A partially solved PERT problem is detailed in the table below.Times are given in weeks.
a.Calculate the expected time for each activity.Enter these values in the appropriate column in the table above.
b.Which activities form the critical path?
c.What is the estimated time of the critical path?
d.What are the project variance and the project standard deviation?
e.What is the probability of completion of the project after week 40?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q40: Describe the differences between a Gantt chart
Q66: What are the earliest activity start time
Q104: Briefly describe the concept of cost/time trade-off
Q107: How is the expected completion time of
Q109: Three critical path activities are candidates for
Q114: Describe in words how to calculate a
Q115: Consider the network described in the table
Q116: Three critical path activities are candidates for
Q117: Pirmin's Bike Shop is behind on a
Q118: A network consists of the following list.Times
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents