Poole Contractors makes a contract with Delta Resources to pay $50,000 for the supply of 500 truckloads of sand within a week. Delta Resources delivers the sand two days after the contract was made, and Poole Contractors pays it $50,000 promised in the contract. This is an instance of ________.
A) substantial performance
B) material breach
C) minor breach
D) strict performance
Correct Answer:
Verified
Q3: Anticipatory repudiation occurs when one contracting party
Q4: Which of the following terms refers to
Q5: Which of the following constitutes material breach?
A)
Q6: When does a minor breach occur?
A) when
Q7: _ is a situation in which a
Q9: Strict performance by a party discharges that
Q10: When a party commits an anticipatory breach,
Q11: Which of the following statements is true
Q12: A nonbreaching party cannot rescind the contract
Q13: Which of the following statements is true
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents