Question 66

Multiple Choice

Answer the following questions using the information below:
Tiger O'Reilly planned to use $85 of material per unit but actually used $82 of material per unit,and planned to make 1200 units but actually made 1000 units.
-The sales-volume variance is:


A) $2400 favourable.
B) $2000 favourable.
C) $17 000 unfavourable.
D) $14 000 unfavourable.