Question 54

Multiple Choice

Which two costs are compared in a performance report that uses activity flexible budgeting?


A) budgeted costs for actual activity-usage levels and the actual activity costs
B) actual activity costs and budgeted overhead costs
C) actual overhead costs and the budgeted activity costs for actual activity-usage levels
D) static activity budget costs and the budgeted activity costs for the actual activity-usage levels

Correct Answer: