Fig.7.2 Which one of the following statements regarding Figure 7.2 is TRUE?
A) Activity S cannot finish until activity T finishes.
B) Activity T cannot begin until activity U is completed.
C) Activity U cannot begin until activities S and T have been completed.
D) Activity V cannot begin until activity S has been completed.
Correct Answer:
Verified
Q23: To obtain the latest start and latest
Q24: Figure to accompany Table 7.1
Q29: A Gantt chart is a project schedule
Q32: The earliest start time for an activity
Q33: A project has three paths.A-B-C has a
Q35: Activity slack is defined as:
A) latest start
Q38: Figure to accompany Table 7.1
Q41: Table 7.5 Q43: Why do managers want to know the Q55: Table 7.4