What Is the Slack Time for Activity E A) 0 Days
B) 1 Day
C) 2 Days
D)

Question 81

Multiple Choice

What is the slack time for activity E?  Early  Early  Late  Late \cline57 Task  Predecessor  Duration  Start  Finish  Start  Finish A8BA14CA238DC,B62326EC32FD,E3238\begin{array} { | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\\cline { 5 - 7 } \text { Task } & \text { Predecessor } & \text { Duration } & \text { Start } & \text { Finish } & \text { Start } & \text { Finish } \\\hline \mathrm { A } & - & 8 & & & & \\\hline \mathrm { B } & \mathrm { A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & 23 & 8 & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & 23 & & 26 & \\\hline \mathbb { E } & \mathrm { C } & & & 32 & & \\\hline \mathbb { F } & \mathrm { D } , \mathrm { E } & & 32 & & & 38 \\\hline\end{array}


A) 0 days
B) 1 day
C) 2 days
D) 4 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents