Aggregate planning and scheduling differ in that:
A) The former ensures capacity is efficiently used whereas the latter is the acquisition of resources.
B) The former is short term in nature while the latter is medium term.
C) The former is first in the hierarchy of capacity planning decisions and the latter is last.
D) The former deals with acquiring resources and the latter deals with allocating resources.
Correct Answer:
Verified
Q11: In the language of constraint management,inventory is:
A)The
Q14: Which of the following questions is NOT
Q15: The SPT rule does a better job
Q17: Scheduling often deals with which three conflicting
Q18: Critical Ratio is:
A)The ratio between processing time
Q19: Finite capacity scheduling assumes which of the
Q19: Scheduling systems need NOT answer which of
Q20: According to Goldratt:
A)An hour lost at the
Q21: First come,first served is widely used in
Q23: Finite Capacity Scheduling can be used to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents