Multiple Choice
Table 2.12
-Using Table 2.12,if the project's normal earliest completion time is to be reduced by two weeks,what is the minimum additional cost that will be incurred in achieving this two-week reduction?
A) less than or equal to $1,000
B) greater than $1,000 but less than or equal to $1,500
C) greater than $1,500 but less than or equal to $2,000
D) greater than $2,000
Correct Answer:
Verified