Refer to the above data. If Riverview applies overhead using a predetermined rate based on labor-hours, what amount of overhead will be assigned to a unit of output which requires 0.5 machine hours and 0.25 labor hours to complete?
A) $16.00.
B) $30.00.
C) $20.00.
D) Some other amount.
Correct Answer:
Verified