A manager has decided that an activity has a pessimistic estimate of 15 days,a most-likely estimate of 6 days,and an optimistic estimate of 3 days The expected duration of this activity is 6 days
Correct Answer:
Verified
Q30: The mean critical path is the path
Q31: The slack of any activity is the
Q32: When calculating the probability that a project
Q33: A normal distribution is usually used to
Q33: In order to determine the probability of
Q34: The latest finish of an activity is
Q36: The standard deviation of the critical path
Q37: A forward pass is the process of
Q38: Crashing an activity will always reduce the
Q40: PERT/Cost is a systematic procedure to help