Solved

Exhibit 15

Question 60

Essay

Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity
Days Required
Predecessor Activities
A 1 −
B 4 A
C 3 B
D 3 C
E 2 B
F 4 E
G 2 D,F
-Refer to Exhibit 15.4.The following spreadsheet was developed to determine the earliest start times and latest start times for the project.Based on the data in the spreadsheet,which activities are on the critical path?
ABCDEFGHI1 Activity  Description  Predecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 1010103 B  Activity B  A 4151504 C  Activity C  B 3585805 D  Activity D  C 381181106 E  Activity EB2575707 F Activity F E471171108 G  Activity G  D, F 2111311130\begin{array}{|r|r|r|r|r|r|r|r|r|r|}\hline&A&B&C&D&E&F&G&H&I\\\hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } &\text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 1 & 0 & 1 & 0 & 1 &0\\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 4 & 1 & 5 & 1 & 5 &0 \\\hline 4 & \text { C } & \text { Activity C } & \text { B } & 3 & 5 & 8 & 5 & 8 &0\\\hline 5 & \text { D } & \text { Activity D } & \text { C } & 3 & 8 & 11 & 8 & 11 &0 \\\hline 6 & \text { E } & \text { Activity } \mathrm{E} & \mathrm{B} & 2 & 5 & 7 & 5 & 7 &0\\\hline 7 & \mathrm{~F} & \text { Activity F } & \mathrm{E} & 4 & 7 & 11 & 7 & 11 &0 \\\hline 8 & \text { G } & \text { Activity G } & \text { D, F } & 2 & 11 & 13 & 11 & 13&0 \\\hline\end{array}

Correct Answer:

verifed

Verified

All activities are on the crit...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents