Solved

Which Is NOT Part of the Requirements Gathering Process

Question 22

Multiple Choice

Which is NOT part of the requirements gathering process?


A) Is used for building political support for the project
B) Is used for establishing trust and rapport between the project team and users
C) Determining 'if we build it, they will come'
D) Key stakeholders need to be included
E) Involving people who may feel slighted if their input is not considered

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents