Assume that we are using 0-1 integer programming model to solve a capital budgeting problem and xj = 1 if project j is selected and xj = 0, otherwise.
The constraint (x1 + x2 + x3 + x4 = 2) means that ________ out of the ________ projects must be selected.
A) exactly 1, 2
B) exactly 2, 4
C) at least 2, 4
D) at most 1, 2
Correct Answer:
Verified
Q97: The Exorbitant Course Fees. The $75
Q98: The Exorbitant Course Fees. The $75
Q99: Future Plastics manufactures plastic products for industrial
Q100: Future Plastics manufactures plastic products for industrial
Q101: The Wiethoff Company has a contract
Q102: In a 0-1 integer programming model, if
Q103: The Wiethoff Company has a contract
Q104: In a 0-1 integer programming model, if
Q106: In formulating a mixed integer programming problem,
Q107: The Wiethoff Company has a contract
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents