Benitez Company Currently Outsources a Relay Switch That Is a Component

Question 34

Multiple Choice

Benitez Company currently outsources a relay switch that is a component in one of its products.The switches cost $20 each.The company is considering making the switches internally at the following projected annual production costs:  Unit-level material cost $3 Unit-level labor cost $2 Unit-level overhead $1 Batch-level set-up cost (5,000 units per batch)  $25,000 Product-level supervisory salaries $37,500 Allocated facility-level costs $20,000\begin{array}{ll}\text { Unit-level material cost } & \$3 \\\text { Unit-level labor cost } & \$2 \\\text { Unit-level overhead } & \$1 \\\text { Batch-level set-up cost (5,000 units per batch) } & \$ 25,000 \\\text { Product-level supervisory salaries } & \$ 37,500 \\\text { Allocated facility-level costs } & \$ 20,000\end{array} The company expects an annual need for 5,000 switches.If the company makes the product,it will have to utilize factory space currently being leased to another company for $1,500 a month.If the company decides to make the parts,total costs will be:


A) $10,500 more than if the switches are purchased.
B) $27,000 less than if the switches are purchased.
C) $20,000 less than if the switches are purchased.
D) $30,500 more than if the switches are purchased.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents