Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.
A) One;$400
B) One;$6,800
C) Two;$1,000
D) Two;$5,000
E) One or two should be crashed;$1,400
Correct Answer:
Verified
Q60: The critical path for the network activities
Q61: A local project being analyzed by PERT
Q62: Which of the following statements regarding time-cost
Q63: A project whose critical path has an
Q65: _ is an organization formed to ensure
Q66: Two critical path activities are candidates for
Q66: A project whose critical path has an
Q69: If an activity whose normal duration is
Q78: If an activity whose normal duration is
Q97: Contract requirements state that a project must
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents