When a Contractor Determines That a Contract Will Result in an Overall

Question 49

Multiple Choice

When a contractor determines that a contract will result in an overall loss,when should that loss be recognized within the completed-contract and percentage-of-completion methods? Completed-Contract Percentage-of-Completion


A) Immediately Over the remainder of the contract
B) At the completion of the contract At the completion of the contract
C) At the completion of the contract Immediately
D) Immediately Immediately