Question 83

Essay

A company that makes construction equipment is exploring different lot sizing approaches to its master requirement planning (MRP) schedule: lot-for-lot (LFL), fixed-order quantity (FOQ) using the EOQ, and periodic-order quantity (POQ). It costs $100 to set up the production line to produce hydraulic jacks, and the carrying cost per unit per week is $1. Annual demand is expected to be 1550 jacks. For planning purposes, the company uses a 50-week work year and disregards the effects of initial inventory and safety stock. The net requirements for hydraulic jacks for the next six weeks are:
 Week 123456 Net Requirements 353040104030\begin{array}{|l|l|l|l|l|l|l|}\hline \text { Week } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Net Requirements } & 35 & 30 & 40 & 10 & 40 & 30 \\\hline\end{array}
a. Using a LFL approach, what is the lot size in week 3?
b. What is the total cost for the LFL method?
c. What is the fixed-order quantity (FOQ) using the EOQ approach?
d. What is the beginning inventory for week 5 using the FOQ approach?
e. What is the total cost using the FOQ method?
f. What is the periodic-order quantity?
g. What is the ending inventory for week 4 using the POQ method?
h. What is the total cost using the POQ approach?

Correct Answer:

verifed

Verified

a. 40; b. $600; c. 7...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents