A firm has prepared the following binary integer program to evaluate a number of potential new capital projects. The firm's goal is to maximize the net present value of their decision while not spending more than their currently available capital.
Max 100x1 + 120x2 + 90x3 + 135x4
s.t. 150x1 + 200x2 + 225x3 + 175x4 ? 500 {Constraint 1}
X1 + x2 + x3 + x4 ? 2 {Constraint 2}
X2 + x4 ? 1 {Constraint 3}
X2 + x3 ? 1 {Constraint 4}
X1 = x4 {Constraint 5}
Which of the constraints ensures that at least two of the potential projects will be selected?
A) Constraint 1
B) Constraint 2
C) Constraint 3
D) Constraint 4
E) Constraint 5
Correct Answer:
Verified
Q51: Note: This problem requires the use
Q52: Note: This problem requires the use
Q53: Note: This problem requires the use
Q54: The university is scheduling cleaning crews
Q55: The university administration would like to
Q57: The university administration would like to
Q58: A new pizza restaurant is moving
Q59: The university administration would like to
Q60: Note: This problem requires the use
Q61: The university is scheduling cleaning crews
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents