A project manager is using the payback method to make the final decision on which project to undertake.The company has a 10% required rate of return and expects a 4% rate of inflation for the following five years.What is the discounted payback of a project that has cash flows as shown in the table?
A) 3.4 years
B) 2.6 years
C) 5.0 years
D) 4.2 years
Correct Answer:
Verified
Q64: The systematic process of selecting,supporting,and managing a
Q68: The most important thing to remember when
Q69: An options model could be used when
Q70: Inatech is contemplating two different projects
Q70: The concept of project portfolio management holds
Q72: Options models are used to assist in
Q74: What are options models and when should
Q75: What two simple rules should be followed
Q78: Evaluating projects in terms of their strategic
Q79: A project that is exceptionally risky might
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents