( Process Analysis with Multiple Flow Units ) Consider a process consisting of five resources that are operated eight hours per day.The process works onthree different products,A,B,and C:
///MISSED IMG
Demand for the three different products is as follows: product A, 40 unts per day: product B,50 unts per day: and product C, 60 units per day.
Whatis the bottleneck? What is the flow rate for each flow unt assuming that demand must be served inthe mix described above (i e.• for every four units of A, there are five units of Band six units of C)?
///MISSED IMG
Demand for the three different products is as follows: product A, 40 unts per day: product B,50 unts per day: and product C, 60 units per day.
Whatis the bottleneck? What is the flow rate for each flow unt assuming that demand must be served inthe mix described above (i e.• for every four units of A, there are five units of Band six units of C)?
التوضيح
The output rate or the capacity of a pro...