Two Projects Have the Following NPVs and Standard Deviations A Person Who Selects Project a Over Project B Is

Question 18

Multiple Choice

Two projects have the following NPVs and standard deviations:  Project A Project B NPV 200200 Standard deviation 75100\begin{array} { | r | c | c | } \hline & \text { Project } A & \text { Project } B \\\hline \text { NPV } & 200 & 200 \\\hline \text { Standard deviation } & 75 & 100 \\\hline\end{array} A person who selects project A over project B is


A) risk seeking.
B) risk indifferent.
C) risk averse.
D) None of the above

Correct Answer: