Deck 9: Project Scheduling: Networks,Duration Estimation,and Critical Path

Full screen (f)
exit full mode
Question
One of the defining points of a network,a junction point joined to some or all of the others by dependency lines,is called a(n):

A) Event.
B) Path.
C) Node.
D) Burst.
Use Space or
up arrow
down arrow
to flip the card.
Question
A sequence of activities defined by the project network logic is a(n):

A) Event.
B) Path.
C) Node.
D) Route.
Question
Hammock activities allow:

A) Project managers to streamline the linkage and sequencing between activities.
B) Project workers to effectively skip nonessential activities without compromising project quality.
C) The project team to better disaggregate the overall project network into subsets.
D) The project manager to identify float more quickly and leverage it more successfully for the overall success of the project.
Question
These can be located by doing a backward pass through a network.

A) Critical paths
B) Merge activities
C) Successors
D) Burst activities
Question
<strong>  Activities C,D,and E in the project represented by the network are to be hammocked.What is the activity length of the hammock activity?</strong> A) 20 B) 16 C) 13 D) 11 <div style=padding-top: 35px>
Activities C,D,and E in the project represented by the network are to be hammocked.What is the activity length of the hammock activity?

A) 20
B) 16
C) 13
D) 11
Question
There's an old saying,"The job is not finished until the paperwork is done." From an activity network standpoint,this does not necessarily mean that the paperwork can't begin until the last non-paperwork activity is completed.It might be possible to work on some paperwork as early activities are completed.In order to depict this in an activity network:

A) Hammock activities could be drawn.
B) Subroutines could be added.
C) Shortcuts can be added to the network.
D) Laddering could be used to redraw the network.
Question
<strong>  Based on the activity network pictured,what is the BEST statement?</strong> A) Activity C is a burst activity. B) Activity E has one predecessor, Activity B. C) Activity A and Activity C are merge activities. D) There are no serial activities in this network. <div style=padding-top: 35px>
Based on the activity network pictured,what is the BEST statement?

A) Activity C is a burst activity.
B) Activity E has one predecessor, Activity B.
C) Activity A and Activity C are merge activities.
D) There are no serial activities in this network.
Question
Summaries for some subsets of the activities identified in the overall project network are called:

A) Ladder activities.
B) Hammock activities.
C) Negative float activities.
D) Compressed activities.
Question
<strong>  Based on the activity network pictured,what is the BEST statement?</strong> A) Before starting Activity C, Activity A and Activity B must be completed. B) Before starting Activity D, Activity A and Activity B need to be completed. C) Before starting Activity E, Activity A and Activity B need to be completed. D) Before starting Activity C, Activity A and Activity D must be completed. <div style=padding-top: 35px>
Based on the activity network pictured,what is the BEST statement?

A) Before starting Activity C, Activity A and Activity B must be completed.
B) Before starting Activity D, Activity A and Activity B need to be completed.
C) Before starting Activity E, Activity A and Activity B need to be completed.
D) Before starting Activity C, Activity A and Activity D must be completed.
Question
Draw a network of any size that has at least one of each of the following features: merge activity,burst activity,hammock activity,ladder activity,critical path,serial activities,concurrent activities,and float.Mark these features on your network.
Question
<strong>  Network logic suggests that:</strong> A) Activity D can start any time. B) Activity A must be complete before Activity B can be done. C) Activities A, B and C must be complete before Activity D can be done. D) Activity C must begin before Activity B begins. <div style=padding-top: 35px>
Network logic suggests that:

A) Activity D can start any time.
B) Activity A must be complete before Activity B can be done.
C) Activities A, B and C must be complete before Activity D can be done.
D) Activity C must begin before Activity B begins.
Question
Serial activities are those that:

A) Flow from one to the next in sequence.
B) Have sequential numbers.
C) Have the same numbers.
D) Should be performed simultaneously.
Question
The overall effect of laddering activities is to:

A) Streamline the linkage and sequencing between activities and keep project resources fully employed.
B) Summarize some subsets of the activities identified in the overall project network.
C) Allow the project team to disaggregate the overall project network into logical summaries.
D) Allow the project manager to more fully deploy resources and complete the project with zero slack.
Question
A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
Question
The term ordered activity means:

A) Tasks must either precede or follow other tasks in project planning and management.
B) Tasks cannot be performed unless the project manager issues a specific command to perform the work.
C) Prior project planning removes the need for any rush so that tasks can be performed in a methodical fashion.
D) Tasks are not performed unless the customer issues a specific request to perform the work.
Question
What is the background of CPM and PERT? What are the differences between the two techniques?
Question
An activity has an expected duration and an expected cost.Another name for an activity is a(n):

A) Work package.
B) Node.
C) Critical path.
D) Event.
Question
<strong>  Activities C,D,and E in the project represented by the network are to be hammocked.What are the early start and late finish times of the hammock activity?</strong> A) 6, 20 B) 6, 26 C) 9, 20 D) 9, 26 <div style=padding-top: 35px>
Activities C,D,and E in the project represented by the network are to be hammocked.What are the early start and late finish times of the hammock activity?

A) 6, 20
B) 6, 26
C) 9, 20
D) 9, 26
Question
Concurrent activities are:

A) Activities that must be done one after the other.
B) Activities that can be performed at the same time.
C) Activities that use labor from the same group of workers.
D) Activities that use resources from the same resource pool.
Question
<strong>  Which of these statements about this network is BEST?</strong> A) Activities A and B are serial activities. B) Activities B and C are serial activities. C) Activities A and C are serial activities. D) Activity D is a merge activity. <div style=padding-top: 35px>
Which of these statements about this network is BEST?

A) Activities A and B are serial activities.
B) Activities B and C are serial activities.
C) Activities A and C are serial activities.
D) Activity D is a merge activity.
Question
An activity has an optimistic time estimate of 25 days,a most likely estimate of 29 days,and a pessimistic estimate of 34 days.What is the expected duration of the activity?

A) Less than 31 days but greater than or equal to 29 days
B) Less than 29 days but greater than or equal to 27 days
C) Less than 27 days but greater than or equal to 25 days
D) Less than 25 days
Question
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project? <strong>Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?  </strong> A) 34 B) 38 C) 42 D) 48 <div style=padding-top: 35px>

A) 34
B) 38
C) 42
D) 48
Question
An activity has an optimistic time estimate of 17 days,a most likely estimate of 23 days,and a pessimistic estimate of 37 days.What is the variance of the activity?

A) 3.33
B) 6.66
C) 9.99
D) 11.11
Question
The variance of an activity is given by:

A) [1/6(b-a)]2.
B) 1/6[b-a].
C) [1/36(b-a)]2.
D) 1/36[b-a].
Question
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project? <strong>Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?  </strong> A) 34 B) 38 C) 42 D) 48 <div style=padding-top: 35px>

A) 34
B) 38
C) 42
D) 48
Question
A merge activity has two or more immediate predecessors.
Question
What are hammock activities and when should they be used?
Question
At a merge point in a forward pass,the largest preceding early finish becomes the early start for that node.
Question
Preceding activities are those that must occur before others can be done.
Question
An activity has an optimistic time estimate of 12 days,a most likely estimate of 16 days,and a pessimistic estimate of 22 days.What is the expected standard deviation of the activity?

A) Between 1 and 2 days
B) Between 2 and 3 days
C) Between 3 and 4 days
D) Between 4 and 5 days
Question
Prior to creating a network,it is important to:

A) Identify all loops through activities.
B) Identify the party responsible for each activity.
C) Calculate the float for each activity.
D) Understand the activity precedence.
Question
Activity Z has estimates a = 5,b = 12,m = 7; activity X has estimates a = 5,b = 11,m = 6; and activity Y has estimates a = 3,b = 11,m = 8.Which of the following statements is BEST?

A) Activity X is longer than Activity Y.
B) Activity X has a higher standard deviation than Activity Z.
C) Activity Z is shorter than Activity Y.
D) Activity Y has a smaller variance than Activity Z.
Question
Burst activities are those with two or more successor activities.
Question
An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time.If the activity variance is 12,what is the expected time?

A) About 8 days
B) About 9 days
C) About 10 days
D) About 11 days
Question
What does a network diagram illustrate and why are they important in project management?
Question
Ray's shipment of materials hit every red light and traffic jam on the way to the site.Upon arrival,half of the material was judged defective,necessitating a trip back to the supplier,and then the same arduous journey back to the site once the new materials were loaded.Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip.In the final analysis:

A) The project activity of Material Delivery was pretty close to the optimistic estimate.
B) The project activity of Material Delivery was pretty close to the most likely estimate.
C) The project activity of Material Delivery had a much higher variance than anticipated.
D) The project activity of Material Delivery was pretty close to the pessimistic estimate.
Question
Consider a project composed of activities X and Y having equal length and performed in that order.Both activities can be laddered such that the first half of each activity is the predecessor for its own second half,so X1 precedes X2 and Y1 precedes Y2.The first half of X1 is also the predecessor for Y1.If the laddering procedure were performed again activities X and Y would be divided in four parts each,with precedence working as it did in the first split.Derive an expression for the minimum length of the project as laddering increases.
Question
The length of time expected to complete an activity assuming that its development proceeds normally is called the:

A) Optimistic duration.
B) Pessimistic duration.
C) Most likely duration.
D) Normal duration.
Question
An activity has an optimistic time estimate of 17 days,a most likely estimate of 22 days,and a pessimistic estimate of 32 days.What is the expected duration of the activity?

A) 22.83 days
B) 23.67 days
C) 24.33 days
D) 25.17 days
Question
At a burst point in a backward pass,the largest succeeding late start becomes the late finish for that node.
Question
You must know the mean of an activity in order to determine its standard deviation.
Question
What is the early start time for Activity D given the activity times and precedence requirements shown in the table? <strong>What is the early start time for Activity D given the activity times and precedence requirements shown in the table?  </strong> A) 7 B) 9 C) 11 D) 13 <div style=padding-top: 35px>

A) 7
B) 9
C) 11
D) 13
Question
Hammock activities break a task into greater levels of detail so that each task is represented as two or more subtasks that each have their own duration and precedence requirements.
Question
Use the information in the table to determine the late start time for Activity E. <strong>Use the information in the table to determine the late start time for Activity E.  </strong> A) Day 23 B) Day 26 C) Day 32 D) Day 17 <div style=padding-top: 35px>

A) Day 23
B) Day 26
C) Day 32
D) Day 17
Question
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the expected completion time of the project? <strong>A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the expected completion time of the project?  </strong> A) 32 days B) 33 days C) 34 days D) 35 days <div style=padding-top: 35px>

A) 32 days
B) 33 days
C) 34 days
D) 35 days
Question
The late start time should be calculated using a forward pass through the network.
Question
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table? <strong>What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?  </strong> A) 15 B) 17 C) 19 D) 21 <div style=padding-top: 35px>

A) 15
B) 17
C) 19
D) 21
Question
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why? Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?  <div style=padding-top: 35px>
Question
Laddering is a technique that allows the project manager to redraw the network to more closely sequence project subtasks to make the overall network sequence more efficient.
Question
In assigning a value for the most pessimistic (b)duration,the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.
Question
Use the information in the table to determine the early start time for Activity B. <strong>Use the information in the table to determine the early start time for Activity B.  </strong> A) Day 10 B) Day 8 C) Day 9 D) Day 11 <div style=padding-top: 35px>

A) Day 10
B) Day 8
C) Day 9
D) Day 11
Question
What are three methods of duration estimation for project activities and what are the advantages and disadvantages of each method?
Question
What is the late start time for Activity B given the activity times and precedence requirements shown in the table? <strong>What is the late start time for Activity B given the activity times and precedence requirements shown in the table?  </strong> A) 11 B) 9 C) 7 D) 5 <div style=padding-top: 35px>

A) 11
B) 9
C) 7
D) 5
Question
What is the late finish time for Activity D given the activity times and precedence requirements shown in the table? <strong>What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?  </strong> A) 14 B) 13 C) 12 D) 11 <div style=padding-top: 35px>

A) 14
B) 13
C) 12
D) 11
Question
What is the late start time for Activity E given the activity times and precedence requirements shown in the table? <strong>What is the late start time for Activity E given the activity times and precedence requirements shown in the table?  </strong> A) 14 B) 15 C) 16 D) 17 <div style=padding-top: 35px>

A) 14
B) 15
C) 16
D) 17
Question
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the standard deviation of the project's critical path? <strong>A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the standard deviation of the project's critical path?  </strong> A) 1.33 days B) 1.56 days C) 1.25 days D) 1.75 days <div style=padding-top: 35px>

A) 1.33 days
B) 1.56 days
C) 1.25 days
D) 1.75 days
Question
What is the early start time for Activity G given the activity times and precedence requirements shown in the table? <strong>What is the early start time for Activity G given the activity times and precedence requirements shown in the table?  </strong> A) 22 B) 21 C) 20 D) 19 <div style=padding-top: 35px>

A) 22
B) 21
C) 20
D) 19
Question
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?  <div style=padding-top: 35px>
Question
What is the underlying theory to the three time estimates approach? What data distribution should be applied in this case and what confidence should a project manager place in the calculations associated with this technique?
Question
<strong>  What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?</strong> A) Day 15 B) Day 7 C) Day 5 D) Day 3 <div style=padding-top: 35px>
What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?

A) Day 15
B) Day 7
C) Day 5
D) Day 3
Question
Phoebe B.Beebee is constructing a canal for the annual canoe races and has identified eleven activities that are required to complete this important project.She calculated early and late start times and early and late finish times but spilled coffee all over her printout.Use the remaining information to reconstruct the table for Phoebe B.Beebee and her new canoe canal.
Phoebe B.Beebee is constructing a canal for the annual canoe races and has identified eleven activities that are required to complete this important project.She calculated early and late start times and early and late finish times but spilled coffee all over her printout.Use the remaining information to reconstruct the table for Phoebe B.Beebee and her new canoe canal.  <div style=padding-top: 35px>
Question
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project? <strong>Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project?  </strong> A) 3 B) 5 C) 7 D) 9 <div style=padding-top: 35px>

A) 3
B) 5
C) 7
D) 9
Question
The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:

A) Delay.
B) Float.
C) Late start.
D) Late finish.
Question
Use the information in the table to sketch the network and compute early and late start times.
Use the information in the table to sketch the network and compute early and late start times.  <div style=padding-top: 35px>
Question
Construct a network using the information in the table and identify the critical path.
Construct a network using the information in the table and identify the critical path.  <div style=padding-top: 35px>
Question
<strong>  Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.</strong> A) 8 B) 13 C) 14 D) 21 <div style=padding-top: 35px>
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

A) 8
B) 13
C) 14
D) 21
Question
<strong>  Use the network diagram and activity lengths in the nodes to determine the late start time for activity F.</strong> A) 21 B) 24 C) 26 D) 23 <div style=padding-top: 35px>
Use the network diagram and activity lengths in the nodes to determine the late start time for activity F.

A) 21
B) 24
C) 26
D) 23
Question
What is the slack time for Activity B given the activity times and precedence requirements shown in the table? <strong>What is the slack time for Activity B given the activity times and precedence requirements shown in the table?  </strong> A) 10 B) 9 C) 8 D) 7 <div style=padding-top: 35px>

A) 10
B) 9
C) 8
D) 7
Question
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity? <strong>A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?  </strong> A) 11, 30 B) 7, 24 C) 11, 24 D) 7, 36 <div style=padding-top: 35px>

A) 11, 30
B) 7, 24
C) 11, 24
D) 7, 36
Question
<strong>  Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.</strong> A) 12 B) 13 C) 14 D) 15 <div style=padding-top: 35px>
Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.

A) 12
B) 13
C) 14
D) 15
Question
<strong>  Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.</strong> A) 8 B) 13 C) 14 D) 21 <div style=padding-top: 35px>
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

A) 8
B) 13
C) 14
D) 21
Question
<strong>  Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.</strong> A) 26 B) 25 C) 24 D) 23 <div style=padding-top: 35px>
Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.

A) 26
B) 25
C) 24
D) 23
Question
Use the information in the table to sketch the network and compute early and late start times.
Use the information in the table to sketch the network and compute early and late start times.  <div style=padding-top: 35px>
Question
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities H and I can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity? <strong>A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities H and I can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?  </strong> A) 13, 36 B) 13, 24 C) 24, 36 D) 7, 36 <div style=padding-top: 35px>

A) 13, 36
B) 13, 24
C) 24, 36
D) 7, 36
Question
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the late finish for the Plant Posts activity? <strong>A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the late finish for the Plant Posts activity?  </strong> A) 13.3 days B) 8 days C) 20.83 days D) 22 days <div style=padding-top: 35px>

A) 13.3 days
B) 8 days
C) 20.83 days
D) 22 days
Question
Use the information in the table to determine the early finish time for Activity D. <strong>Use the information in the table to determine the early finish time for Activity D.  </strong> A) Day 23 B) Day 26 C) Day 29 D) Day 32 <div style=padding-top: 35px>

A) Day 23
B) Day 26
C) Day 29
D) Day 32
Question
The least amount of float is found:

A) In a resource-limited schedule.
B) After a burst activity.
C) On the critical path.
D) After a merge activity.
Question
What is the slack time for Activity D given the activity times and precedence requirements shown in the table? <strong>What is the slack time for Activity D given the activity times and precedence requirements shown in the table?  </strong> A) 2 B) 1 C) 0 D) 3 <div style=padding-top: 35px>

A) 2
B) 1
C) 0
D) 3
Question
Use the information in the table to determine the late finish time for Activity B. <strong>Use the information in the table to determine the late finish time for Activity B.  </strong> A) Day 17 B) Day 20 C) Day 23 D) Day 26 <div style=padding-top: 35px>

A) Day 17
B) Day 20
C) Day 23
D) Day 26
Question
Compute early and late start and finish times for the network shown.
Compute early and late start and finish times for the network shown.  <div style=padding-top: 35px>
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/105
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 9: Project Scheduling: Networks,Duration Estimation,and Critical Path
1
One of the defining points of a network,a junction point joined to some or all of the others by dependency lines,is called a(n):

A) Event.
B) Path.
C) Node.
D) Burst.
C
2
A sequence of activities defined by the project network logic is a(n):

A) Event.
B) Path.
C) Node.
D) Route.
B
3
Hammock activities allow:

A) Project managers to streamline the linkage and sequencing between activities.
B) Project workers to effectively skip nonessential activities without compromising project quality.
C) The project team to better disaggregate the overall project network into subsets.
D) The project manager to identify float more quickly and leverage it more successfully for the overall success of the project.
C
4
These can be located by doing a backward pass through a network.

A) Critical paths
B) Merge activities
C) Successors
D) Burst activities
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
5
<strong>  Activities C,D,and E in the project represented by the network are to be hammocked.What is the activity length of the hammock activity?</strong> A) 20 B) 16 C) 13 D) 11
Activities C,D,and E in the project represented by the network are to be hammocked.What is the activity length of the hammock activity?

A) 20
B) 16
C) 13
D) 11
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
6
There's an old saying,"The job is not finished until the paperwork is done." From an activity network standpoint,this does not necessarily mean that the paperwork can't begin until the last non-paperwork activity is completed.It might be possible to work on some paperwork as early activities are completed.In order to depict this in an activity network:

A) Hammock activities could be drawn.
B) Subroutines could be added.
C) Shortcuts can be added to the network.
D) Laddering could be used to redraw the network.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
7
<strong>  Based on the activity network pictured,what is the BEST statement?</strong> A) Activity C is a burst activity. B) Activity E has one predecessor, Activity B. C) Activity A and Activity C are merge activities. D) There are no serial activities in this network.
Based on the activity network pictured,what is the BEST statement?

A) Activity C is a burst activity.
B) Activity E has one predecessor, Activity B.
C) Activity A and Activity C are merge activities.
D) There are no serial activities in this network.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
8
Summaries for some subsets of the activities identified in the overall project network are called:

A) Ladder activities.
B) Hammock activities.
C) Negative float activities.
D) Compressed activities.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
9
<strong>  Based on the activity network pictured,what is the BEST statement?</strong> A) Before starting Activity C, Activity A and Activity B must be completed. B) Before starting Activity D, Activity A and Activity B need to be completed. C) Before starting Activity E, Activity A and Activity B need to be completed. D) Before starting Activity C, Activity A and Activity D must be completed.
Based on the activity network pictured,what is the BEST statement?

A) Before starting Activity C, Activity A and Activity B must be completed.
B) Before starting Activity D, Activity A and Activity B need to be completed.
C) Before starting Activity E, Activity A and Activity B need to be completed.
D) Before starting Activity C, Activity A and Activity D must be completed.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
10
Draw a network of any size that has at least one of each of the following features: merge activity,burst activity,hammock activity,ladder activity,critical path,serial activities,concurrent activities,and float.Mark these features on your network.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
11
<strong>  Network logic suggests that:</strong> A) Activity D can start any time. B) Activity A must be complete before Activity B can be done. C) Activities A, B and C must be complete before Activity D can be done. D) Activity C must begin before Activity B begins.
Network logic suggests that:

A) Activity D can start any time.
B) Activity A must be complete before Activity B can be done.
C) Activities A, B and C must be complete before Activity D can be done.
D) Activity C must begin before Activity B begins.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
12
Serial activities are those that:

A) Flow from one to the next in sequence.
B) Have sequential numbers.
C) Have the same numbers.
D) Should be performed simultaneously.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
13
The overall effect of laddering activities is to:

A) Streamline the linkage and sequencing between activities and keep project resources fully employed.
B) Summarize some subsets of the activities identified in the overall project network.
C) Allow the project team to disaggregate the overall project network into logical summaries.
D) Allow the project manager to more fully deploy resources and complete the project with zero slack.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
14
A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
15
The term ordered activity means:

A) Tasks must either precede or follow other tasks in project planning and management.
B) Tasks cannot be performed unless the project manager issues a specific command to perform the work.
C) Prior project planning removes the need for any rush so that tasks can be performed in a methodical fashion.
D) Tasks are not performed unless the customer issues a specific request to perform the work.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
16
What is the background of CPM and PERT? What are the differences between the two techniques?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
17
An activity has an expected duration and an expected cost.Another name for an activity is a(n):

A) Work package.
B) Node.
C) Critical path.
D) Event.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
18
<strong>  Activities C,D,and E in the project represented by the network are to be hammocked.What are the early start and late finish times of the hammock activity?</strong> A) 6, 20 B) 6, 26 C) 9, 20 D) 9, 26
Activities C,D,and E in the project represented by the network are to be hammocked.What are the early start and late finish times of the hammock activity?

A) 6, 20
B) 6, 26
C) 9, 20
D) 9, 26
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
19
Concurrent activities are:

A) Activities that must be done one after the other.
B) Activities that can be performed at the same time.
C) Activities that use labor from the same group of workers.
D) Activities that use resources from the same resource pool.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
20
<strong>  Which of these statements about this network is BEST?</strong> A) Activities A and B are serial activities. B) Activities B and C are serial activities. C) Activities A and C are serial activities. D) Activity D is a merge activity.
Which of these statements about this network is BEST?

A) Activities A and B are serial activities.
B) Activities B and C are serial activities.
C) Activities A and C are serial activities.
D) Activity D is a merge activity.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
21
An activity has an optimistic time estimate of 25 days,a most likely estimate of 29 days,and a pessimistic estimate of 34 days.What is the expected duration of the activity?

A) Less than 31 days but greater than or equal to 29 days
B) Less than 29 days but greater than or equal to 27 days
C) Less than 27 days but greater than or equal to 25 days
D) Less than 25 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
22
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project? <strong>Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?  </strong> A) 34 B) 38 C) 42 D) 48

A) 34
B) 38
C) 42
D) 48
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
23
An activity has an optimistic time estimate of 17 days,a most likely estimate of 23 days,and a pessimistic estimate of 37 days.What is the variance of the activity?

A) 3.33
B) 6.66
C) 9.99
D) 11.11
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
24
The variance of an activity is given by:

A) [1/6(b-a)]2.
B) 1/6[b-a].
C) [1/36(b-a)]2.
D) 1/36[b-a].
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
25
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project? <strong>Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?  </strong> A) 34 B) 38 C) 42 D) 48

A) 34
B) 38
C) 42
D) 48
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
26
A merge activity has two or more immediate predecessors.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
27
What are hammock activities and when should they be used?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
28
At a merge point in a forward pass,the largest preceding early finish becomes the early start for that node.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
29
Preceding activities are those that must occur before others can be done.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
30
An activity has an optimistic time estimate of 12 days,a most likely estimate of 16 days,and a pessimistic estimate of 22 days.What is the expected standard deviation of the activity?

A) Between 1 and 2 days
B) Between 2 and 3 days
C) Between 3 and 4 days
D) Between 4 and 5 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
31
Prior to creating a network,it is important to:

A) Identify all loops through activities.
B) Identify the party responsible for each activity.
C) Calculate the float for each activity.
D) Understand the activity precedence.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
32
Activity Z has estimates a = 5,b = 12,m = 7; activity X has estimates a = 5,b = 11,m = 6; and activity Y has estimates a = 3,b = 11,m = 8.Which of the following statements is BEST?

A) Activity X is longer than Activity Y.
B) Activity X has a higher standard deviation than Activity Z.
C) Activity Z is shorter than Activity Y.
D) Activity Y has a smaller variance than Activity Z.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
33
Burst activities are those with two or more successor activities.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
34
An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time.If the activity variance is 12,what is the expected time?

A) About 8 days
B) About 9 days
C) About 10 days
D) About 11 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
35
What does a network diagram illustrate and why are they important in project management?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
36
Ray's shipment of materials hit every red light and traffic jam on the way to the site.Upon arrival,half of the material was judged defective,necessitating a trip back to the supplier,and then the same arduous journey back to the site once the new materials were loaded.Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip.In the final analysis:

A) The project activity of Material Delivery was pretty close to the optimistic estimate.
B) The project activity of Material Delivery was pretty close to the most likely estimate.
C) The project activity of Material Delivery had a much higher variance than anticipated.
D) The project activity of Material Delivery was pretty close to the pessimistic estimate.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
37
Consider a project composed of activities X and Y having equal length and performed in that order.Both activities can be laddered such that the first half of each activity is the predecessor for its own second half,so X1 precedes X2 and Y1 precedes Y2.The first half of X1 is also the predecessor for Y1.If the laddering procedure were performed again activities X and Y would be divided in four parts each,with precedence working as it did in the first split.Derive an expression for the minimum length of the project as laddering increases.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
38
The length of time expected to complete an activity assuming that its development proceeds normally is called the:

A) Optimistic duration.
B) Pessimistic duration.
C) Most likely duration.
D) Normal duration.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
39
An activity has an optimistic time estimate of 17 days,a most likely estimate of 22 days,and a pessimistic estimate of 32 days.What is the expected duration of the activity?

A) 22.83 days
B) 23.67 days
C) 24.33 days
D) 25.17 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
40
At a burst point in a backward pass,the largest succeeding late start becomes the late finish for that node.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
41
You must know the mean of an activity in order to determine its standard deviation.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
42
What is the early start time for Activity D given the activity times and precedence requirements shown in the table? <strong>What is the early start time for Activity D given the activity times and precedence requirements shown in the table?  </strong> A) 7 B) 9 C) 11 D) 13

A) 7
B) 9
C) 11
D) 13
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
43
Hammock activities break a task into greater levels of detail so that each task is represented as two or more subtasks that each have their own duration and precedence requirements.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
44
Use the information in the table to determine the late start time for Activity E. <strong>Use the information in the table to determine the late start time for Activity E.  </strong> A) Day 23 B) Day 26 C) Day 32 D) Day 17

A) Day 23
B) Day 26
C) Day 32
D) Day 17
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
45
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the expected completion time of the project? <strong>A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the expected completion time of the project?  </strong> A) 32 days B) 33 days C) 34 days D) 35 days

A) 32 days
B) 33 days
C) 34 days
D) 35 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
46
The late start time should be calculated using a forward pass through the network.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
47
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table? <strong>What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?  </strong> A) 15 B) 17 C) 19 D) 21

A) 15
B) 17
C) 19
D) 21
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
48
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why? Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
49
Laddering is a technique that allows the project manager to redraw the network to more closely sequence project subtasks to make the overall network sequence more efficient.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
50
In assigning a value for the most pessimistic (b)duration,the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
51
Use the information in the table to determine the early start time for Activity B. <strong>Use the information in the table to determine the early start time for Activity B.  </strong> A) Day 10 B) Day 8 C) Day 9 D) Day 11

A) Day 10
B) Day 8
C) Day 9
D) Day 11
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
52
What are three methods of duration estimation for project activities and what are the advantages and disadvantages of each method?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
53
What is the late start time for Activity B given the activity times and precedence requirements shown in the table? <strong>What is the late start time for Activity B given the activity times and precedence requirements shown in the table?  </strong> A) 11 B) 9 C) 7 D) 5

A) 11
B) 9
C) 7
D) 5
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
54
What is the late finish time for Activity D given the activity times and precedence requirements shown in the table? <strong>What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?  </strong> A) 14 B) 13 C) 12 D) 11

A) 14
B) 13
C) 12
D) 11
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
55
What is the late start time for Activity E given the activity times and precedence requirements shown in the table? <strong>What is the late start time for Activity E given the activity times and precedence requirements shown in the table?  </strong> A) 14 B) 15 C) 16 D) 17

A) 14
B) 15
C) 16
D) 17
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
56
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the standard deviation of the project's critical path? <strong>A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the standard deviation of the project's critical path?  </strong> A) 1.33 days B) 1.56 days C) 1.25 days D) 1.75 days

A) 1.33 days
B) 1.56 days
C) 1.25 days
D) 1.75 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
57
What is the early start time for Activity G given the activity times and precedence requirements shown in the table? <strong>What is the early start time for Activity G given the activity times and precedence requirements shown in the table?  </strong> A) 22 B) 21 C) 20 D) 19

A) 22
B) 21
C) 20
D) 19
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
58
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
59
What is the underlying theory to the three time estimates approach? What data distribution should be applied in this case and what confidence should a project manager place in the calculations associated with this technique?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
60
<strong>  What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?</strong> A) Day 15 B) Day 7 C) Day 5 D) Day 3
What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?

A) Day 15
B) Day 7
C) Day 5
D) Day 3
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
61
Phoebe B.Beebee is constructing a canal for the annual canoe races and has identified eleven activities that are required to complete this important project.She calculated early and late start times and early and late finish times but spilled coffee all over her printout.Use the remaining information to reconstruct the table for Phoebe B.Beebee and her new canoe canal.
Phoebe B.Beebee is constructing a canal for the annual canoe races and has identified eleven activities that are required to complete this important project.She calculated early and late start times and early and late finish times but spilled coffee all over her printout.Use the remaining information to reconstruct the table for Phoebe B.Beebee and her new canoe canal.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
62
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project? <strong>Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project?  </strong> A) 3 B) 5 C) 7 D) 9

A) 3
B) 5
C) 7
D) 9
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
63
The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:

A) Delay.
B) Float.
C) Late start.
D) Late finish.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
64
Use the information in the table to sketch the network and compute early and late start times.
Use the information in the table to sketch the network and compute early and late start times.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
65
Construct a network using the information in the table and identify the critical path.
Construct a network using the information in the table and identify the critical path.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
66
<strong>  Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.</strong> A) 8 B) 13 C) 14 D) 21
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

A) 8
B) 13
C) 14
D) 21
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
67
<strong>  Use the network diagram and activity lengths in the nodes to determine the late start time for activity F.</strong> A) 21 B) 24 C) 26 D) 23
Use the network diagram and activity lengths in the nodes to determine the late start time for activity F.

A) 21
B) 24
C) 26
D) 23
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
68
What is the slack time for Activity B given the activity times and precedence requirements shown in the table? <strong>What is the slack time for Activity B given the activity times and precedence requirements shown in the table?  </strong> A) 10 B) 9 C) 8 D) 7

A) 10
B) 9
C) 8
D) 7
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
69
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity? <strong>A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?  </strong> A) 11, 30 B) 7, 24 C) 11, 24 D) 7, 36

A) 11, 30
B) 7, 24
C) 11, 24
D) 7, 36
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
70
<strong>  Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.</strong> A) 12 B) 13 C) 14 D) 15
Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.

A) 12
B) 13
C) 14
D) 15
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
71
<strong>  Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.</strong> A) 8 B) 13 C) 14 D) 21
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

A) 8
B) 13
C) 14
D) 21
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
72
<strong>  Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.</strong> A) 26 B) 25 C) 24 D) 23
Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.

A) 26
B) 25
C) 24
D) 23
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
73
Use the information in the table to sketch the network and compute early and late start times.
Use the information in the table to sketch the network and compute early and late start times.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
74
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities H and I can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity? <strong>A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities H and I can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?  </strong> A) 13, 36 B) 13, 24 C) 24, 36 D) 7, 36

A) 13, 36
B) 13, 24
C) 24, 36
D) 7, 36
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
75
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the late finish for the Plant Posts activity? <strong>A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the late finish for the Plant Posts activity?  </strong> A) 13.3 days B) 8 days C) 20.83 days D) 22 days

A) 13.3 days
B) 8 days
C) 20.83 days
D) 22 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
76
Use the information in the table to determine the early finish time for Activity D. <strong>Use the information in the table to determine the early finish time for Activity D.  </strong> A) Day 23 B) Day 26 C) Day 29 D) Day 32

A) Day 23
B) Day 26
C) Day 29
D) Day 32
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
77
The least amount of float is found:

A) In a resource-limited schedule.
B) After a burst activity.
C) On the critical path.
D) After a merge activity.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
78
What is the slack time for Activity D given the activity times and precedence requirements shown in the table? <strong>What is the slack time for Activity D given the activity times and precedence requirements shown in the table?  </strong> A) 2 B) 1 C) 0 D) 3

A) 2
B) 1
C) 0
D) 3
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
79
Use the information in the table to determine the late finish time for Activity B. <strong>Use the information in the table to determine the late finish time for Activity B.  </strong> A) Day 17 B) Day 20 C) Day 23 D) Day 26

A) Day 17
B) Day 20
C) Day 23
D) Day 26
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
80
Compute early and late start and finish times for the network shown.
Compute early and late start and finish times for the network shown.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 105 flashcards in this deck.