Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are 1 week, and the quantities required are shown in parentheses. The master production schedule calls for the completion of 100 As in week 4 and 50 in week 5. There are 300 Bs scheduled to be received in week 1 and 200 Ds in week 3. There are also 20 As available.



التوضيح
Low-level codes:
The low-level code mea...