Deck 10: Project Scheduling: Lagging, crashing, and Activity Networks

Full screen (f)
exit full mode
Question
Gantt charts cannot depict float.
Use Space or
up arrow
down arrow
to flip the card.
Question
The most common type of logical sequencing between tasks is the ________ relationship.
Question
________ represent one of the first attempts to develop a network diagram that orders project activities by baseline calendar dates.
Question
In an actual project,one means of crashing critical path activities would be to perform at a lower level of quality.
Question
The critical path may not contain a dummy activity.
Question
In order to accelerate completion of a project,the manager must crash critical path activities.
Question
Quite often the marginal gains in employee productivity decrease dramatically with the increased use of overtime.
Question
Networks are adaptable and useful for all scheduling challenges that an organization faces.
Question
Most activity estimations using PERT methods lead to overly optimistic activity duration estimates.
Question
The logical relationship between the start and finish of one activity and the start and finish of another activity is the ________.
Question
Gantt charts can display early start or late start logic.
Question
Finish to start lags are the same as additional activity slack.
Question
The least common type of lag relationship occurs when a successor's finish is dependent upon a predecessor's start.
Question
Most project management software employs AOA diagramming
Question
For large projects,network diagrams are more useful if they are completely detailed.
Question
Start-to-start lags are becoming increasingly used as a means to accelerate projects through a process known as ________.
Question
AOA is a more useful technique than AON if the project is complex and has many significant milestones.
Question
A(n)________ relationship is appropriate where two or more linked activities must be completed before a successor is begun.
Question
Dummy activities are used in AOA networks to indicate the existence of precedent relationships between activities and their event nodes.
Question
Brook's Law states that the typical crashing decision to add more resources to an activity only delays the activity further.
Question
Each individual bar on a Gantt chart represents a(n)________.
Question
Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B? <strong>Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B?  </strong> A)The early finish for A increases to 31. B)The early start time for A increases to 24. C)The early finish time for B increases to 31. D)The early start time for D falls to 23. <div style=padding-top: 35px>

A)The early finish for A increases to 31.
B)The early start time for A increases to 24.
C)The early finish time for B increases to 31.
D)The early start time for D falls to 23.
Question
The three principal methods for accelerating project activities are to change the ________,________,and ________ of the project resources.
Question
In analyzing crash options for project activities,each activity has a slope that is calculated as the ________ divided by the ________.
Question
The most common type of logical sequencing between tasks is referred to as the:

A)finish to start relationship.
B)finish to finish relationship.
C)start to start relationship.
D)start to finish relationship.
Question
An activity of duration zero whose sole purpose is to maintain network logic is a(n)________.
Question
Use the Gantt chart and the activity list to determine which resource is used the least. <strong>Use the Gantt chart and the activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 3 C)Resource 4 D)Resource 2 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 3 C)Resource 4 D)Resource 2 <div style=padding-top: 35px>

A)Resource 1
B)Resource 3
C)Resource 4
D)Resource 2
Question
The horizontal axis for a Gantt chart is ________.
Question
The process of accelerating a project is referred to as ________.
Question
Which statement about this Gantt chart is best? <strong>Which statement about this Gantt chart is best?  </strong> A)Activity a has a duration that could be as short as 1 day and as long as 10. B)Activity b probably has activity a as a predecessor. C)No progress has been made on activity c. D)Activity d is the longest activity. <div style=padding-top: 35px>

A)Activity a has a duration that could be as short as 1 day and as long as 10.
B)Activity b probably has activity a as a predecessor.
C)No progress has been made on activity c.
D)Activity d is the longest activity.
Question
PERT analysis is based on ________ estimates,which,if unreasonably determined,can lead to inaccurate and misleading project schedules.
Question
The primary drawback with ________ occurs when the project is very complex,with numerous paths through the model.
Question
If a project is extraordinarily complex,rather than showing every possible path through the network and every activity sequence,a(n)________ that shows only the key subroutines or network paths can be created.
Question
Use the Gantt chart and the activity list to determine when resource 5 is free. <strong>Use the Gantt chart and the activity list to determine when resource 5 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine when resource 5 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60 <div style=padding-top: 35px>

A)between 0 and 15
B)between 15 and 30
C)between 30 and 45
D)between 45 and 60
Question
Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project? <strong>Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project?  </strong> A)10 minutes B)15 minutes C)0 minutes D)5 minutes <div style=padding-top: 35px>

A)10 minutes
B)15 minutes
C)0 minutes
D)5 minutes
Question
What is the early start time for activity C if it has the start to start relationship shown? <strong>What is the early start time for activity C if it has the start to start relationship shown?  </strong> A)day 20 B)day 25 C)day 27 D)day 29 <div style=padding-top: 35px>

A)day 20
B)day 25
C)day 27
D)day 29
Question
The two primary drawbacks to the use of overtime as a means of crashing a product are the ________ and the ________.
Question
A finish to start lag delay is usually shown:

A)as an added value in the predecessor's activity time.
B)on the line adjoining the two activity nodes.
C)as an added value in the predecessors early start time.
D)as a subtracted value in the follower's early finish time.
Question
Use the Gantt chart and the activity list to determine when resource 2 is free. <strong>Use the Gantt chart and the activity list to determine when resource 2 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine when resource 2 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60 <div style=padding-top: 35px>

A)between 0 and 15
B)between 15 and 30
C)between 30 and 45
D)between 45 and 60
Question
Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown.Which statement is best? <strong>Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown.Which statement is best?  </strong> A)a < d B)a < c C)b < c D)d < a <div style=padding-top: 35px>

A)a < d
B)a < c
C)b < c
D)d < a
Question
Which of these approaches will NOT accelerate the completion of a project?

A)Improve the productivity of existing project resources.
B)Increase the bureaucratic oversight.
C)Improve the working method.
D)Increase the quantity of personnel and equipment.
Question
A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of general laborers that costs $5,000 per week.In order to complete this activity within 10 weeks,you must hire additional general laborers at a cost of $2,000 per week.What is the slope for this activity?

A)$0 per week
B)$1,000 per week
C)$2,000 per week
D)$6,000 per week
Question
Use the Gantt chart and activity list to determine which resource has the greatest continual use. <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 4 B)Resource 2 C)Resource 3 D)Resource 5 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 4 B)Resource 2 C)Resource 3 D)Resource 5 <div style=padding-top: 35px>

A)Resource 4
B)Resource 2
C)Resource 3
D)Resource 5
Question
One reason for crashing a project is:

A)the project has slipped behind schedule.
B)that the initial schedule may be too pessimistic.
C)market needs change and the project is not in demand any more.
D)there are no repercussions for delivering the project late.
Question
Use the Gantt chart and activity list to determine which resource has the greatest continual use. <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 3 B)Resource 1 C)Resource 2 D)Resource 4 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 3 B)Resource 1 C)Resource 2 D)Resource 4 <div style=padding-top: 35px>

A)Resource 3
B)Resource 1
C)Resource 2
D)Resource 4
Question
Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others. <strong>Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2 <div style=padding-top: 35px>

A)Resource 4
B)Resource 3
C)Resource 1
D)Resource 2
Question
Use the Gantt chart and activity list to determine which resource is used the most. <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 5 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 5 <div style=padding-top: 35px>

A)Resource 4
B)Resource 2
C)Resource 1
D)Resource 5
Question
An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000.Due to slippage on the critical path you need to reduce this activity by three weeks.If the subcontractor informs you that the activity can be completed in 15 weeks for $200,000,what is the slope for the activity?

A)$20,000 per week
B)$33,333 per week
C)$5,000 per week
D)$13,333 per week
Question
A basic Gantt chart:

A)clearly displays early and late start and finish times for all activities.
B)cannot be used to track the project's progress.
C)permits scheduling resources well before they are needed.
D)shows dummy activities to preserve network logic.
Question
Use the Gantt chart and activity list to determine which resource is used the most. <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5 <div style=padding-top: 35px>

A)Resource 1
B)Resource 2
C)Resource 4
D)Resource 5
Question
Given the cost information in the table,what is the cheapest activity to crash on a per week basis? <strong>Given the cost information in the table,what is the cheapest activity to crash on a per week basis?  </strong> A)Activity A B)Activity B C)Activity C D)Activity D <div style=padding-top: 35px>

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Question
The process of accelerating a project is referred to as:

A)streamlining.
B)expediting.
C)rushing.
D)crashing.
Question
Use the Gantt chart and activity list to determine which resource is used the least. <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5 <div style=padding-top: 35px>

A)Resource 1
B)Resource 2
C)Resource 4
D)Resource 5
Question
Use the Gantt chart and the activity list to determine which resource is needed earliest in this project. <strong>Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.    </strong> A)Resource 2 B)Resource 3 C)Resource 1 D)Resource 4 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.    </strong> A)Resource 2 B)Resource 3 C)Resource 1 D)Resource 4 <div style=padding-top: 35px>

A)Resource 2
B)Resource 3
C)Resource 1
D)Resource 4
Question
Use the Gantt chart and activity list to determine when resource 3 is free. <strong>Use the Gantt chart and activity list to determine when resource 3 is free.    </strong> A)between 0 and 10 B)between 10 and 20 C)between 20 and 30 D)between 30 and 40 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine when resource 3 is free.    </strong> A)between 0 and 10 B)between 10 and 20 C)between 20 and 30 D)between 30 and 40 <div style=padding-top: 35px>

A)between 0 and 10
B)between 10 and 20
C)between 20 and 30
D)between 30 and 40
Question
If an activity's cost is plotted against its duration on axes with zeros at the origin:

A)the slope of the line is positive because it costs more to finish an activity more quickly.
B)the slope of the line is negative because a shorter activity costs less than a longer one.
C)the slope of the line is negative because it costs more to finish an activity more quickly.
D)the slope of the line is positive because a longer activity costs more than a shorter one.
Question
Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest. <strong>Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.    </strong> A)Resource 2 B)Resource 4 C)Resource 1 D)Resource 3 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.    </strong> A)Resource 2 B)Resource 4 C)Resource 1 D)Resource 3 <div style=padding-top: 35px>

A)Resource 2
B)Resource 4
C)Resource 1
D)Resource 3
Question
The most common method for shortening activity durations involves the decision to:

A)eliminate bureaucracy.
B)alter the technology used in the activity.
C)assign more senior personnel to the activity.
D)increase project resources.
Question
Use the Gantt chart and the activity list to determine which resource is used the most. <strong>Use the Gantt chart and the activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2 <div style=padding-top: 35px>

A)Resource 4
B)Resource 3
C)Resource 1
D)Resource 2
Question
Use the Gantt chart and activity list to determine which resource is used the least. <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 3 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 3 <div style=padding-top: 35px>

A)Resource 4
B)Resource 2
C)Resource 1
D)Resource 3
Question
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project in 50 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project in 50 days?  </strong> A)$253,000 B)$237,000 C)$216,000 D)$207,000 <div style=padding-top: 35px>

A)$253,000
B)$237,000
C)$216,000
D)$207,000
Question
What is the late finish for activity D in the network shown in the diagram? <strong>What is the late finish for activity D in the network shown in the diagram?  </strong> A)15 B)16 C)17 D)18 <div style=padding-top: 35px>

A)15
B)16
C)17
D)18
Question
An activity on an arrow network:

A)cannot have more arrows than nodes.
B)cannot have more nodes than arrows.
C)has one more node than arrows.
D)has one more arrow than nodes.
Question
Use the information in the table (all times are in days)to determine the lowest extra cost for an 18-day project. <strong>Use the information in the table (all times are in days)to determine the lowest extra cost for an 18-day project.  </strong> A)$380 B)$400 C)$420 D)$440 <div style=padding-top: 35px>

A)$380
B)$400
C)$420
D)$440
Question
It costs $75 per day for each day that a construction crew is on site.The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.Use this information to determine the lowest cost for this project.All times given are in days. <strong>It costs $75 per day for each day that a construction crew is on site.The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.Use this information to determine the lowest cost for this project.All times given are in days.  </strong> A)$1,800 B)$1,770 C)$1,700 D)$1,630 <div style=padding-top: 35px>

A)$1,800
B)$1,770
C)$1,700
D)$1,630
Question
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the cost of the least expensive project possible? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the cost of the least expensive project possible?  </strong> A)$18,100 B)$19,350 C)$17,416.67 D)$16,110 <div style=padding-top: 35px>

A)$18,100
B)$19,350
C)$17,416.67
D)$16,110
Question
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project?  </strong> A)$222,667 B)$217,000 C)$222,000 D)$208,000 <div style=padding-top: 35px>

A)$222,667
B)$217,000
C)$222,000
D)$208,000
Question
Dummy activities have a duration equal to the:

A)slack on the critical path.
B)length of the predecessor.
C)length of the successor.
D)lag needed to preserve network logic.
Question
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 45 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 45 days?  </strong> A)$222,667 B)$243,675 C)$258,333 D)$272,500 <div style=padding-top: 35px>

A)$222,667
B)$243,675
C)$258,333
D)$272,500
Question
The critical path of this network is: <strong>The critical path of this network is:  </strong> A)14. B)15. C)12. D)13. <div style=padding-top: 35px>

A)14.
B)15.
C)12.
D)13.
Question
Use the information in the table (all times are in days)to determine the lowest extra cost for a 20-day project. <strong>Use the information in the table (all times are in days)to determine the lowest extra cost for a 20-day project.  </strong> A)$200 B)$130 C)$120 D)$100 <div style=padding-top: 35px>

A)$200
B)$130
C)$120
D)$100
Question
The fastest completion time for this project is: <strong>The fastest completion time for this project is:  </strong> A)14. B)15. C)16. D)17. <div style=padding-top: 35px>

A)14.
B)15.
C)16.
D)17.
Question
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the duration of the least expensive project possible? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the duration of the least expensive project possible?  </strong> A)60 weeks B)57 weeks C)53 weeks D)50 weeks <div style=padding-top: 35px>

A)60 weeks
B)57 weeks
C)53 weeks
D)50 weeks
Question
The AOA network described by this table needs: <strong>The AOA network described by this table needs:  </strong> A)zero dummy activities. B)one dummy activity. C)two dummy activities. D)three dummy activities. <div style=padding-top: 35px>

A)zero dummy activities.
B)one dummy activity.
C)two dummy activities.
D)three dummy activities.
Question
The AOA network described by this table needs: <strong>The AOA network described by this table needs:  </strong> A)zero dummy activities. B)one dummy activity. C)two dummy activities. D)three dummy activities. <div style=padding-top: 35px>

A)zero dummy activities.
B)one dummy activity.
C)two dummy activities.
D)three dummy activities.
Question
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 55 weeks? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 55 weeks?  </strong> A)$16,950 B)$15,000 C)$16,350 D)$15,350 <div style=padding-top: 35px>

A)$16,950
B)$15,000
C)$16,350
D)$15,350
Question
What information is NOT included in the nodes for an AOA network?

A)label
B)early start time
C)late finish time
D)early finish time
Question
Use the information in the table (all times are in days)to determine the lowest cost minimum completion time? <strong>Use the information in the table (all times are in days)to determine the lowest cost minimum completion time?  </strong> A)$1,040 B)$1,020 C)$740 D)$720 <div style=padding-top: 35px>

A)$1,040
B)$1,020
C)$740
D)$720
Question
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project?  </strong> A)$234,000 B)$255,600 C)$248,333 D)$252,000 <div style=padding-top: 35px>

A)$234,000
B)$255,600
C)$248,333
D)$252,000
Question
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 40 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 40 days?  </strong> A)$242,667 B)$255,600 C)$263,333 D)$272,500 <div style=padding-top: 35px>

A)$242,667
B)$255,600
C)$263,333
D)$272,500
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/110
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 10: Project Scheduling: Lagging, crashing, and Activity Networks
1
Gantt charts cannot depict float.
False
2
The most common type of logical sequencing between tasks is the ________ relationship.
finish to start
3
________ represent one of the first attempts to develop a network diagram that orders project activities by baseline calendar dates.
Gantt charts
4
In an actual project,one means of crashing critical path activities would be to perform at a lower level of quality.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
5
The critical path may not contain a dummy activity.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
6
In order to accelerate completion of a project,the manager must crash critical path activities.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
7
Quite often the marginal gains in employee productivity decrease dramatically with the increased use of overtime.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
8
Networks are adaptable and useful for all scheduling challenges that an organization faces.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
9
Most activity estimations using PERT methods lead to overly optimistic activity duration estimates.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
10
The logical relationship between the start and finish of one activity and the start and finish of another activity is the ________.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
11
Gantt charts can display early start or late start logic.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
12
Finish to start lags are the same as additional activity slack.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
13
The least common type of lag relationship occurs when a successor's finish is dependent upon a predecessor's start.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
14
Most project management software employs AOA diagramming
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
15
For large projects,network diagrams are more useful if they are completely detailed.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
16
Start-to-start lags are becoming increasingly used as a means to accelerate projects through a process known as ________.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
17
AOA is a more useful technique than AON if the project is complex and has many significant milestones.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
18
A(n)________ relationship is appropriate where two or more linked activities must be completed before a successor is begun.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
19
Dummy activities are used in AOA networks to indicate the existence of precedent relationships between activities and their event nodes.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
20
Brook's Law states that the typical crashing decision to add more resources to an activity only delays the activity further.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
21
Each individual bar on a Gantt chart represents a(n)________.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
22
Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B? <strong>Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B?  </strong> A)The early finish for A increases to 31. B)The early start time for A increases to 24. C)The early finish time for B increases to 31. D)The early start time for D falls to 23.

A)The early finish for A increases to 31.
B)The early start time for A increases to 24.
C)The early finish time for B increases to 31.
D)The early start time for D falls to 23.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
23
The three principal methods for accelerating project activities are to change the ________,________,and ________ of the project resources.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
24
In analyzing crash options for project activities,each activity has a slope that is calculated as the ________ divided by the ________.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
25
The most common type of logical sequencing between tasks is referred to as the:

A)finish to start relationship.
B)finish to finish relationship.
C)start to start relationship.
D)start to finish relationship.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
26
An activity of duration zero whose sole purpose is to maintain network logic is a(n)________.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
27
Use the Gantt chart and the activity list to determine which resource is used the least. <strong>Use the Gantt chart and the activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 3 C)Resource 4 D)Resource 2 <strong>Use the Gantt chart and the activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 3 C)Resource 4 D)Resource 2

A)Resource 1
B)Resource 3
C)Resource 4
D)Resource 2
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
28
The horizontal axis for a Gantt chart is ________.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
29
The process of accelerating a project is referred to as ________.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
30
Which statement about this Gantt chart is best? <strong>Which statement about this Gantt chart is best?  </strong> A)Activity a has a duration that could be as short as 1 day and as long as 10. B)Activity b probably has activity a as a predecessor. C)No progress has been made on activity c. D)Activity d is the longest activity.

A)Activity a has a duration that could be as short as 1 day and as long as 10.
B)Activity b probably has activity a as a predecessor.
C)No progress has been made on activity c.
D)Activity d is the longest activity.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
31
PERT analysis is based on ________ estimates,which,if unreasonably determined,can lead to inaccurate and misleading project schedules.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
32
The primary drawback with ________ occurs when the project is very complex,with numerous paths through the model.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
33
If a project is extraordinarily complex,rather than showing every possible path through the network and every activity sequence,a(n)________ that shows only the key subroutines or network paths can be created.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
34
Use the Gantt chart and the activity list to determine when resource 5 is free. <strong>Use the Gantt chart and the activity list to determine when resource 5 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60 <strong>Use the Gantt chart and the activity list to determine when resource 5 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60

A)between 0 and 15
B)between 15 and 30
C)between 30 and 45
D)between 45 and 60
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
35
Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project? <strong>Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project?  </strong> A)10 minutes B)15 minutes C)0 minutes D)5 minutes

A)10 minutes
B)15 minutes
C)0 minutes
D)5 minutes
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
36
What is the early start time for activity C if it has the start to start relationship shown? <strong>What is the early start time for activity C if it has the start to start relationship shown?  </strong> A)day 20 B)day 25 C)day 27 D)day 29

A)day 20
B)day 25
C)day 27
D)day 29
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
37
The two primary drawbacks to the use of overtime as a means of crashing a product are the ________ and the ________.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
38
A finish to start lag delay is usually shown:

A)as an added value in the predecessor's activity time.
B)on the line adjoining the two activity nodes.
C)as an added value in the predecessors early start time.
D)as a subtracted value in the follower's early finish time.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
39
Use the Gantt chart and the activity list to determine when resource 2 is free. <strong>Use the Gantt chart and the activity list to determine when resource 2 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60 <strong>Use the Gantt chart and the activity list to determine when resource 2 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60

A)between 0 and 15
B)between 15 and 30
C)between 30 and 45
D)between 45 and 60
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
40
Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown.Which statement is best? <strong>Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown.Which statement is best?  </strong> A)a < d B)a < c C)b < c D)d < a

A)a < d
B)a < c
C)b < c
D)d < a
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
41
Which of these approaches will NOT accelerate the completion of a project?

A)Improve the productivity of existing project resources.
B)Increase the bureaucratic oversight.
C)Improve the working method.
D)Increase the quantity of personnel and equipment.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
42
A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of general laborers that costs $5,000 per week.In order to complete this activity within 10 weeks,you must hire additional general laborers at a cost of $2,000 per week.What is the slope for this activity?

A)$0 per week
B)$1,000 per week
C)$2,000 per week
D)$6,000 per week
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
43
Use the Gantt chart and activity list to determine which resource has the greatest continual use. <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 4 B)Resource 2 C)Resource 3 D)Resource 5 <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 4 B)Resource 2 C)Resource 3 D)Resource 5

A)Resource 4
B)Resource 2
C)Resource 3
D)Resource 5
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
44
One reason for crashing a project is:

A)the project has slipped behind schedule.
B)that the initial schedule may be too pessimistic.
C)market needs change and the project is not in demand any more.
D)there are no repercussions for delivering the project late.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
45
Use the Gantt chart and activity list to determine which resource has the greatest continual use. <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 3 B)Resource 1 C)Resource 2 D)Resource 4 <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 3 B)Resource 1 C)Resource 2 D)Resource 4

A)Resource 3
B)Resource 1
C)Resource 2
D)Resource 4
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
46
Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others. <strong>Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2 <strong>Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2

A)Resource 4
B)Resource 3
C)Resource 1
D)Resource 2
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
47
Use the Gantt chart and activity list to determine which resource is used the most. <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 5 <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 5

A)Resource 4
B)Resource 2
C)Resource 1
D)Resource 5
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
48
An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000.Due to slippage on the critical path you need to reduce this activity by three weeks.If the subcontractor informs you that the activity can be completed in 15 weeks for $200,000,what is the slope for the activity?

A)$20,000 per week
B)$33,333 per week
C)$5,000 per week
D)$13,333 per week
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
49
A basic Gantt chart:

A)clearly displays early and late start and finish times for all activities.
B)cannot be used to track the project's progress.
C)permits scheduling resources well before they are needed.
D)shows dummy activities to preserve network logic.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
50
Use the Gantt chart and activity list to determine which resource is used the most. <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5 <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5

A)Resource 1
B)Resource 2
C)Resource 4
D)Resource 5
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
51
Given the cost information in the table,what is the cheapest activity to crash on a per week basis? <strong>Given the cost information in the table,what is the cheapest activity to crash on a per week basis?  </strong> A)Activity A B)Activity B C)Activity C D)Activity D

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
52
The process of accelerating a project is referred to as:

A)streamlining.
B)expediting.
C)rushing.
D)crashing.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
53
Use the Gantt chart and activity list to determine which resource is used the least. <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5 <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5

A)Resource 1
B)Resource 2
C)Resource 4
D)Resource 5
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
54
Use the Gantt chart and the activity list to determine which resource is needed earliest in this project. <strong>Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.    </strong> A)Resource 2 B)Resource 3 C)Resource 1 D)Resource 4 <strong>Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.    </strong> A)Resource 2 B)Resource 3 C)Resource 1 D)Resource 4

A)Resource 2
B)Resource 3
C)Resource 1
D)Resource 4
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
55
Use the Gantt chart and activity list to determine when resource 3 is free. <strong>Use the Gantt chart and activity list to determine when resource 3 is free.    </strong> A)between 0 and 10 B)between 10 and 20 C)between 20 and 30 D)between 30 and 40 <strong>Use the Gantt chart and activity list to determine when resource 3 is free.    </strong> A)between 0 and 10 B)between 10 and 20 C)between 20 and 30 D)between 30 and 40

A)between 0 and 10
B)between 10 and 20
C)between 20 and 30
D)between 30 and 40
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
56
If an activity's cost is plotted against its duration on axes with zeros at the origin:

A)the slope of the line is positive because it costs more to finish an activity more quickly.
B)the slope of the line is negative because a shorter activity costs less than a longer one.
C)the slope of the line is negative because it costs more to finish an activity more quickly.
D)the slope of the line is positive because a longer activity costs more than a shorter one.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
57
Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest. <strong>Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.    </strong> A)Resource 2 B)Resource 4 C)Resource 1 D)Resource 3 <strong>Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.    </strong> A)Resource 2 B)Resource 4 C)Resource 1 D)Resource 3

A)Resource 2
B)Resource 4
C)Resource 1
D)Resource 3
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
58
The most common method for shortening activity durations involves the decision to:

A)eliminate bureaucracy.
B)alter the technology used in the activity.
C)assign more senior personnel to the activity.
D)increase project resources.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
59
Use the Gantt chart and the activity list to determine which resource is used the most. <strong>Use the Gantt chart and the activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2 <strong>Use the Gantt chart and the activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2

A)Resource 4
B)Resource 3
C)Resource 1
D)Resource 2
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
60
Use the Gantt chart and activity list to determine which resource is used the least. <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 3 <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 3

A)Resource 4
B)Resource 2
C)Resource 1
D)Resource 3
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
61
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project in 50 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project in 50 days?  </strong> A)$253,000 B)$237,000 C)$216,000 D)$207,000

A)$253,000
B)$237,000
C)$216,000
D)$207,000
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
62
What is the late finish for activity D in the network shown in the diagram? <strong>What is the late finish for activity D in the network shown in the diagram?  </strong> A)15 B)16 C)17 D)18

A)15
B)16
C)17
D)18
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
63
An activity on an arrow network:

A)cannot have more arrows than nodes.
B)cannot have more nodes than arrows.
C)has one more node than arrows.
D)has one more arrow than nodes.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
64
Use the information in the table (all times are in days)to determine the lowest extra cost for an 18-day project. <strong>Use the information in the table (all times are in days)to determine the lowest extra cost for an 18-day project.  </strong> A)$380 B)$400 C)$420 D)$440

A)$380
B)$400
C)$420
D)$440
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
65
It costs $75 per day for each day that a construction crew is on site.The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.Use this information to determine the lowest cost for this project.All times given are in days. <strong>It costs $75 per day for each day that a construction crew is on site.The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.Use this information to determine the lowest cost for this project.All times given are in days.  </strong> A)$1,800 B)$1,770 C)$1,700 D)$1,630

A)$1,800
B)$1,770
C)$1,700
D)$1,630
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
66
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the cost of the least expensive project possible? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the cost of the least expensive project possible?  </strong> A)$18,100 B)$19,350 C)$17,416.67 D)$16,110

A)$18,100
B)$19,350
C)$17,416.67
D)$16,110
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
67
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project?  </strong> A)$222,667 B)$217,000 C)$222,000 D)$208,000

A)$222,667
B)$217,000
C)$222,000
D)$208,000
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
68
Dummy activities have a duration equal to the:

A)slack on the critical path.
B)length of the predecessor.
C)length of the successor.
D)lag needed to preserve network logic.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
69
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 45 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 45 days?  </strong> A)$222,667 B)$243,675 C)$258,333 D)$272,500

A)$222,667
B)$243,675
C)$258,333
D)$272,500
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
70
The critical path of this network is: <strong>The critical path of this network is:  </strong> A)14. B)15. C)12. D)13.

A)14.
B)15.
C)12.
D)13.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
71
Use the information in the table (all times are in days)to determine the lowest extra cost for a 20-day project. <strong>Use the information in the table (all times are in days)to determine the lowest extra cost for a 20-day project.  </strong> A)$200 B)$130 C)$120 D)$100

A)$200
B)$130
C)$120
D)$100
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
72
The fastest completion time for this project is: <strong>The fastest completion time for this project is:  </strong> A)14. B)15. C)16. D)17.

A)14.
B)15.
C)16.
D)17.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
73
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the duration of the least expensive project possible? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the duration of the least expensive project possible?  </strong> A)60 weeks B)57 weeks C)53 weeks D)50 weeks

A)60 weeks
B)57 weeks
C)53 weeks
D)50 weeks
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
74
The AOA network described by this table needs: <strong>The AOA network described by this table needs:  </strong> A)zero dummy activities. B)one dummy activity. C)two dummy activities. D)three dummy activities.

A)zero dummy activities.
B)one dummy activity.
C)two dummy activities.
D)three dummy activities.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
75
The AOA network described by this table needs: <strong>The AOA network described by this table needs:  </strong> A)zero dummy activities. B)one dummy activity. C)two dummy activities. D)three dummy activities.

A)zero dummy activities.
B)one dummy activity.
C)two dummy activities.
D)three dummy activities.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
76
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 55 weeks? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 55 weeks?  </strong> A)$16,950 B)$15,000 C)$16,350 D)$15,350

A)$16,950
B)$15,000
C)$16,350
D)$15,350
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
77
What information is NOT included in the nodes for an AOA network?

A)label
B)early start time
C)late finish time
D)early finish time
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
78
Use the information in the table (all times are in days)to determine the lowest cost minimum completion time? <strong>Use the information in the table (all times are in days)to determine the lowest cost minimum completion time?  </strong> A)$1,040 B)$1,020 C)$740 D)$720

A)$1,040
B)$1,020
C)$740
D)$720
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
79
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project?  </strong> A)$234,000 B)$255,600 C)$248,333 D)$252,000

A)$234,000
B)$255,600
C)$248,333
D)$252,000
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
80
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 40 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 40 days?  </strong> A)$242,667 B)$255,600 C)$263,333 D)$272,500

A)$242,667
B)$255,600
C)$263,333
D)$272,500
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 110 flashcards in this deck.