expand icon
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

النسخة 13الرقم المعياري الدولي: 978-1439043271
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

النسخة 13الرقم المعياري الدولي: 978-1439043271
تمرين 24
Consider the following project network. Note that the normal or expected activity times are denoted T i , i = A, B, … ,I. Let x i = the earliest finish time for activity i. Formulate a linear programming model that can be used to determine the length of the critical path. Consider the following project network. Note that the normal or expected activity times are denoted T i , i = A, B, … ,I. Let x i = the earliest finish time for activity i. Formulate a linear programming model that can be used to determine the length of the critical path.
التوضيح
موثّق
like image
like image

Formulate a linear programming model as ...