Because the critical path is the shortest path through a network,it defines the project completion time.
Correct Answer:
Verified
Q26: A project's duration can be reduced by
Q27: Crashing activities with positive slack reduces a
Q28: Which of the following is not a
Q29: Unlike PERT,CPM incorporates probabilistic time estimates into
Q30: The project management process encompasses
A)planning.
B)scheduling.
C)control.
D)All of these
Q32: A(n)_ breaks down a project into components,subcomponents,activities,and
Q33: The _ is a document that provides
Q34: Which of the following is not a
Q35: With an activity-on-node (AON)network diagram,the nodes indicate
Q36: PERT stands for program enterprise and resource