An Assembly Line with 28 Activities Is to Be Balanced

Question 71

Essay

An assembly line with 28 activities is to be balanced.The total amount of time required for all 28 activities is 39 minutes.The longest activity is 2.2 minutes and the shortest is 0.8 minutes.The line will operate for 450 minutes per day.Using a cycle time of 60 seconds, determine an assembly line balance by selecting the longest task available.Compute the total idle time, and assembly line efficiency.

Correct Answer:

verifed

Verified

Station 1: A, B
Station 2: C, D
Station ...