A company wants to develop a project using PERT to modify one of their products which has poor sales.They have determined the following activities, precedence relationships and time estimates in days for the project: a.What is the expected duration for activity a?
b.What is the variance for activity d?
c.How many paths are there in the network?
d.What is the earliest start (ES) time for activity e?
e.What is the slack in days for activity b?
f.What is the critical path?
g.What is the duration of the critical path in days?
h.What is the standard deviation of the critical path?
i.What is the probability that the project will take longer than 28 weeks to complete?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q49: A manufacturing company is planning to use
Q52: Explain the stages of the project life
Q55: A company has a PERT project with
Q56: Consider the project network and data shown
Q57: The network below represents a project being
Q58: A company has developed a project using
Q59: A company has used PERT for a
Q83: List at least six principal factors (contributors)
Q97: Describe how a project fits into each
Q99: Define critical path and explain how it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents