Mel Torme,sales manager for Hokque,Inc.has received numerous customer complaints about the length of time it takes to receive an order.He has gathered the following information from a recent order to help him understand the issue.
Hours Required
Process customer order 1
Wait for direct materials to arrive 24
Fabrication of parts 30
Move parts to assembly area 8
Wait for machine time 45
Assembly of parts 24
Move parts to finishing department 3
Wait for machine time 24
Finishing
a.Calculate the delivery cycle time for the order.
b.Calculate the manufacturing cycle time for the order.
c.Calculate the value-added time for the order.
d.Calculate the manufacturing cycle efficiency.
Correct Answer:
Verified
Q159: Financial measures alone do not capture all
Q160: Morgan Company has provided you with the
Q161: Another way of evaluating a company's performance
Q162: Because the organization's vision and strategy lie
Q162: Explain the difference between a leading indicator
Q162: Explain the difference between a leading indicator
Q163: Customers typically have expectations for how quickly
Q164: You have been assigned to a team
Q168: Traditionally,organizations have evaluated their performance using only
Q169: Ledbetter Industries makes and sells two types
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents