The Critical Path Is the Path Through the Project Network

Question 41

Multiple Choice

The critical path is the path through the project network in which none of the activities have _______, that is, the path for which ________ for all activities in the path.


A) sack / AS = FS and FE = FL
B) compression / CS = LS and CE = LF
C) better timed / LS = ES and LF = EF
D) crashed / SE = SL and FE = FL
E) slack / ES = LS and EF = LF