, specify number of hours per day, and verify calendar.
Question
A moderately time- consuming method of tracking progress in Microsoft Project is:

A)always track by entering the actual work done and work remaining.
B)always track by entering the hours of work done per time period.
C)always track by entering the percent of work remaining.
D)always track by entering the percent of work complete.
Question
The resource graph view shows the:

A)percent of allocation for that resource on the dates shown.
B)resources assigned to multiple tasks.
C)number of hours each resource is working on each task on a given day.
D)none of the above.
Question
Microsoft Project calculates schedules based on________ .
Question
You can choose between all four task dependencies in the ________ dialog box.
Question
"Always track by entering the actual work done and work remaining" is the ________ accurate method of tracking.
Question
The dialog "________ " allows you to access a variety of different views.
Question
"Always track by entering the hours of work done per time period" is the________ accurate method of tracking.
Question
"Always track by entering the percent of work complete" is the ________ accurate method of tracking.
Question
In the resource entry table, the type________ is reserved for human resources.
Question
Microsoft Project determines the start and finish dates and times for each task based on the project's estimated start date, working on nonworking times, and task________ .
Question
You can group tasks into a summary task using the ________ link.
Question
To enter tasks, you can either input them directly or________ .
Question
Once a project is saved as a ________ , all subsequent changes will be shown in the relation to that plan.
Question
To specify a day as non- working time, click on________ .
Question
Before entering resources, you should identify the ________ that comprise the resources for your project.
Question
The________ view shows the number of hours each resource is working on each task on a given day.
Question
Once you have specified all resources and determined the working times, you can________
.
Question
The________ view shows the percent of allocation for a resource on the dates shown.
Question
Major tasks in a project can be marked as ________ .
Question
________ have a duration of zero.
Question
The________ view allows you to see at a glance how your project is progressing.
Question
The________ column allows to specify the units of a material resource.
Question
The first time you assign resources to a task, Project calculates the duration of the task by multiplying the work required to complete the task by the percentage of work units.
Question
In Microsoft Project, you can specify working times for individual resources that are different from the project's normal working time.
Question
Project can generate WBS numbering codes to identify the levels of decomposition for each task level.
Question
Always track by entering the actual work done and work remaining is the fastest but least accurate method of tracking progress in Microsoft Project.
Question
In Microsoft Project, you can only use one calendar for all resources.
Question
In Microsoft Project, once a critical path task has been completed, it is no longer considered a critical task.
Question
If a task does not take a full day, you should enter the time in ________ .
Question
When scheduling tasks in Microsoft Project, you should always set the start and finish dates.
Question
Always track by entering the hours of work done per time period is the most accurate, though time- consuming, method of tracking progress in Microsoft Project.
Question
In the tracking Gantt chart view, the black bar indicates the actual progress made for the project, and the colored bar indicates the baseline plan.
Question
Having too many people assigned to a task can sometimes cause more problems than it solves, both administratively and financially.
Question
For several sequential tasks, you have to set the dependencies for each task individually.
Question
The first step to manage progress of a project is to save a baseline plan to compare with later versions.
Question
It is not possible to set the duration for summary tasks in Microsoft Project.
Question
Before entering material resources, you will have to enter the column "Type" into the resource table.
Question
Material resources include software and equipment, but not transportation to and from the job site.
Question
Unfortunately, you cannot see the critical path in a Gantt chart.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/57
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 13: Understanding Task Dependencies, Resource Allocation, and Progress Tracking
1
By default, every task in Microsoft Project is set to start:

A)finish no later than.
B)as late as possible.
C)as soon as possible.
D)finish no earlier than.
C
2
For task durations, the default in Microsoft Project is:

A)months.
B)days.
C)weeks.
D)hours.
B
3
In Microsoft Project, defining the project's working time is a ________ step process.

A)four
B)five
C)three
D)six
five
4
What is NOT among the calendar templates offered in Microsoft Project?

A)24 Hour
B)Flex time
C)Night Shift
D)Standard
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
5
Microsoft Project determines the start and finish dates and times for each task based on the project's:

A)working on nonworking times.
B)estimated start date.
C)task parameters.
D)all of the above.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
6
The most time- consuming method of tracking progress in Microsoft Project is:

A)always track by entering the percent of work complete.
B)always track by entering the actual work done and work remaining.
C)always track by entering the percent of work remaining.
D)always track by entering the hours of work done per time period.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
7
In the earned value report, Microsoft Project uses________ to indicate the planned value (PV).

A)BCWS
B)BCWP
C)ACWS
D)ACWP
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
8
The default view in Microsoft Project is the ________ view.

A)Network Diagram
B)tabular
C)Task Pane
D)Gantt chart
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
9
Which dependency option is NOT available in the Schedule Tasks pane?

A)Start to finish
B)Start to start
C)Finish to start
D)Finish to finish
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
10
What is not among the options in the "Change Working Time" dialog?

A)Full time
B)Use default
C)Nonworking time
D)Nondefault working time
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
11
In the earned value report, Microsoft Project uses ________ to indicate the earned value (EV).

A)BCWS
B)ACWS
C)ACWP
D)BCWP
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
12
In the earned value report, Microsoft Project uses________ to indicate the actual cost (AC).

A)BCWP
B)ACWP
C)ACWS
D)BCWS
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
13
A red bar in the resource graph view indicates that the resource is________ .
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
14
What is NOT an option for assigning an extra resource to a task?

A)Increase the work required for the task to keep the duration constant
B)Increase the duration to keep the work the same
C)Keep both the hours of work and the duration constant
D)Reduce the duration to keep the work the same
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
15
What is NOT among the options for entering resources?

A)Enter resources manually
B)Add resources from the company Address Book
C)Add resources from a Web site
D)Add resources from the company directory
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
16
The________ is a toolbar that includes the most often used tools in Microsoft Project.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
17
The fastest method of tracking progress in Microsoft Project is:

A)always track by entering the actual work done and work remaining.
B)always track by entering the hours of work done per time period.
C)always track by entering the percent of work complete.
D)always track by entering the percent of work remaining.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
18
In Microsoft Project, the correct sequence of defining a project's working time is:

A)select calendar template, manipulate days of the week, specify number of hours per day, specify non- working time, and verify calendar.
B)select calendar template, specify non- working time, manipulate days of the week, specify number of hours per day, and verify calendar.
C)select calendar template, specify non- working time, specify number of hours per day, manipulate days of the week, and verify calendar.
D)select calendar template, manipulate days of the week, specify non- working time, specify number of hours per day, and verify calendar.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
19
A moderately time- consuming method of tracking progress in Microsoft Project is:

A)always track by entering the actual work done and work remaining.
B)always track by entering the hours of work done per time period.
C)always track by entering the percent of work remaining.
D)always track by entering the percent of work complete.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
20
The resource graph view shows the:

A)percent of allocation for that resource on the dates shown.
B)resources assigned to multiple tasks.
C)number of hours each resource is working on each task on a given day.
D)none of the above.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
21
Microsoft Project calculates schedules based on________ .
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
22
You can choose between all four task dependencies in the ________ dialog box.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
23
"Always track by entering the actual work done and work remaining" is the ________ accurate method of tracking.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
24
The dialog "________ " allows you to access a variety of different views.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
25
"Always track by entering the hours of work done per time period" is the________ accurate method of tracking.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
26
"Always track by entering the percent of work complete" is the ________ accurate method of tracking.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
27
In the resource entry table, the type________ is reserved for human resources.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
28
Microsoft Project determines the start and finish dates and times for each task based on the project's estimated start date, working on nonworking times, and task________ .
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
29
You can group tasks into a summary task using the ________ link.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
30
To enter tasks, you can either input them directly or________ .
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
31
Once a project is saved as a ________ , all subsequent changes will be shown in the relation to that plan.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
32
To specify a day as non- working time, click on________ .
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
33
Before entering resources, you should identify the ________ that comprise the resources for your project.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
34
The________ view shows the number of hours each resource is working on each task on a given day.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
35
Once you have specified all resources and determined the working times, you can________
.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
36
The________ view shows the percent of allocation for a resource on the dates shown.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
37
Major tasks in a project can be marked as ________ .
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
38
________ have a duration of zero.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
39
The________ view allows you to see at a glance how your project is progressing.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
40
The________ column allows to specify the units of a material resource.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
41
The first time you assign resources to a task, Project calculates the duration of the task by multiplying the work required to complete the task by the percentage of work units.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
42
In Microsoft Project, you can specify working times for individual resources that are different from the project's normal working time.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
43
Project can generate WBS numbering codes to identify the levels of decomposition for each task level.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
44
Always track by entering the actual work done and work remaining is the fastest but least accurate method of tracking progress in Microsoft Project.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
45
In Microsoft Project, you can only use one calendar for all resources.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
46
In Microsoft Project, once a critical path task has been completed, it is no longer considered a critical task.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
47
If a task does not take a full day, you should enter the time in ________ .
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
48
When scheduling tasks in Microsoft Project, you should always set the start and finish dates.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
49
Always track by entering the hours of work done per time period is the most accurate, though time- consuming, method of tracking progress in Microsoft Project.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
50
In the tracking Gantt chart view, the black bar indicates the actual progress made for the project, and the colored bar indicates the baseline plan.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
51
Having too many people assigned to a task can sometimes cause more problems than it solves, both administratively and financially.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
52
For several sequential tasks, you have to set the dependencies for each task individually.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
53
The first step to manage progress of a project is to save a baseline plan to compare with later versions.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
54
It is not possible to set the duration for summary tasks in Microsoft Project.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
55
Before entering material resources, you will have to enter the column "Type" into the resource table.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
56
Material resources include software and equipment, but not transportation to and from the job site.
Unlock Deck
Unlock for access to all 57 flashcards in this deck.
Unlock Deck
k this deck
57
Unfortunately, you cannot see the critical path in a Gantt chart.